Liaison Group 18 June 2014 Shirley Kilcullen Charging for - - PowerPoint PPT Presentation

liaison group 18 june 2014 shirley kilcullen charging for
SMART_READER_LITE
LIVE PREVIEW

Liaison Group 18 June 2014 Shirley Kilcullen Charging for - - PowerPoint PPT Presentation

Liaison Group 18 June 2014 Shirley Kilcullen Charging for Harmonics What is Connection Charging Recovery of shallow connection asset capital costs associated with customer connections. Focuses on transmission assets required


slide-1
SLIDE 1

Liaison Group – 18 June 2014 Shirley Kilcullen

Charging for Harmonics

slide-2
SLIDE 2

What is Connection Charging

  • Recovery of “shallow” connection asset capital

costs associated with customer connections.

  • Focuses on transmission assets required up to

the meshed system.

  • Governed by a number of policy documents

which set out high level principles for the assigning of costs.

slide-3
SLIDE 3

Connection Charging: Basics

  • Focus on determining causation and drivers of

specific works.

  • Charging applied on an LCC basis.
  • Assets which are not driven exclusively by a given

customer/subgroup are considered “deep” and recovered via TUoS tariffs.

  • Assets which are driven exclusively by a given

customer/subgroup even if considered “deep”, should be paid for by the customer/subgroup.

  • Rebates - payable where customers connect to

assets which were funded by pre-connected parties.

slide-4
SLIDE 4

Harmonics issues in a charging context

  • Per policy, customers should be charged for

deeps required to mitigate against harmonic issues arising due to CP UGC.

  • If harmonic solutions are optimised on a

geographic basis, are deep in the system and mitigate harmonics for a number of applicants, assigning causation and apportioning the cost of these solutions within SG’s is v difficult.

slide-5
SLIDE 5

Considerations

  • The charging approach needs to:

– Be fair and proportional. – Send a signal about the cost that cable requests impose on the system and inform customer decision making on that basis. – Be relatively simple to apply - not requiring a suite of “charging” power quality studies. – Be robust and enduring - not just solve issues with current Offer Process modifications. – Protect the interests of the TUoS customer.

slide-6
SLIDE 6

Options being considered

slide-7
SLIDE 7

Option 1: Charge for the actual solution implemented

  • Actual solution implemented charged in its entirety
  • n the basis of out-turn cost.

Pro:

  • Entirely cost reflective – TUoS fully protected.

Pro/Con:

  • Potential for optimisation but could impose undue

inflexibility & cause delays. Cons:

  • Extremely complex - v difficult to assign causation.
  • Rebating issues.
  • In SG, if a party “falls away” – TUoS wouldn’t cover

their share of charges for harmonics.

slide-8
SLIDE 8

Option 2: Apply a Least Cost approach

  • Apply an LCC type approach – e.g. std charge for a filter

bank at the point of connection to the meshed system where the connection exceeds harmonics limits. Pros:

  • Consistent with the LCC principle, pay for the lowest cost

solution to the problem, regardless of what is ultimately installed.

  • Charge more predictable.

Pro/Con:

  • Same optimisation considerations as Option 1.

Cons:

  • Same issues as for Option 1.
  • Potential TUoS exposure.
slide-9
SLIDE 9

Option 3: Apply a harmonics levy

  • Apply a levy on all customer requests for cable on a per

km UGC basis. Pros:

  • Reflects that harmonics issues are cumulative.
  • Clear & transparent - avoids rebating and SG cost

allocation issues. Cons:

  • Customers that request cable in an area of low

underlying harmonics would pay the same as in high areas, unless a “postcode” approach was applied.

  • € per km levy = a function of a number of variables each
  • f which has potential for inaccuracy.
  • V difficult to derive an accurate € per km levy without

time limits for customer requests for UGC.

slide-10
SLIDE 10

Option 4: Recover via TUoS

Pros:

  • Ease of implementation.
  • Recognises cumulative nature of harmonics issues.
  • No rebating required or issues with assigning

causation. Cons:

  • Shields customers requesting UGC from full

incremental cost.

  • Totally misaligned with principle of Clause 5.4 of the

CMS.

slide-11
SLIDE 11

Proposed scope

  • Apply charging decision –

– To all customers who have already been put on notice re this issue via holding statements in their connection agreements and – To all customers who request UGC after the date of publication

  • f the harmonics consultation paper (13/06/14)
slide-12
SLIDE 12

Next steps

Comments welcome re 4 charging

  • ptions and any alternatives by

18/07/14

slide-13
SLIDE 13