CATHEDRAL OF THE NATIVITY

Conceptual Design Presentation

slide-2
SLIDE 2

Process and Timeline Condition Survey Fall, 2014 Programming and Goals Spring, 2015 Initial Option Sketching Summer, 2015 Option Refinement Fall, 2015 Cost Estimating Winter, 2016 Presentation to Congregation Spring, 2016

slide-3
SLIDE 3

Condition Survey Highlights

slide-4
SLIDE 4

Areas of weak concrete

slide-5
SLIDE 5

Rotted wall framing, South face

slide-6
SLIDE 6

Poor access for those with limited mobility

slide-7
SLIDE 7

Non-conforming balcony access

slide-8
SLIDE 8

Generally solid upper structure

slide-9
SLIDE 9

Committee Priorities

  • Critical structural repairs
  • New ADA restrooms
  • Welcoming new Entry
  • Expanded Seating
  • Expanded Narthex
  • Addition of elevator
  • Improved exterior aesthetics
  • Improved exterior site spaces
  • Improved mechanical, electrical

systems

slide-10
SLIDE 10

Option A, First Floor

  • New Street-level entry
  • Welcoming lobby
  • New ADA restrooms
  • Rebuilt Mary Joyce Room
  • Expanded plaza on West
  • Large elevator
  • Structural repairs
slide-11
SLIDE 11

Option A, Second Floor

  • Expanded Narthex
  • Baptismal Font
  • Additional seating for 24
  • Loss of Balcony
  • Easy front connection to

Rectory

slide-12
SLIDE 12

Option B, First Floor

  • All work, Option A
  • New Kitchen and Pantry
  • New mechanical and

storage spaces

slide-13
SLIDE 13

Option B, Second Floor

  • All work, Option A
  • New Transept framing
  • New Seating for 35
  • Reconstruction of vault

at Sanctuary, improved sight lines

slide-14
SLIDE 14

Option A/B, Gold Street Exterior

slide-15
SLIDE 15

Option A/B, 5th Street Exterior

slide-16
SLIDE 16

Option C, First Floor

  • All new structure
  • Expanded entry lobby
  • ADA restrooms
  • Comfortable elevator and stairs
  • Expanded west plaza
  • New Kitchen, mechanical,

and storage spaces

slide-17
SLIDE 17

Option C, Second Floor

  • All new construction
  • Expanded seating, 218

at main floor

  • All seating with good sight lines
  • Re-use of existing trusses and

leaded glass.

  • Expanded Narthex
  • Baptismal Font
  • New Sacristy adjoining

Sanctuary

  • New Reconciliation space
slide-18
SLIDE 18

Option C, Balcony

  • All new construction
  • Compliant ADA access
  • Additional seating for 36
  • Good sight lines
slide-19
SLIDE 19

Option C, Cross Section of Framing

  • Re-use of existing trusses
  • Re-use of leaded glass
  • High energy efficiency
  • Optimization of site
slide-20
SLIDE 20

Option C, Gold Street Exterior

slide-21
SLIDE 21

Option C, 5th Street Exterior

slide-22
SLIDE 22

OPTION A (New South extension): $1,600,000 OPTION B (All of A, add new Transept): $2,200,000 OPTION C (All new expanded building): $3,900,000 OPTION D (Critical structural repairs, ?):

Not established

TOTAL PROJECT COSTS, EACH OPTION

Option A and B include 35% markup for contingency, design, misc. Option C includes 32% markup for contingency, design, misc.