LONG BRANCH SLIGO CREEK NEIGHBORHOOD ASSOCIATION COMMUNITY MEETING - - PowerPoint PPT Presentation

long branch sligo creek neighborhood association
SMART_READER_LITE
LIVE PREVIEW

LONG BRANCH SLIGO CREEK NEIGHBORHOOD ASSOCIATION COMMUNITY MEETING - - PowerPoint PPT Presentation

LONG BRANCH SLIGO CREEK NEIGHBORHOOD ASSOCIATION COMMUNITY MEETING Brendan Gamble, Construction Manager Washington Gas SEPTEMBER 26, 2016 Washington Gas Demographics Has served the Washington, D.C., metropolitan area for over 160 years


slide-1
SLIDE 1

LONG BRANCH – SLIGO CREEK NEIGHBORHOOD ASSOCIATION COMMUNITY MEETING

SEPTEMBER 26, 2016

Washington Gas

Brendan Gamble, Construction Manager

slide-2
SLIDE 2

Washington Gas Demographics

2

  • Has served the Washington, D.C., metropolitan area for over 160 years
  • Mission:

–“To deliver clean and efficient natural gas safely, reliably and at a reasonable cost”

  • Over 1 Million Customers in Washington , D.C., Maryland and Virginia
  • Over 461,000 Meters in Maryland with 225,000 in Montgomery County
slide-3
SLIDE 3

Using Natural Gas Safely

3

  • Natural Gas is non-toxic, colorless, odorless

and combustible

  • Mercaptan is added as an unpleasant odorant

to help detect leaking natural gas

  • You are an important part of our safety

program

  • Remember the 3 R’s:

Recognize, React, and Respond!

slide-4
SLIDE 4

Introduction

4

  • PROJECT PARTICIPANTS

– DESIGN

  • Kayla Yaglou, System Replacement Engineer

– CONSTRUCTION

  • Brendan Gamble, Manager
  • Paul Frederick, Supervisor
  • Rick Ayoub, Supervisor

– CORPORATE RELATIONS

  • Kelly Gibson Caplan, Community Outreach Manager
slide-5
SLIDE 5

Project Coordination

5

  • Coordinated with Takoma Park and MD SHA
  • Accelerated gas line replacement project
  • Submission to PSC for approval
  • MD STRIDE Accelerated Replacement Program
  • Allows for more timely upgrades to eligible utility infrastructure
  • Annual Replacement Program – based on system analysis of historical system trends as

well as other factors

slide-6
SLIDE 6

Natural Gas - Infrastructure 101

6

  • 1. Main Line
  • 2. Service Line
  • 3. Meter Build-up
slide-7
SLIDE 7

Project Scope

7

  • Replace approximately 29,350 feet of low pressure steel and cast iron

main with medium pressure HDPE plastic gas main –Increases reliability and safety

  • 557 affected customers

– 172 service laterals will be replaced due to material type – 385 service laterals will be switched over to the new main

  • Proposed Schedule of Work: October 2016 – April 2017
slide-8
SLIDE 8

Project Area

8

Affected Streets:

  • Flower Ave
  • Domer Ave
  • Garland Ave
  • Central Ave
  • Davis Ave
  • Jackson Ave
  • Minter Pl
  • Carroll Ave
slide-9
SLIDE 9

Project Area

9

Affected Streets:

  • Flower Ave
  • Domer Ave
  • Garland Ave
  • Central Ave
  • Davis Ave
  • Jackson Ave
  • Minter Pl
  • Carroll Ave
slide-10
SLIDE 10

Construction Overview

10

  • Construction Method

– Project involves direct burying new main and replacing associated services

  • Construction Process

– Installation and activation of new gas main in roadway or behind curb in ROW –Temporarily shut off gas during replacement or changeover of service – Inside meters will be moved outside – Relighting of gas appliances will be done after the service replacement is completed

  • Restoration

– Private property and yards will be restored as close to their original state as possible – Road restoration will occur in sections as construction is completed

  • Temporary restoration (cold patch or hot mix)
  • Permanent restoration
slide-11
SLIDE 11

Construction Overview

11

slide-12
SLIDE 12

Construction Overview

12

slide-13
SLIDE 13

Customer Experience

13

  • Customer Notification Letter
  • Miss Utility Markings
  • No parking signs (several days in advance of construction)
  • Main installation behind curb or in roadway
  • Coordinator schedules service replacement
  • Gas service interruption
  • Relight technician scheduled for that evening
  • Private property restoration (one week)
  • Permanent road restoration
slide-14
SLIDE 14

Points of Contact

14

  • Kayla Yaglou, System Replacement Engineer

–(703) 750-4838 office –KYaglou@washgas.com

  • Brendan Gamble, Construction Manager

–(703) 343-0395 mobile –BGamble@washgas.com

  • Paul Frederick, Construction Supervisor

–(703) 969-7721 mobile –PaulFrederick@washgas.com

  • Kelly Gibson Caplan, Community Outreach Manager

–(202) 624-6335 office –Kelly.Caplan@washgas.com

slide-15
SLIDE 15

15

QUESTIONS?