SLIDE 1 logo
file:///.file/id=657136 7.10122715
CATHEDRAL OF THE NATIVITY
Conceptual Design Presentation
SLIDE 2
Process and Timeline Condition Survey Fall, 2014 Programming and Goals Spring, 2015 Initial Option Sketching Summer, 2015 Option Refinement Fall, 2015 Cost Estimating Winter, 2016 Presentation to Congregation Spring, 2016
SLIDE 3
Condition Survey Highlights
SLIDE 4
Areas of weak concrete
SLIDE 5
Rotted wall framing, South face
SLIDE 6
Poor access for those with limited mobility
SLIDE 7
Non-conforming balcony access
SLIDE 8
Generally solid upper structure
SLIDE 9 Committee Priorities
- Critical structural repairs
- New ADA restrooms
- Welcoming new Entry
- Expanded Seating
- Expanded Narthex
- Addition of elevator
- Improved exterior aesthetics
- Improved exterior site spaces
- Improved mechanical, electrical
systems
SLIDE 10 Option A, First Floor
- New Street-level entry
- Welcoming lobby
- New ADA restrooms
- Rebuilt Mary Joyce Room
- Expanded plaza on West
- Large elevator
- Structural repairs
SLIDE 11 Option A, Second Floor
- Expanded Narthex
- Baptismal Font
- Additional seating for 24
- Loss of Balcony
- Easy front connection to
Rectory
SLIDE 12 Option B, First Floor
- All work, Option A
- New Kitchen and Pantry
- New mechanical and
storage spaces
SLIDE 13 Option B, Second Floor
- All work, Option A
- New Transept framing
- New Seating for 35
- Reconstruction of vault
at Sanctuary, improved sight lines
SLIDE 14
Option A/B, Gold Street Exterior
SLIDE 15
Option A/B, 5th Street Exterior
SLIDE 16 Option C, First Floor
- All new structure
- Expanded entry lobby
- ADA restrooms
- Comfortable elevator and stairs
- Expanded west plaza
- New Kitchen, mechanical,
and storage spaces
SLIDE 17 Option C, Second Floor
- All new construction
- Expanded seating, 218
at main floor
- All seating with good sight lines
- Re-use of existing trusses and
leaded glass.
- Expanded Narthex
- Baptismal Font
- New Sacristy adjoining
Sanctuary
SLIDE 18 Option C, Balcony
- All new construction
- Compliant ADA access
- Additional seating for 36
- Good sight lines
SLIDE 19 Option C, Cross Section of Framing
- Re-use of existing trusses
- Re-use of leaded glass
- High energy efficiency
- Optimization of site
SLIDE 20
Option C, Gold Street Exterior
SLIDE 21
Option C, 5th Street Exterior
SLIDE 22 OPTION A (New South extension): $1,600,000 OPTION B (All of A, add new Transept): $2,200,000 OPTION C (All new expanded building): $3,900,000 OPTION D (Critical structural repairs, ?):
Not established
TOTAL PROJECT COSTS, EACH OPTION
Option A and B include 35% markup for contingency, design, misc. Option C includes 32% markup for contingency, design, misc.