10/21/2016 Ohio Department of Transportation Local Government Programs Andrea Stevenson, Local Programs Manager Jeff Peyton, Local Projects Coordinator ODOT Office of Systems Planning and Program Manager John R. Kasich, Governor Jerry


slide-1
SLIDE 1

10/21/2016 1

Ohio Department of Transportation

w w w. t r a n s p o r t a t i o n . o h i o . g o v John R. Kasich, Governor • Jerry Wray, Director

Local Government Programs

Andrea Stevenson, Local Programs Manager Jeff Peyton, Local Projects Coordinator ODOT Office of Systems Planning and Program Manager 2

LPA Administered Projects

Supervision and Staffing -

  • Compliance with all applicable Federal and State requirements.
  • The local public agency is adequately staffed and suitably

equipped to undertake and satisfactorily complete the work.

  • Local public agency shall provide a full-time employee of the

agency to be in responsible charge of the project.

slide-2
SLIDE 2

10/21/2016 2

3

  • “Person in Responsible charge” means:
  • Aware of day-to-day operations on the project
  • Aware of and involved in decisions about changed conditions

that require change orders

  • Aware of qualifications, assignments, performance of

consultant staff at all stages of the project

  • Visiting the project on a frequency that is commensurate with

the magnitude & complexity of the project.

Locally Administered Projects

4

Person in Responsible Charge vs. Construction Project Engineer (CPE)

The “Person in Responsible Charge” must be a permanent employee of the Local Agency.

  • Not required to have an Engineering License but may also act as the

Construction Project Engineer (CPE) if Licensed to do so.

The CPE can work under contract or agreement for the LPA, but cannot serve as the “Person in Responsible Charge” unless permanently employed by the LPA.

slide-3
SLIDE 3

10/21/2016 3

5

LPA Communication to ODOT

Pre-con notifications (Coordinate date) Progress Meetings Regular Status updates

  • Weekly or Bi-weekly -

Change Order notifications – All Final Inspections – Walk through

6

Preconstruction Conference

  • Discuss the details of project construction –
  • Project Staffing / Contacts
  • List of Material Suppliers
  • Plan and Proposal Notes / As Per Plan Items
  • Progress Schedule / Completion
  • Method of Payment – Direct by ODOT or thru LPA
  • Change Order Review / Claims Process
  • Status of Utility Relocations / Railroad Coordination
  • Prevailing Wage / EEO / DBE Responsibilities
  • EPA Commitments
  • Maintenance of Traffic – Any closing of the road
  • Erosion Control
  • Set up a date with the ODOT Construction Monitor (Jon Milesky)
slide-4
SLIDE 4

10/21/2016 4

7

Progress Meetings

  • Frequency based on project complexity.
  • Minimum requirement of one per month. (while work is being performed)
  • Attendance at progress meetings is required for the Contractor’s

Superintendent, Construction Project Engineer and others including Subcontractor representatives, suppliers, utilities, and railroads.

  • The CPE must record minutes and provide them to attendees, and ODOT

should the Department not be in attendance.

  • Agenda should include –
  • Outstanding Issues
  • Safety
  • Work in Progress – Look Ahead
  • Progress Schedule – Critical Path Activities / Completion Date
  • Critical / Non-Critical Delays / Time Extensions
  • RW / Utilities / Environmental Commitments
  • Testing / Materials
  • Project Submittals
  • Dispute Resolution / Claims
  • DBE

8

Administration and Documentation

slide-5
SLIDE 5

10/21/2016 5

9

  • Schedules
  • Correspondence
  • Change Orders
  • Invoices
  • Property Owner

Agreements

  • Complaint Log
  • Finalization
  • Plan Revisions
  • Right-of-Way
  • Railroad
  • Utilities
  • Other
  • Materials
  • Daily Diaries
  • Certified Payrolls

Project Files

10

Project Documentation

Major areas of documentation

  • Daily diaries or Inspector’s daily reports
  • Method of Measurement & Basis of Payment
  • Materials submittals
  • (certificates of compliance, test reports, etc)
  • Shop drawings
  • NPDES/environmental compliance
  • Work Zone safety & traffic control
  • Change Orders, Extensions of Time
  • Claims
slide-6
SLIDE 6

10/21/2016 6

11

Documentation Best Practices

  • State facts, not opinions (include digital photos)
  • Maintain organized support documents
  • Job Progress Meeting Minutes
  • Utility Meeting Minutes
  • Referenced Memos or Reports by Others
  • Materials Inspection Reports
  • Inspector’s reports
  • Daily Diaries
  • Inspection forms and pay item summaries

12

Project Diaries

  • Complete, concise, accurate
  • Factual (no hearsay)
  • Signed & dated by inspector
  • Major items to include:
  • Items of work
  • Weather
  • Contractors & Equipment
  • Traffic control – MOT
  • NPDES
  • Testing
  • Compliance issues
  • Measurements
  • Pay quantities
  • Decisions made on-site
  • Force account work
  • WHY?? Legal document for

Disputes, Claims, Audits, etc.

slide-7
SLIDE 7

10/21/2016 7

13

Project Diaries

Document the actual pay item(s) of work performed each day.

  • Include the appropriate C&MS Item number
  • Also include the Project Reference number

14

Materials Acceptance

  • All materials incorporated into the Work need to be

documented.

  • Use C&MS Section 700 for documentation guidance

“700 Minimum Requirements for Sampling Materials” (Page 663 of the 2016 C&MS)

  • Temporary materials are to be documented in this manner as

well.

slide-8
SLIDE 8

10/21/2016 8

15

Materials Acceptance

  • Make sure the Contractor provides a list of materials to you at the

preconstruction meeting per C&MS 108.02

  • The Prime Contractor must provide a list of materials to be used by

all of the subcontractors as well.

  • The (CPE) Construction Project Engineer is responsible

for ensuring ALL materials are approved before use on site.

16

Reference / Pay Item Files

  • Provide individual folders for each Pay item of work.

Include all required materials documentation in the folder.

This simplifies the auditing process.

  • Field Documentation Inspection Forms
  • Seven identifiers
  • Project Number, Item Number, Plan Reference Number, Work

Description, Location, Date, Signature

  • Plan quantity vs. Actual Quantity?
  • Don’t just pay plan quantity.

(Often becomes a red flag when auditing)

  • Properly document field measurements and calculations.
slide-9
SLIDE 9

10/21/2016 9

17

Reference / Pay Item Files

  • Summarized final quantity sheet in each Pay item Folder

Include Dates of work, Locations, Daily Payment Amounts and the Running Totals to date. Summary sheets should cross check with the inspector’s Daily Diary Entries.

  • Non-performed items still require documentation

18

Change Orders

slide-10
SLIDE 10

10/21/2016 10

19

Change Orders

Read, Understand, and follow C&MS 109.05 Know how to determine State Average Prices and Comparables. Follow The LPA Manual of Procedures, Refer to Appendix “K” and “L”

Footer (use Insert>Headers & Footers to change)

slide-11
SLIDE 11

10/21/2016 11

22

  • Original Contract prices adjusted for increases or

decreases in material costs, labor costs, or equipment costs.

  • State-wide average unit prices.
  • Average price awarded on three different projects of

similar work and quantity.

  • Prices computed by Office of Estimating.
  • Cost analysis of labor, material, equipment, and allowed

mark-ups.

  • Cost analysis of compensable delays.
  • CMS 105.09.C Force Account
  • Last resort, only use when unit prices can not be agreed upon.

CMS 109.05.B Negotiated Prices

slide-12
SLIDE 12

10/21/2016 12

23

  • Obtain the Construction Monitor’s Prior concurrence for all

“significant” change orders.

  • “Significant” change orders are as follows:

$25,000 for projects <$500,000 Lesser of 5% of total bid contract or $100,000 for projects >$500,000 Over $500,000 ($25,000+2.5% of invoice over amount over the $500,000 Changes that impact project limits, scope, environmental,

  • r

structural design

Change Orders

Footer (use Insert>Headers & Footers to change)

slide-13
SLIDE 13

10/21/2016 13

25

LPA Invoicing

26

Pay Items that are NOT eligible for Reimbursement?

  • Does your project have funding splits or include

different reimbursement percentages?

  • Know what items of work are Eligible and those that are not.

Urban Paving projects (Curb to curb, Top 3-1/2” of Pavement) Extra work? Decorative/ Local preference items? (light poles, banners etc.) Work beyond original scope or outside the R.O.W?

slide-14
SLIDE 14

10/21/2016 14

27

Submitting Invoices to ODOT:

Local Let Summary and Payable Invoice (LLS&PI) Don’t just sign and send !!

The CPE or Person in Responsible Charge has an obligation to review and insure that the reimbursement amounts are true and accurate.

Does everything make sense??

28

Submitting Invoices to ODOT:

By signing and dating, you are attesting that you have audited all the calculations and quantities for payment. ODOT personnel discover numerous errors that are simply unacceptable. Invoices with errors will be rejected and sent back for revision.

slide-15
SLIDE 15

10/21/2016 15

29

Submitting Invoices to ODOT Dist-08

All reimbursement submittals should be sent Directly to the District LPA Construction Monitor:

ODOT Jon Milesky, PE, PS 505 South SR. 741 Lebanon, OH 45036 Include Original and Two complete copies of the Contractor or Consultant’s Invoice with all pertinent support documentation.

30

Project Close Out

slide-16
SLIDE 16

10/21/2016 16

31

Project Closeout

  • Once the contractor completes the project to the satisfaction of

the CPE/Person in Responsible Charge a final inspection shall be completed within 10 days.

  • Final Inspection Team should include –
  • CPE / LPA Person in Responsible Charge
  • ODOT CM / Jon Milesky
  • Contractor – Invited but not required
  • If applicable, a punch list shall be included in the final inspection

report.

32

Project Closeout

  • Prepare and Self Audit Contract Quantities and Materials

documentation.

  • Do you have sufficient Support Documentation for final

quantities? For every Line item?

  • List of approved final quantities sent to Contractor for

concurrence

  • Final Change Order for adjustments
  • Final Material Acceptance
  • Review project testing and acceptance records to support each

final quantity

slide-17
SLIDE 17

10/21/2016 17

33

Project Closeout

Final Report to ODOT should include:

  • Final Invoice(s) which reconciles individual pay items to final

quantities (Always Required) even if there is $0.00 reimbursement remaining from ODOT/FHWA

  • District Construction Inspection Report (Jon)
  • Affidavit of DBE/EDGE Subcontractor (Appendix R)
  • Final Completion Report from LPA (Appendix P)
  • All Final paperwork including payment requests and invoices need

to be completed within 6 Months of The Work Completion Date. ( Don’t make it ODOT’s problem to remind you )

34

Contract Administration:

Opportunities for Improvement Regular Communication from (LPA) PE’s/PM’s to ODOT Construction Monitor.

Schedule and perform regular meetings as required. Give District CM’s weekly or bi-weekly status updates on your project. (Emails works best.) Use the proper PID# when sending correspondence to ODOT. Close out projects in a timely manner.

This doesn’t mean June or July of the following year.

slide-18
SLIDE 18

10/21/2016 18

Main sources of information specific to LPA Projects:

Local Programs Home Page

http://www.dot.state.oh.us/Divisions/Planning/LocalPrograms/Pages/default.aspx

LPA Construction Contract Administration

http://www.dot.state.oh.us/DIVISIONS/CONSTRUCTIONMGT/LPACONSTRUCTIONCONTRACTADMINISTRATION/Pages/LPAConstructionContract Administration.aspx

Other Reference Sites:

ODOT 2016 Construction and Materials Specifications

http://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/2013-Online-Spec-Book.aspx

ODOT 2016 Construction Inspection Manual of Procedures- step by step inspection guide

http://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Pages/2013-Manual-of-Procedures.aspx

Materials and Testing Info:

C&MS 700 Section: Material Requirements Matrix

http://www.dot.state.oh.us/Divisions/ConstructionMgt/OnlineDocs/Specifications/2013CMS/700/700.htm

Office of Materials Management- Approved sources, Certified Suppliers, QPL items, etc.

http://www.dot.state.oh.us/Divisions/ConstructionMgt/Materials/Pages/default.aspx

Local Let Material Procedures, Guidelines, and Documents

http://www.dot.state.oh.us/Divisions/ConstructionMgt/Materials/Pages/Localprojects-Rev.aspx

2010 Sampling and Testing Manual

http://www.dot.state.oh.us/Divisions/ConstructionMgt/Materials/STM2010/Forms/PUBLIC.aspx

Miscellaneous:

Division of Planning/ Office of Estimating

ODOT Historical Bid Items- State Average Prices, Comparable Bid info

http://www.dot.state.oh.us/Divisions/Planning/Estimating/Pages/Bid_Histories.aspx

PW, EEO and DBE information

http://www.dot.state.oh.us/Divisions/ContractAdmin/Contracts/Pages/DBE.aspx

36

Questions