lorry route applications old oak common
play

Lorry Route Applications Old Oak Common Community presentation - PowerPoint PPT Presentation

1 Lorry Route Applications Old Oak Common Community presentation Online event 12 May 2020 2 Overview Introductions Housekeeping Purpose of this event: Introduction to the Schedule 17 lorry routes for the construction of the station


  1. 1 Lorry Route Applications Old Oak Common Community presentation Online event 12 May 2020

  2. 2 Overview Introductions Housekeeping Purpose of this event: • Introduction to the Schedule 17 lorry routes for the construction of the station (Application No. 20/0057/HS2OPDC) • Update on combined lorry routes numbers – BBVS and SCS JV works

  3. 3 Schedule 17 - Condition relating to Road Transport Approval of Lorry Routes Paragraph 6 (1) If the relevant planning authority is a qualifying authority, development must , with respect to the matters to which this paragraph applies, be carried out in accordance with arrangements approved by that authority. (2) The matters to which this paragraph applies are the routes by which anything is to be transported on a highway by a large goods vehicle to — (a) a working or storage site, (b) a site where it will be re-used, or (c) a waste disposal site.

  4. 4 Schedule 17 - Condition relating to Road Transport Approval of Lorry Routes (5) The relevant planning authority may only refuse to approve arrangements for the purposes of this paragraph on the ground that— (b) the arrangements ought to be modified— (i) to preserve the local environment or local amenity, (ii) to prevent or reduce prejudicial effects on road safety or on the free flow of traffic in the local area, or (iii) to preserve a site of archaeological or historic interest or nature conservation value, and are reasonably capable of being so modified. (6) The relevant planning authority may only impose conditions on approval for the purposes of this paragraph— (a) with the agreement of the nominated undertaker, and (b) on the ground referred to in sub-paragraph (5)(b).

  5. 5 Old Oak Common station Lorry routes Paul Rasmussen Logistics Manager

  6. 6 BBVS Schedule 17 lorry route timeline 23 June 2020 21 April 2020 12 May 2020 Decision on BBVS BBVS submitted Resident online event Schedule 17 lorry route Schedule 17 lorry route focused on the application application to OPDC proposed lorry routes

  7. 7 HS2 sites in Old Oak Common Channel Gate Road Atlas Road Victoria Road (A4000) Old Oak Common Lane Old Oak Common Station Horn Lane UTX Satellite Sites A and B Leamington Park Road

  8. 8 OOC station construction programme headlines* * Subject to change Anticipated Start date (quarter/year) Activity Estimated Completion of Works (quarter/year) Q3 2020 Main site preparation works Q1 2021 Q3 2020 Satellite Site A/B preparation works Q3 2021 Q3 2020 Stamford Brook Sewer works Q3 2021 Q3 2020 Ground remediation works Q3 2021 Q3 2020 Excavation works Q4 2023 Q3 2020 Under Track Crossing works Q1 2024 Q4 2020 Piling and diaphragm wall works Q2 2022 Q1 2021 Conveyor installation Q3 2021 Q2 2021 Decommissioning the Heathrow Express depot Q3 2021 Q2 2021 Installation of Tower Cranes Q4 2021 Q4 2021 Utilities Protection Slab works Q3 2022

  9. 9 Update: SCSJV lorry routes and indicative construction programme in Old Oak Aaron Renker Traffic and Highways Manager James McCaffrey Construction Manager

  10. 10 SCSJV Schedule 17 lorry route timeline January Spring Late 2019 2020 Pending 2020 SCSJV SCSJV and HS2 submitted Approval of Ongoing held a lorry Schedule 17 SCSJV’s OPDC review routes focused lorry route Schedule 17 of SCSJV’s community application to lorry route Schedule 17 drop-in on 15 OPDC in late- application lorry route January at 2019 application The Collective

  11. 11 HS2 sites in Old Oak Common Channel Gate Road Atlas Road Victoria Road (A4000) Old Oak Common Lane Old Oak Common Station Horn Lane UTX Satellite Sites A and B Leamington Park Road

  12. 12 Combined BBVS and SCS JV lorry routes numbers

  13. Contractor forecasts comparison with Environmental Statement 13 The table below shows the average combined two-way vehicle trips during busy periods and within the peak month of activity. These figures are likely to change as more detail comes available. ES ES ES Contractor Contractor Forecast Contractor Forecast Forecast Period with busy vehicle Estimated Estimated period with Worksite HGV trips* HGV trips* movements duration of busy vehicle movements Estimated duration worksite use of worksite use 700 6 months 5 years Old Oak Common Station 600 22 months 9 years 460-570 22 months 8 ½ years main compound 140 32 months Stamford Brooks satellite 4-9 4-9 13 months 1 ½ years compound Victoria Road Crossover Box 195-260 2 years 8 years 190-260 4 months 6 ½ years main compound Victoria Road Tunnel Drive 195-260 3 years 4 ½ years 150-230 21 months 6 ½ years main compound Atlas Road satellite compound 270-360 3 ½ years 5 years 270-360 12 months 6 ½ years Willesden Euroterminal main 75-100 2 years 7 ½ years 150-150 6 months 6 ½ years compound Please note : HS2 has assessed the case for maximising use of rail to remove materials from the sites in Old Oak. we plan to maximise the amount of material removed by rail, wherever possible, using a conveyor system and rail head from the Willesden Euroterminal site. Until the conveyor and rail head are built, we will need to remove all materials by road. We continue to look at ways to minimise local road use and disruption to local residents.

  14. 14 SCSJV construction programme planned dates (subject to change) Old Oak Common Station Compound Anticipated start on site date Activity Estimated completion of works (quarter / year) (quarter / year) Q2 2022 Site set up Q1 2023 Q2 2022 Arrival of Temporary Logistics Tunnel TBM Q3 2022 Q2 2023 Euston tunnels TBM drive Q2 2024 Q2 2025 Demobilisation Q3 2025

  15. SCSJV construction programme planned dates (subject to change) 15 Victoria Road Tunnel Drive Main Compound Anticipated start on site Activity Estimated completion of date (quarter / year) works (quarter / year) Q4 2019 Site set up Q3 2020 Q3 2020 Provision of welfare facilities Q3 2020 Q1 2022 Logistical support for Northolt Tunnel Drives Q1 2023 Demobilisation Q2 2025 Victoria Road Crossover Box Main Compound Anticipated start on site Activity Estimated completion of date (quarter / year) works (quarter / year) Q4 2019 Site set up Q4 2020 Q2 2020 Construction of Victoria Road Crossover Box and Ancillary Shaft Q2 2025 Q3 2022 Tunnel Boring Machine (TBM) launch Q4 2022 Q3 2020 Temporary conveyor installation Q4 2021 Q4 2022 Construction of headhouse Q2 2024 Demobilisation Q2 2025

  16. 16 SCSJV construction programme planned dates (subject to change) Atlas Road Satellite Compound Anticipated start on site date Activity Estimated completion of works (quarter / year) (quarter / year) Q1 2020 Site set up Q1 2021 Q2 2020 Construction of traffic bridge (over Grand Union Canal) Q1 2021 Q3 2020 Construction of logistics tunnel Q4 2022 Q2 2021 Temporary conveyor installation Q4 2021 Q3 2023 Receipt of TBMs from Euston Throat and Greenpark Way Vent Q4 2024 Shaft Q2 2025 Demobilisation Q3 2025

  17. 17 SCSJV construction programme planned dates (subject to change) Willesden Euroterminal Main Compound Anticipated start on site date Activity Estimated completion of works (quarter / year) (quarter / year) Q4 2019 Site set up Q3 2020 Q2 2020 Construction of traffic bridge (over Grand Union Canal) Q1 2021 Q2 2020 Construction of temporary railhead and excavated material Q4 2020 handling facility Q1 2021 Temporary conveyor installation Q4 2021 Q4 2020 Operation of handling facility for removal of excavated material Q3 2024 by rail Q2 2025 Demobilisation Q4 2025

  18. 18 Questions and Answers

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend