SLIDE 1 Luther Road Habitat Restoration Project
Flood Resiliency, Habitat Creation and Community Building
ESA is where solutions and service meet.
Joe Richards, PE, CWRE jrichards@esassoc.com
SLIDE 2 Presentation Outline
- Johnson Creek Watershed and the Project Site
- Design, Permitting and Construction
- Monitoring
- First Winter 2014 – 2015
- Second Winter 2015 – 2016
- Second Summer 2016
- Third Winter 2016 – 2017
- Lessons Learned
SLIDE 3 Project Team
Portland Department of Transportation Portland Parks and Recreation Department of State Lands Oregon Department of Fish and Wildlife US Army Corps of Engineers National Marine Fisheries Service
Implementation Partners Funding Partners
SLIDE 4
THE JOHNSON CREEK WATERSHED AND THE PROJECT SITE
SLIDE 5
Project Site
Johnson Creek Watershed
SLIDE 6
Project Vicinity
SLIDE 7
Site Map 2013
SLIDE 8
1920 2007
T The 76-inch Monolithic Trunk Sewer and Manhole were exposed due to Vertical Incision by Johnson Creek.
The Problem with the Interceptor Sewer
SLIDE 9 Coho Salmon, Chinook Salmon, Steelhead, Rainbow Trout and Lamprey
Source: Washington Department of Fish and Wildlife
SLIDE 10
Flooding 12-3-2007
SLIDE 11
DESIGN DEVELOPMENT
SLIDE 12 Project Goals
- 1. Protect Public Health
- Protect sewer crossing and manhole from stream forces
- Protect private property from erosion and flooding
- Treat stormwater from existing industrial outfalls
- 2. Restore Johnson Creek
- Enhance stream process, reconnect floodplains and increase
stream complexity within project area
- Improve fish and macro invertebrate habitat
- Add high flow refuge and improve fish passage
- 3. Protect Natural Areas
- Remove nonnative vegetation & enhance the riparian corridor
- 4. Create a Community Resource
- Integrate park and natural area developments together
- Provide community educational opportunities
SLIDE 13
Historical Aerials
1939 Aerial 2,365’ Main Channel 972’ Secondary Channel
1977 Aerial 2,203’ Main Channel
SLIDE 14
Geotechnical Exploration
SLIDE 15
Designing the Riffle Pool Sequence
SLIDE 16
Large Woody Debris (LWD)
SLIDE 17
Hydraulic Modeling
Existing Conditions Model Proposed Conditions Model
SLIDE 18
PERMITTING AND PROPERTY ACQUISITION
SLIDE 19 Permitting Summary
Listed Species: Steelhead, Coho & Chinook salmon
- Clackamas County Land Use Review
- NPDES 1200c Permit for Construction Activities
- COE/DSL Joint Permit for Removal and Fill
– Individual Permit (timeframes expanded to 10-years to support project construction and adaptive management).
- DEQ 401 WQ Certification
- FEMA CLOMR/LOMR
- ODFW Fish Salvage Permit
– In-Water Work Window: July 15th to August 31st
SLIDE 20
Sewer and Channel Change Easements
SLIDE 21
Industrial Property Easements
SLIDE 22 CONSTRUCTION
The engineers estimate was $3,512,683 which is near the average of the 10 bids received for the project. Colf Construction, LLC was the low bidder at $2,125,604 and was awarded the contract.
SLIDE 23
Invasive Species Management
SLIDE 24
Contaminated Media
SLIDE 25
Stream Diversion Construction
SLIDE 26
Site Map Spring 2014
SLIDE 27
Fish Salvage Complete
July 22 to July 24 Salvage Counts
Native Fish Total: 5216 Non-Native Fish Total: 14
SLIDE 28
Mass Grading
76,000 cy of cut, 38,000 cy of fill 38,000 cy of haul off. 8,050 cy Contaminated (on-site disposal).
SLIDE 29
Condition of the Interceptor Crossing
SLIDE 30
Interceptor Sewer Rehabilitation Plan
SLIDE 31
Installing LWD
SLIDE 32
Soil Wrapped Lifts
SLIDE 33
Constructing Streambed
SLIDE 34
Stream Diversion and Fish Salvage: September 17, 2014
SLIDE 35 Project Fish Salvage Statistics
Native Species
7/22/2014 7/23/2014 7/24/2014 8/28/2014 9/17/2014 Total
- No. Injured Cond. at Release
Mortality Rainbow/Steelhead 12 2 33 7 31 92 Stable, no visible harm 7 Cutthroat Trout 9 9 Stable, no visible harm Largescale Sucker 6 9 33 48 Stable, no visible harm Redside Shiner 576 359 1217 797 62 3116 Stable, no visible harm 105 Golden Shiner 1 1 Stable, no visible harm Cottids sp. 692 842 923 263 158 2959 Stable, no visible harm 81 Speckled Dace 122 43 121 108 231 692 Stable, no visible harm 67 Longnose Dace 1 3 7 Stable, no visible harm 3 Pikeminnow 2 7 10 Stable, no visible harm 1 Pacific Lamprey, adult 1 1 2 Stable, no visible harm Lamprey, Ammocetes 89 25 131 105 12 362 Stable, no visible harm Crayfish, spp. 156 522 361 266 175 1492 Stable, no visible harm 12 Sub total (native fish): 1499 1271 2446 1321 672 276 Total Native Fish: 7485 Non-Native Species
7/22/2014 7/23/2014 7/24/2014 8/28/2014 9/17/2014 Total
- No. Injured Cond. at Release
Mortality Bluegill 3 3 Stable, no visible harm Pumpkinseed 4 6 27 37 Stable, no visible harm Brown Bullhead 1 1 Stable, no visible harm Crappie sp. 1 1 Stable, no visible harm Sub total (invasive fish): 4 9 1 28 Total Invasive Fish: 42
SLIDE 36
MONITORING
SLIDE 37
738 cfs (1-17-15) 754 cfs,(3-15-15)
2015 Flowrates
First Winter 2015
SLIDE 38
The Interceptor Crossing
First Winter 2015
SLIDE 39
Bank Protection
First Winter 2015
SLIDE 40
Water Quality Facility
First Winter 2015
SLIDE 41
Connected Floodplains Provide Refuge
First Winter 2015
SLIDE 42
A Community Resource
First Winter 2015
SLIDE 43
Site Map Spring 2015
SLIDE 44 Wettest December, wettest month ever in Portland in 75 years
Previous Records for Portland International Airport (PIA)
- December 1996 Total = 13.35 inches PIA
- 2.59 inches in 24 hours on December 12-13, 1977.
New Records for Portland International Airport
- December 2015 Total = 16.18 inches PIA
- 2.67 inches in 24 hours PIA December 7, 2015
Johnson Creek Watershed -Gresham Fire Station (GFS)
- December 2015 Total = 18.62 inches GFS
- 3.47 inches in 24 hours GFS, December 7, 2015
SLIDE 45
2,740 cfs (12-7-15)
Second Winter 2015
2015 Flowrates
SLIDE 46
Second Winter 2015
Interceptor Crossing
SLIDE 47
Second Winter 2015
Water Quality Facility
SLIDE 48
Second Winter 2015
Bottom of Project Site
SLIDE 49
Second Winter 2015
Bottom of Project Site
SLIDE 50
Post Flood (Video)
SLIDE 51
Site Map Spring 2016
SLIDE 52
Channel Comparison 2015 to 2016
SLIDE 53
Summer 2016 – BES Monitoring
SLIDE 54
DSL Years 1 and 2 Monitoring by BES
SLIDE 55 DSL Years 1 and 2 Monitoring by BES
Instream Habitat Assessment Summary Overall, the Luther Road habitat restoration project should be deemed a success. The condition of habitat in the reach prior to the project was poor, but it is now
- n a trajectory toward very high quality.
The abundance and distribution of pool habitat in the reach is a major asset. Three backwater pools were mapped this year. These habitats are highly valuable year-round, as they provide low energy areas for fish to feed and rest. Greater quantities of wood within the pools will provide the needed cover habitat while creating the hydraulic energy necessary to moves sediment out of the pools and maintain pool depth.
SLIDE 56
Geomorphic Monitoring
SLIDE 57 Geomorphic Monitoring
Sediment Mass Balance The mass balance analysis produced a net fill in the project area of 1,135 cubic yards of sediment. This material, which represents approximately 20% of the total volume of aggraded material in the project area, must have come from upstream reaches. Key Adaptive Management Areas
- 1. Protection of the sewer Interceptor crossing,
- 2. Grade control at the upstream end of Reach C to protect
against the potential for headcut migration, and
- 3. Right bank stabilization along the avulsed channel to
protect the overlook structure.
SLIDE 58
Fall 2016 – Pre Winter Pictures
SLIDE 59
Future Park Area – Meadow Habitat
Fall 2016 – Before Third Winter
SLIDE 60
Stable Riffles
Fall 2016 – Before Third Winter
SLIDE 61
Lents Interceptor Sewer Crossing
Fall 2016 – Before Third Winter
SLIDE 62
Lents Interceptor Sewer Crossing
Fall 2016 – Before Third Winter
SLIDE 63
Large Bend with LWD Structures
Fall 2016 – Before Third Winter
SLIDE 64
Side Channel
Fall 2016 – Before Third Winter
SLIDE 65
Floodplain Bench
Fall 2016 – Before Third Winter
SLIDE 66
Water Quality Facility
Fall 2016 – Before Third Winter
SLIDE 67
Interpretive Features
Fall 2016 – Before Third Winter
SLIDE 68
Floodplain Restoration
Fall 2016 – Before Third Winter
SLIDE 69
Side Channel
Fall 2016 – Before Third Winter
SLIDE 70
Connected Off Channel Wetland
Fall 2016 – Before Third Winter
SLIDE 71
Return Flow to Oxbow Feature
Fall 2016 – Before Third Winter
SLIDE 72
Community Gathering Place
Fall 2016 – Before Third Winter
SLIDE 73
Winter 2016
SLIDE 74
Lents Interceptor Sewer Crossing
11-25-16 (600 cfs) November 2016 –Third Winter
SLIDE 75
Lents Interceptor Sewer Crossing (Video)
11-25-16 (600 cfs) November 2016 –Third Winter
SLIDE 76
Floodplain Connections
(300 cfs) 11-24-16 (600 cfs) 11-25-16 November 2016 –Third Winter
SLIDE 77
Reconnected Floodplains (Video)
11-25-16 (600 cfs) November 2016 –Third Winter
SLIDE 78
Leaving the Project Site
11-25-16 (600 cfs)
SLIDE 79 Revisit Project Goals
- 1. Protect Public Health
- Protect sewer crossing and manhole from stream forces
- Protect private property from erosion and flooding
- Treat stormwater from existing industrial outfalls
- 2. Restore Johnson Creek
- Enhance stream process, reconnect floodplains and increase
stream complexity within project area
- Improve fish and macro invertebrate habitat
- Add high flow refuge and improve fish passage
- 3. Protect Natural Areas
- Remove nonnative vegetation & enhance the riparian corridor
- 4. Create a Community Resource
- Integrate park and natural area developments together
- Provide community educational opportunities
SLIDE 80 Lessons Learned
- 1. Achieve Benefits that the Community Values
- 2. Plan for Adaptive Management
- 3. Use an Experience Based Procurement Process
- 4. Use Risk to Divide the Site in Urban Streams
- Communicate Fixed and Dynamic Segments
- Geomorphic Process Creates Enduring Habitat
- Valley Width Trumps Channel Form
- 5. Visit Your Sites and Learn From the Experience
SLIDE 81 Joe Richards, PE, CWRE jrichards@esassoc.com
“The river, then, is the carpenter of its own edifice.”
- Dr. Luna B. Leopold, A View of the River, 1996.