Low-power test results and analysis of the modular cavity D. - - PowerPoint PPT Presentation

low power test results and analysis of the modular cavity
SMART_READER_LITE
LIVE PREVIEW

Low-power test results and analysis of the modular cavity D. - - PowerPoint PPT Presentation

Low-power test results and analysis of the modular cavity D. Bowring 1 with A. Haase 2 , T. Luo 3 , and J. van Pelt 2 1 Fermilab, 2 SLAC, and 3 LBNL May 11-15, 2014 D. Bowring (FNAL) Modular Cavity Status May 11-15, 2014 1 / 18 1.


slide-1
SLIDE 1

Low-power test results and analysis of the modular cavity

  • D. Bowring1

with A. Haase2, T. Luo3, and J. van Pelt2

1Fermilab, 2SLAC, and 3LBNL

May 11-15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 1 / 18

slide-2
SLIDE 2
  • 1. Introduction
  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 2 / 18

slide-3
SLIDE 3

Work done between May 11 and May 15, 2014

What was done?

1

Repair N-to-975 adapter piece

2

With dead-soft OFHC Cu gaskets and no vacuum seal, measure RF properties as a function of clamping bolt torque.

3

Open cavity, replace gaskets, seal cavity again.

4

Repeat item # 2.

5

Profilometry on gaskets to assess “knife edge” indentation on

  • gasket. Check for variation with

angular position. (This work is in progress.)

6

Discuss/plan for final proposal & discussion at MAP meeting.

By whom?

Andy Haase (SLAC) Tianhuan Luo (LBNL) John van Pelt (SLAC) Daniel Bowring (FNAL)

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 3 / 18

slide-4
SLIDE 4

Summary of results

We observed critical coupling using both sets of gaskets. Tightening clamp bolts improved RF properties monotonically and

  • asymptotically. We observed no significant change between 70

inch-pounds of torque and 90 in-lbs in either case. Measurements were repeatable on loosening/re-tightening clamp

  • bolts. The details of this repeatability have interesting implications

for repair options, to be discussed later in this talk.

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 4 / 18

slide-5
SLIDE 5
  • 2. May 11, 2014
  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 5 / 18

slide-6
SLIDE 6

Tianhuan assisted with measurements on May 11, 2014

1 Prior to her visit, the vacuum gaskets were removed from the cavity.

The dead-soft, OFHC Cu RF gaskets were left in.

2 During shipping, the N-to-975 adapter piece was damaged. This

damage was repaired. We observed some minor loss in the system during measurement (see below) that may be explained by this damage/repair process.

3 Bolts tightened with a torque wrench in 10 inch-pounnd increments.

Frequency, Q measured at each increment.

4 Asymptotic behavior observed at and above 80 inch-pounds.

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 6 / 18

slide-7
SLIDE 7

Tianhuan assisted with measurements on May 11, 2014

90 in-lb torque

Ql 11903 beta 0.948 Q0 23188 Qe 24408 f0 f1 f2 f3 f4 804.615 6 804.633 6 804.598 9 804.648 9 804.581 3 Ql measured by s21 -3dB points is 11893.

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 7 / 18

slide-8
SLIDE 8
  • 3. Photos from gasket swap
  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 8 / 18

slide-9
SLIDE 9

Gasket swap on May 15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 9 / 18

slide-10
SLIDE 10

Gasket swap on May 15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 10 / 18

slide-11
SLIDE 11

Gasket swap on May 15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 11 / 18

slide-12
SLIDE 12

Gasket swap on May 15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 12 / 18

slide-13
SLIDE 13

Gasket swap on May 15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 13 / 18

slide-14
SLIDE 14

Gasket swap on May 15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 14 / 18

slide-15
SLIDE 15

Gasket swap on May 15, 2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 15 / 18

slide-16
SLIDE 16
  • 4. RF measurements on May 15,

2014

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 16 / 18

slide-17
SLIDE 17

RF measurements on May 15, 2014

β ≈ 1, f = 804.65 MHz.

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 17 / 18

slide-18
SLIDE 18

Coupling is repeatable under repeated bolt tightening/loosening.

After measurement at 100 inch-pounds, loosen upstream bolts to finger-tight. Tightening/loosening bolts moves repeatably between outer/inner circle. ∼ 10o tightening on two bolts is sufficient to make this transition!

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 18 / 18

slide-19
SLIDE 19

Interpretation of easily repeatable coupling transition

End plate, gasket deform during clamping to make RF seal. Good news: This is demonstrably easy in this case. Bad news: We don’t control the deformation! This gives further support to SLAC’s proposed clamp ring re-design. c.f. “push bolts”.

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 19 / 18

slide-20
SLIDE 20

What now?

1 SLAC will make their complete proposal at the MAP meeting. 2 On Tuesday they’ll circulate a written report so we can all be on the

same page, prepared for the MAP meeting.

3 They’re currently evaluating a design that uses Mo-alloyed “super

bolts”. These would eliminate the need to drill/tap new holes in the cavity.

4 I have a lot of photos to upload to the MTA site.

  • D. Bowring (FNAL)

Modular Cavity Status May 11-15, 2014 20 / 18