Long term challenges in reflecting network costs: Pricing and other - - PowerPoint PPT Presentation

long term challenges in reflecting network costs
SMART_READER_LITE
LIVE PREVIEW

Long term challenges in reflecting network costs: Pricing and other - - PowerPoint PPT Presentation

Long term challenges in reflecting network costs: Pricing and other solutions to manage network challenges. (feat. Network Opportunity Maps) Chris Dunstan (Research Director, ISF) AER Tariff Structure Statement Forum 14 December, 2015


slide-1
SLIDE 1

Long term challenges in reflecting network costs:

Pricing and other solutions to manage network challenges.

(feat. Network Opportunity Maps)

Chris Dunstan (Research Director, ISF)

AER Tariff Structure Statement Forum 14 December, 2015

slide-2
SLIDE 2
  • 1. Challenges
  • 2. Network Opportunity Maps

Information for the decentralised energy era

  • 3. Conclusions

OVERVIEW

slide-3
SLIDE 3

CHALLENGES

slide-4
SLIDE 4

isf.uts.edu.au

CHALLENGES FOR COST REFLECTIVE NETWORK PRICING

  • Locational specificity
  • Time responsiveness: by hour, day, month, year
  • It’s not just about peak demand

Low voltage network; voltage management; power factor; ramp rates; fault current, reliability, asset replacement, reliability and forecast unserved energy (USE)

  • New technology: Solar PV, Electric Vehicles, Batteries, energy

management, hydrogen & fuel cells

slide-5
SLIDE 5

CENTRALISED ELECTRICITY SUPPLY: Have we already peaked?

isf.uts.edu.au Rooftop solar PV Energy efficiency

Annual Energy Forecast for the NEM

(NEFR, June 2014)

slide-6
SLIDE 6

PEAK DEMAND – Still rising?

Source: 2015 AEMO National Electricity Forecasting Report (NEFR) (June 2014)

Low load factor = higher prices

slide-7
SLIDE 7

isf.uts.edu.au

ELECTRICITY NETWORKS: LOCATION, LOCATION, TIME

Networks comprise >50% power bills (nationally) Network costs are highly location & season specific Mapping can help identify priority areas for non- network alternatives (Decentralised Energy)

5 10 15 20 25 30 35 ACT Qld NSW VIC* SA Cents per kilowatt-hour (AUD 2010)

GST Carbon Price ESS/REES GGAS /Qld Gas SRES LRET FiT Metering Retail Distribution Transmission Generation

Electricity prices by state (2011/12)

Source: AEMC , Future Possible Retail Electricity Price Movements, 2011; Treasury modelling (*Vic = 2012)

slide-8
SLIDE 8

isf.uts.edu.au

New Technology: This is just the beginning

slide-9
SLIDE 9

isf.uts.edu.au

Distributed Generation

Cogeneration Standby Generation Biomass Generation Small Gas Generation Solar Photovoltaics

Energy Efficiency

Efficient motors & chillers Efficient Lighting Efficient showerheads Efficiency Retrofits Behaviour change

Peak Load Management

Interruptible loads Power factor correction Gas Chillers Ice Storage Electric to Gas Hot Water Time of Use tariffs Fuel Cells Battery Storage Electric Vehicles

Decentralised Energy includes:

slide-10
SLIDE 10

isf.uts.edu.au

THE CHANGING ELECTRICITY SECTOR

The past Centralised supply Forecast demand Flat prices Build least cost infrastructure Little engagement with customers (end users) The future → Decentralised supply → Manage demand → Cost reflective prices → Invest in least cost supply and demand side mix → Extensive engagement with customers (and retailers and service providers)

How to deliver a win-win for networks (NSPs) and customers?

Information and collaboration are key

slide-11
SLIDE 11

NETWORK OPPORTUNITY MAPS

slide-12
SLIDE 12

isf.uts.edu.au

Where within the electricity network do the most cost-effective DE opportunities exist? How much could DE be worth at these locations? When are the key years and times of constraint?

To answer these questions, ISF created

Network Opportunity Maps

(AKA….the Dynamic Avoidable Network Cost Evaluation or DANCE model)

slide-13
SLIDE 13

A resource to show where/when to target Renewable Energy and DE technologies & services:

  • Annually updated through streamlined process
  • Consistently applied in every (NEM) jurisdiction
  • Freely available on online platform
  • Woven into Networks’ Demand Side Engagement

Strategies

isf.uts.edu.au

NETWORK OPPORTUNITY MAPS PROJECT

slide-14
SLIDE 14

isf.uts.edu.au

NETWORK OPPORTUNITY MAPS PROJECT

  • Three year project, Sept 2014 – Sept 2017
  • Funded by ARENA, UTS, NSW Govt, and Ergon Energy
  • Formal network business partners: Ergon Energy,

Electranet, TransGrid

  • Data provision and collaboration with all NSPs in the NEM
  • Produced on NICTA’s new Australian Renewable Energy

Mapping Infrastructure (AREMI) portal

  • http://nationalmap.gov.au/renewables/
  • This is first public release of Sample Maps
slide-15
SLIDE 15

PROJECT TIMELINE

Sample Maps (Oct 2015) Sample Maps (Oct 2015) 1st Full Iteration (May 2016) 1st Full Iteration (May 2016) 2nd Full Iteration (May 2017) 2nd Full Iteration (May 2017)

isf.uts.edu.au

slide-16
SLIDE 16

WHAT DATA GOES IN?

  • All data comes from Network Service Providers
  • For Sample Maps: generally as published in 2014 Distribution Annual

Planning Reports, and 2015 Transmission Annual Planning Reports)

  • Proposed network investments (augmentation, replacement, other)
  • Cost of capital (WACC), depreciation
  • NSP demand forecasts for each network asset
  • Current capacity of lines and substations
  • Zone substation region boundaries (+ how different assets connect)
  • Hourly load data (load profiles)
slide-17
SLIDE 17

isf.uts.edu.au

WHAT MAPS COME OUT?

  • 1. Available Capacity (MVA)
  • 2. Planned network investment ($m)
  • 3. Value of potentially avoidable investment (‘annual deferral value; $/kVAyr)
  • 4. Peak Day Available Capacity (% exceedance in each hour)
slide-18
SLIDE 18

isf.uts.edu.au

WHAT NETWORK LEVELS ARE COVERED?

Network Opportunity Maps

slide-19
SLIDE 19

THE MAPS: live online

See: http://nationalmap.gov.au/renewables/

slide-20
SLIDE 20

http://cfsites1.uts.edu.au/isf/news-events/newsarchive-detail.cfm?ItemId=31169

Network Opportunity Maps - Available Capacity

slide-21
SLIDE 21

http://cfsites1.uts.edu.au/isf/news-events/newsarchive-detail.cfm?ItemId=31169

Network Opportunity Maps - Available Capacity

slide-22
SLIDE 22

Network Opportunity Maps - Available Capacity

slide-23
SLIDE 23

MAP 2: PROPOSED INVESTMENT

[$MILLION BY YEAR]

See AREMI platform: http://nationalmap.gov.au/renewables/

slide-24
SLIDE 24

MAP 2: PROPOSED INVESTMENT [$m]

slide-25
SLIDE 25

Map 2: Proposed Investment [$m]

slide-26
SLIDE 26

Map 2: Proposed Investment [$m] (c.f. NSW)

slide-27
SLIDE 27

Note: Each zone has detailed clickable data

slide-28
SLIDE 28

÷

ANNUAL DEFERRAL VALUE [$/KVA/YEAR]

x ( + )

slide-29
SLIDE 29

http://cfsites1.uts.edu.au/isf/news-events/newsarchive-detail.cfm?ItemId=31169

Annual Deferral Value [$/kVA/year] - 2016

slide-30
SLIDE 30

Annual Deferral Value [$/kVA/year] - 2017

slide-31
SLIDE 31

Annual Deferral Value [$/kVA/year] - 2018

slide-32
SLIDE 32

Annual Deferral Value [$/kVA/year] - 2019

slide-33
SLIDE 33

Annual Deferral Value [$/kVA/year] - 2020

slide-34
SLIDE 34

Annual Deferral Value [$/kVA/year] - 2021

slide-35
SLIDE 35

MAP 4: HOURLY AVAILABLE CAPACITY

(PEAK DAY- % OF FIRM CAPACITY)

  • Compares forecast hourly demand to firm local network

capacity

  • BUT generally only provided where load is forecast to exceed

capacity.

  • Shown for peak day only (in relevant peak season).
  • Shows Transmission, Sub-transm’n & Distrib’n Zone capacity.
  • Note that this map has changed from hourly deferral value in

previous network opportunity map versions.

slide-36
SLIDE 36

Hourly available capacity- Summer Peak Day, 1pm

slide-37
SLIDE 37

PEAK DAY (HOURLY) AVAILABLE CAPACITY MAP

isf.uts.edu.au

slide-38
SLIDE 38

PROJECT TIMELINE

Sample Maps (Oct 2015) Sample Maps (Oct 2015) 1st Full Iteration (May 2016) 1st Full Iteration (May 2016) 2nd Full Iteration (May 2017) 2nd Full Iteration (May 2017)

isf.uts.edu.au

  • Targeted User Feedback
  • Short user feedback survey (see project website)
slide-39
SLIDE 39

isf.uts.edu.au

EXPECTED PROJECT OUTCOMES

  • Develop a more diverse market of non-network service providers
  • Enhance service offers and choice for customers
  • Develop new business for NSPs in decentralised energy
  • Demonstrate effective collaboration to deliver win-win outcomes

for NSPs and customers “Meeting the information of needs the new decentralised energy era”

slide-40
SLIDE 40

Victoria is well placed to lead on CRNP and DE

  • Lower network investment in recent years
  • Less surplus capacity
  • Higher load at risk
  • Tradition of probabilistic network planning
  • Smart meter rollout means:
  • Better understanding of network conditions
  • More data on voltage excursions and other code noncompliance
  • More capacity for smarter control
  • Network businesses looking for opportunities
  • Government desire to lead on new and clean technology

isf.uts.edu.au

slide-41
SLIDE 41

POLICY TOOLS FOR NETWORK DM

isf.uts.edu.au

Committed 1: Decoupling (via Revenue Cap) 2: Capital Savings Incentive (CESS) 3: Contestable Metering 4: Cost reflective network pricing 5: Customer Information Proposed (DM Incentive Scheme) 6: Least cost objective 7: DM Incentive Payments Potential 8: Voluntary DM targets

  • 9. Performance Reporting
slide-42
SLIDE 42
  • Cost reflective pricing is crucial but not sufficient
  • Clear accessible information is key to this more decentralised

energy market

  • The future needs more competition and more collaboration
  • The future is in flux - flexibility is crucial
  • Customers need better incentives - and so do utilities

Conclusions

slide-43
SLIDE 43

QUESTIONS?

View the maps: http://nationalmap.gov.au/renewables/ [click ‘Electricity Infrastructure’, ‘Network Opportunities – ISF’] Chris Dunstan, chris.dunstan@uts.edu.au (02) 9514 4882 Ed Langham, edward.langham@uts.edu.au (02) 9514 4971