Luther Road Habitat Restoration Project Flood Resiliency, Habitat - - PowerPoint PPT Presentation

luther road habitat restoration project
SMART_READER_LITE
LIVE PREVIEW

Luther Road Habitat Restoration Project Flood Resiliency, Habitat - - PowerPoint PPT Presentation

Luther Road Habitat Restoration Project Flood Resiliency, Habitat Creation and Community Building ESA is where Joe Richards, PE, CWRE solutions and jrichards@esassoc.com service meet. Presentation Outline Johnson Creek Watershed and


slide-1
SLIDE 1

Luther Road Habitat Restoration Project

Flood Resiliency, Habitat Creation and Community Building

ESA is where solutions and service meet.

Joe Richards, PE, CWRE jrichards@esassoc.com

slide-2
SLIDE 2

Presentation Outline

  • Johnson Creek Watershed and the Project Site
  • Design, Permitting and Construction
  • Monitoring
  • First Winter 2014 – 2015
  • Second Winter 2015 – 2016
  • Second Summer 2016
  • Third Winter 2016 – 2017
  • Lessons Learned
slide-3
SLIDE 3

Project Team

Portland Department of Transportation Portland Parks and Recreation Department of State Lands Oregon Department of Fish and Wildlife US Army Corps of Engineers National Marine Fisheries Service

Implementation Partners Funding Partners

slide-4
SLIDE 4

THE JOHNSON CREEK WATERSHED AND THE PROJECT SITE

slide-5
SLIDE 5

Project Site

Johnson Creek Watershed

slide-6
SLIDE 6

Project Vicinity

slide-7
SLIDE 7

Site Map 2013

slide-8
SLIDE 8

1920 2007

T The 76-inch Monolithic Trunk Sewer and Manhole were exposed due to Vertical Incision by Johnson Creek.

The Problem with the Interceptor Sewer

slide-9
SLIDE 9

Coho Salmon, Chinook Salmon, Steelhead, Rainbow Trout and Lamprey

Source: Washington Department of Fish and Wildlife

slide-10
SLIDE 10

Flooding 12-3-2007

slide-11
SLIDE 11

DESIGN DEVELOPMENT

slide-12
SLIDE 12

Project Goals

  • 1. Protect Public Health
  • Protect sewer crossing and manhole from stream forces
  • Protect private property from erosion and flooding
  • Treat stormwater from existing industrial outfalls
  • 2. Restore Johnson Creek
  • Enhance stream process, reconnect floodplains and increase

stream complexity within project area

  • Improve fish and macro invertebrate habitat
  • Add high flow refuge and improve fish passage
  • 3. Protect Natural Areas
  • Remove nonnative vegetation & enhance the riparian corridor
  • 4. Create a Community Resource
  • Integrate park and natural area developments together
  • Provide community educational opportunities
slide-13
SLIDE 13

Historical Aerials

1939 Aerial 2,365’ Main Channel 972’ Secondary Channel

1977 Aerial 2,203’ Main Channel

slide-14
SLIDE 14

Geotechnical Exploration

slide-15
SLIDE 15

Designing the Riffle Pool Sequence

slide-16
SLIDE 16

Large Woody Debris (LWD)

slide-17
SLIDE 17

Hydraulic Modeling

Existing Conditions Model Proposed Conditions Model

slide-18
SLIDE 18

PERMITTING AND PROPERTY ACQUISITION

slide-19
SLIDE 19

Permitting Summary

Listed Species: Steelhead, Coho & Chinook salmon

  • Clackamas County Land Use Review
  • NPDES 1200c Permit for Construction Activities
  • COE/DSL Joint Permit for Removal and Fill

– Individual Permit (timeframes expanded to 10-years to support project construction and adaptive management).

  • DEQ 401 WQ Certification
  • FEMA CLOMR/LOMR
  • ODFW Fish Salvage Permit

– In-Water Work Window: July 15th to August 31st

slide-20
SLIDE 20

Sewer and Channel Change Easements

slide-21
SLIDE 21

Industrial Property Easements

slide-22
SLIDE 22

CONSTRUCTION

The engineers estimate was $3,512,683 which is near the average of the 10 bids received for the project. Colf Construction, LLC was the low bidder at $2,125,604 and was awarded the contract.

slide-23
SLIDE 23

Invasive Species Management

slide-24
SLIDE 24

Contaminated Media

slide-25
SLIDE 25

Stream Diversion Construction

slide-26
SLIDE 26

Site Map Spring 2014

slide-27
SLIDE 27

Fish Salvage Complete

July 22 to July 24 Salvage Counts

Native Fish Total: 5216 Non-Native Fish Total: 14

slide-28
SLIDE 28

Mass Grading

76,000 cy of cut, 38,000 cy of fill 38,000 cy of haul off. 8,050 cy Contaminated (on-site disposal).

slide-29
SLIDE 29

Condition of the Interceptor Crossing

slide-30
SLIDE 30

Interceptor Sewer Rehabilitation Plan

slide-31
SLIDE 31

Installing LWD

slide-32
SLIDE 32

Soil Wrapped Lifts

slide-33
SLIDE 33

Constructing Streambed

slide-34
SLIDE 34

Stream Diversion and Fish Salvage: September 17, 2014

slide-35
SLIDE 35

Project Fish Salvage Statistics

Native Species

7/22/2014 7/23/2014 7/24/2014 8/28/2014 9/17/2014 Total

  • No. Injured Cond. at Release

Mortality Rainbow/Steelhead 12 2 33 7 31 92 Stable, no visible harm 7 Cutthroat Trout 9 9 Stable, no visible harm Largescale Sucker 6 9 33 48 Stable, no visible harm Redside Shiner 576 359 1217 797 62 3116 Stable, no visible harm 105 Golden Shiner 1 1 Stable, no visible harm Cottids sp. 692 842 923 263 158 2959 Stable, no visible harm 81 Speckled Dace 122 43 121 108 231 692 Stable, no visible harm 67 Longnose Dace 1 3 7 Stable, no visible harm 3 Pikeminnow 2 7 10 Stable, no visible harm 1 Pacific Lamprey, adult 1 1 2 Stable, no visible harm Lamprey, Ammocetes 89 25 131 105 12 362 Stable, no visible harm Crayfish, spp. 156 522 361 266 175 1492 Stable, no visible harm 12 Sub total (native fish): 1499 1271 2446 1321 672 276 Total Native Fish: 7485 Non-Native Species

7/22/2014 7/23/2014 7/24/2014 8/28/2014 9/17/2014 Total

  • No. Injured Cond. at Release

Mortality Bluegill 3 3 Stable, no visible harm Pumpkinseed 4 6 27 37 Stable, no visible harm Brown Bullhead 1 1 Stable, no visible harm Crappie sp. 1 1 Stable, no visible harm Sub total (invasive fish): 4 9 1 28 Total Invasive Fish: 42

slide-36
SLIDE 36

MONITORING

slide-37
SLIDE 37

738 cfs (1-17-15) 754 cfs,(3-15-15)

2015 Flowrates

First Winter 2015

slide-38
SLIDE 38

The Interceptor Crossing

First Winter 2015

slide-39
SLIDE 39

Bank Protection

First Winter 2015

slide-40
SLIDE 40

Water Quality Facility

First Winter 2015

slide-41
SLIDE 41

Connected Floodplains Provide Refuge

First Winter 2015

slide-42
SLIDE 42

A Community Resource

First Winter 2015

slide-43
SLIDE 43

Site Map Spring 2015

slide-44
SLIDE 44

Wettest December, wettest month ever in Portland in 75 years

Previous Records for Portland International Airport (PIA)

  • December 1996 Total = 13.35 inches PIA
  • 2.59 inches in 24 hours on December 12-13, 1977.

New Records for Portland International Airport

  • December 2015 Total = 16.18 inches PIA
  • 2.67 inches in 24 hours PIA December 7, 2015

Johnson Creek Watershed -Gresham Fire Station (GFS)

  • December 2015 Total = 18.62 inches GFS
  • 3.47 inches in 24 hours GFS, December 7, 2015
slide-45
SLIDE 45

2,740 cfs (12-7-15)

Second Winter 2015

2015 Flowrates

slide-46
SLIDE 46

Second Winter 2015

Interceptor Crossing

slide-47
SLIDE 47

Second Winter 2015

Water Quality Facility

slide-48
SLIDE 48

Second Winter 2015

Bottom of Project Site

slide-49
SLIDE 49

Second Winter 2015

Bottom of Project Site

slide-50
SLIDE 50

Post Flood (Video)

slide-51
SLIDE 51

Site Map Spring 2016

slide-52
SLIDE 52

Channel Comparison 2015 to 2016

slide-53
SLIDE 53

Summer 2016 – BES Monitoring

slide-54
SLIDE 54

DSL Years 1 and 2 Monitoring by BES

slide-55
SLIDE 55

DSL Years 1 and 2 Monitoring by BES

Instream Habitat Assessment Summary Overall, the Luther Road habitat restoration project should be deemed a success. The condition of habitat in the reach prior to the project was poor, but it is now

  • n a trajectory toward very high quality.

The abundance and distribution of pool habitat in the reach is a major asset. Three backwater pools were mapped this year. These habitats are highly valuable year-round, as they provide low energy areas for fish to feed and rest. Greater quantities of wood within the pools will provide the needed cover habitat while creating the hydraulic energy necessary to moves sediment out of the pools and maintain pool depth.

slide-56
SLIDE 56

Geomorphic Monitoring

slide-57
SLIDE 57

Geomorphic Monitoring

Sediment Mass Balance The mass balance analysis produced a net fill in the project area of 1,135 cubic yards of sediment. This material, which represents approximately 20% of the total volume of aggraded material in the project area, must have come from upstream reaches. Key Adaptive Management Areas

  • 1. Protection of the sewer Interceptor crossing,
  • 2. Grade control at the upstream end of Reach C to protect

against the potential for headcut migration, and

  • 3. Right bank stabilization along the avulsed channel to

protect the overlook structure.

slide-58
SLIDE 58

Fall 2016 – Pre Winter Pictures

slide-59
SLIDE 59

Future Park Area – Meadow Habitat

Fall 2016 – Before Third Winter

slide-60
SLIDE 60

Stable Riffles

Fall 2016 – Before Third Winter

slide-61
SLIDE 61

Lents Interceptor Sewer Crossing

Fall 2016 – Before Third Winter

slide-62
SLIDE 62

Lents Interceptor Sewer Crossing

Fall 2016 – Before Third Winter

slide-63
SLIDE 63

Large Bend with LWD Structures

Fall 2016 – Before Third Winter

slide-64
SLIDE 64

Side Channel

Fall 2016 – Before Third Winter

slide-65
SLIDE 65

Floodplain Bench

Fall 2016 – Before Third Winter

slide-66
SLIDE 66

Water Quality Facility

Fall 2016 – Before Third Winter

slide-67
SLIDE 67

Interpretive Features

Fall 2016 – Before Third Winter

slide-68
SLIDE 68

Floodplain Restoration

Fall 2016 – Before Third Winter

slide-69
SLIDE 69

Side Channel

Fall 2016 – Before Third Winter

slide-70
SLIDE 70

Connected Off Channel Wetland

Fall 2016 – Before Third Winter

slide-71
SLIDE 71

Return Flow to Oxbow Feature

Fall 2016 – Before Third Winter

slide-72
SLIDE 72

Community Gathering Place

Fall 2016 – Before Third Winter

slide-73
SLIDE 73

Winter 2016

slide-74
SLIDE 74

Lents Interceptor Sewer Crossing

11-25-16 (600 cfs) November 2016 –Third Winter

slide-75
SLIDE 75

Lents Interceptor Sewer Crossing (Video)

11-25-16 (600 cfs) November 2016 –Third Winter

slide-76
SLIDE 76

Floodplain Connections

(300 cfs) 11-24-16 (600 cfs) 11-25-16 November 2016 –Third Winter

slide-77
SLIDE 77

Reconnected Floodplains (Video)

11-25-16 (600 cfs) November 2016 –Third Winter

slide-78
SLIDE 78

Leaving the Project Site

11-25-16 (600 cfs)

slide-79
SLIDE 79

Revisit Project Goals

  • 1. Protect Public Health
  • Protect sewer crossing and manhole from stream forces
  • Protect private property from erosion and flooding
  • Treat stormwater from existing industrial outfalls
  • 2. Restore Johnson Creek
  • Enhance stream process, reconnect floodplains and increase

stream complexity within project area

  • Improve fish and macro invertebrate habitat
  • Add high flow refuge and improve fish passage
  • 3. Protect Natural Areas
  • Remove nonnative vegetation & enhance the riparian corridor
  • 4. Create a Community Resource
  • Integrate park and natural area developments together
  • Provide community educational opportunities
slide-80
SLIDE 80

Lessons Learned

  • 1. Achieve Benefits that the Community Values
  • 2. Plan for Adaptive Management
  • 3. Use an Experience Based Procurement Process
  • 4. Use Risk to Divide the Site in Urban Streams
  • Communicate Fixed and Dynamic Segments
  • Geomorphic Process Creates Enduring Habitat
  • Valley Width Trumps Channel Form
  • 5. Visit Your Sites and Learn From the Experience
slide-81
SLIDE 81

Joe Richards, PE, CWRE jrichards@esassoc.com

“The river, then, is the carpenter of its own edifice.”

  • Dr. Luna B. Leopold, A View of the River, 1996.