M ISSION C RITICAL HVAC COLLABORATION - - PowerPoint PPT Presentation

m ission c ritical hvac
SMART_READER_LITE
LIVE PREVIEW

M ISSION C RITICAL HVAC COLLABORATION - - PowerPoint PPT Presentation

D ESIGN -B UILD FOR M ISSION C RITICAL F ACILITIES Case Study: California ISO Iron Point Facility Folsom, CA COLLABORATION CERTAINTY M ISSION P OSSIBLE Mission Critical Headquarters Delivered Early


slide-1
SLIDE 1

DESIGN-BUILD FOR MISSION CRITICAL FACILITIES

Case Study:

California ISO Iron Point Facility

Folsom, CA

slide-2
SLIDE 2

COLLABORATION CERTAINTY

MISSION POSSIBLE

 Mission Critical Headquarters  Design-Build Delivery  Delivered Early  Delivered Under Budget

slide-3
SLIDE 3

COLLABORATION CERTAINTY

PRESENTERS

Katie Twomey Clark Construction Principal in Charge Blythe Shannon Clark Construction Design Manager / Sr. PM Hector Alvarez California ISO Director of Campus Operations Gus Fischer Dreyfuss and Blackford Project Architect Phil Ball Frank M. Booth Engineer of Record Caroline Fenlon-Harding WSP Flack + Kurtz Engineer of Record

slide-4
SLIDE 4

OWNER: CALIFORNIA ISO CONSTRUCTION MANAGER: VANIR DESIGN-BUILDER: CLARK CONSTRUCTION DESIGNER: DREYFUSS & BLACKFORD STRUCTURAL ENGINEER: BUEHLER & BUEHLER MECHANICAL & PLUMBING ENGINEER: FRANK M. BOOTH ELECTRICAL ENGINEER: WSP FLACK + KURTZ ELECTRICAL SUBCONTRACTOR (DESIGN-ASSIST): HELIX ELECTRIC COMMISSIONING AGENT: GLUMAC

COLLABORATION CERTAINTY

PROJECT TEAM

slide-5
SLIDE 5

COLLABORATION CERTAINTY

PROJECT MISSION

slide-6
SLIDE 6

COLLABORATION CERTAINTY

PROJECT MISSION

slide-7
SLIDE 7

COLLABORATION CERTAINTY

PRESENTATION AGENDA

Major Topics

  • Sustainability
  • MEP Design and Innovation
  • Innovation to Achieve Early Completion
  • How We Did It
slide-8
SLIDE 8

COLLABORATION CERTAINTY

COLLABORATIVE APPROACH

Team Formation and Owner Groundwork

slide-9
SLIDE 9

COLLABORATION CERTAINTY

SUSTAINABILITY

LEED Project History

  • LEED NC v2.2 – (69 Possible Points)
  • Project Conception - Owner initially had no criteria
  • Pre-Design Build – Owner targeted LEED Silver minimum
  • Design-Build RFP required a target of LEED Gold +10 points (49 points)
  • Project enhancements targeted LEED Platinum (52 points minimum)
  • Final LEED awarded 55 of 57 points attempted
slide-10
SLIDE 10

COLLABORATION CERTAINTY

SUSTAINABILITY

  • Sustainable Sites (10 of 14 Points)
  • Water Efficiency (5 of 5 Points)
slide-11
SLIDE 11

COLLABORATION CERTAINTY

SUSTAINABILITY

  • Energy and Atmosphere (14 of 17 Points)
slide-12
SLIDE 12

COLLABORATION CERTAINTY

SUSTAINABILITY

  • Materials and Resources (7 of 13 Points)
slide-13
SLIDE 13

COLLABORATION CERTAINTY

SUSTAINABILITY

  • Indoor Environmental Quality (14 of 15 Points)
  • Innovation (5 of 5 Points)
slide-14
SLIDE 14

COLLABORATION CERTAINTY

WATER EFFICIENCY & SUSTAINABILITY

Cooling Towers Water Closet Urinal Lavatory Condensate

Drinking Fountain

Shower

Reclaimed Water Storage Tank Graywater Storage Tank

Subsurface Irrigation

Estimated Annual Inflow : 2,800,000 gal Estimated Annual Re-Use: 2,800,000 gal Estimated Annual Inflow : 2,340,000 gal Estimated Annual Re-Use: 2,200,000 gal Estimated Overflow to S.S.: 160,000 gal Reclaimed Water for Sew age Conveyance (820,000 gal/yr) Grayw ater Production From Building Fixtures (360,000 gal/yr) Waste Water Production (2,800,000 gal/yr)

(2,200,000 gal/yr)

Overflow

slide-15
SLIDE 15

COLLABORATION CERTAINTY

HVAC COOLING PRODUCTION

slide-16
SLIDE 16

COLLABORATION CERTAINTY

MISSION CRITICAL HVAC

slide-17
SLIDE 17

COLLABORATION CERTAINTY

HVAC AIR DISTRIBUTION

slide-18
SLIDE 18

COLLABORATION CERTAINTY

MISSION CRITICAL - ELECTRICAL

Tier Levels

TIER LEVEL REQUIREMENTS

1

  • Single non-redundant distribution path serving the IT equipment
  • Non-redundant capacity components
  • Basic site infrastructure guaranteeing 99.671% availability

2

  • Fulfills all Tier 1 requirements
  • Redundant site infrastructure capacity components guaranteeing 99.741% availability

3

  • Fulfils all Tier 1 & Tier 2 requirements
  • Multiple independent distribution paths serving the IT equipment
  • All IT equip must be dual-powered and fully compatible with the topology of a site's

architecture

  • Concurrently maintainable site infrastructure guaranteeing 99.982% availability

4

  • Fulfils all Tier 1, Tier 2 and Tier 3 requirements
  • All cooling equipment is independently dual-powered, including chillers and HVAC
  • Fault tolerant site infrastructure with electrical power storage and distribution facilities

guaranteeing 99.995% availability

slide-19
SLIDE 19

COLLABORATION CERTAINTY

DATA CENTER ELECTRICAL SYSTEM

slide-20
SLIDE 20

COLLABORATION CERTAINTY

MISSION CRITICAL - ELECTRICAL PLANT

slide-21
SLIDE 21

COLLABORATION CERTAINTY

MISSION CRITICAL - PRIMARY SERVICE

  • (2) Services, Switchgear
  • 12,000V, 3ph, 3W
  • Utility: SMUD
  • Manufacturer: Square D
slide-22
SLIDE 22

COLLABORATION CERTAINTY

MISSION CRITICAL - UNIT SUBSTATIONS

  • (2) 2,000kVA for UPS system
  • (2) 2,000kVA for HVAC system
  • Main-Tie-Tie-Main (OPR)
  • ATO
  • Manufacturer: Square D
slide-23
SLIDE 23

COLLABORATION CERTAINTY

GENERATORS

  • (2) @ 2,500kW
  • 277/480V, 3ph, 4W
  • Hospital Grade Silencer
  • 72 hours of fuel
  • NEC 702
slide-24
SLIDE 24

COLLABORATION CERTAINTY

PERMANENT LOADBANK

  • 2,500kW
  • Shunt trip
  • Shared with Generator and UPS
slide-25
SLIDE 25

COLLABORATION CERTAINTY

MISSIONCRITICAL-PARALLELINGSWITCHGEAR

  • Physically separate, connected by a tie
  • 277/480V, 3ph, 4W
slide-26
SLIDE 26

COLLABORATION CERTAINTY

UPS + TIE CABINET

slide-27
SLIDE 27

COLLABORATION CERTAINTY

MISSION CRITICAL - UPS

  • (2) 750kW UPS on both sides
  • Hot-sync bypass
  • Manufacturer: Powerware
slide-28
SLIDE 28
  • Manual Tie with Key Sequence
  • Enables bypass and transferring load to redundant UPS

COLLABORATION CERTAINTY

MISSIONCRITICAL-UPS OUTPUTSWITCHGEAR

slide-29
SLIDE 29

COLLABORATION CERTAINTY

COMPARTMENTEDHVAC/ELECTRICALSERVICES

RPP “A” RPP “B” PDU “A” PDU “B”

slide-30
SLIDE 30

COLLABORATION CERTAINTY

MISSION CRITICAL - CONTROL ROOM

  • Consoles
  • Video wall
  • Single-corded equipment

Dual cord power strip

slide-31
SLIDE 31

COLLABORATION CERTAINTY

LOAD SEQUENCING DIAGRAMS

slide-32
SLIDE 32

COLLABORATION CERTAINTY

LOAD SEQUENCING DIAGRAMS

slide-33
SLIDE 33

COLLABORATION CERTAINTY

INNOVATIONS FOR EARLY DELIVERY

Phased Permitting

2 Permits 2 Permits 3 Permits Site: 4 Separate Permits

slide-34
SLIDE 34

COLLABORATION CERTAINTY

INNOVATIONS FOR EARLY DELIVERY

Integrated Steel Design & Delivery

  • Integrated Steel Design and

Delivery (ISDD) is collaborative design, detailing, fabrication and delivery of structural steel

  • Direct Engineer-Detailer-

Fabricator integration

  • Only 17 Steel RFI’s
  • 6 months from project award

to steel erection including design and fabrication

slide-35
SLIDE 35

COLLABORATION CERTAINTY

INNOVATIONS FOR EARLY DELIVERY

Traditional Workflow

slide-36
SLIDE 36

COLLABORATION CERTAINTY

INNOVATIONS FOR EARLY DELIVERY

Modified Workflow

slide-37
SLIDE 37

COLLABORATION CERTAINTY

MEETING OWNER NEEDS

Phased Occupancy

Public Wing

slide-38
SLIDE 38

COLLABORATION CERTAINTY

HOW WE DID IT

THE DESIGN-BUILD EXPERIENCE

Collaboration Respect Trust

slide-39
SLIDE 39

COLLABORATION CERTAINTY

“MISSION ACCOMPLISHED”

Cutting Edge Security Highly Sustainable “Feels like home”