Leveraging Technology to Design + Deliver Manufactured Construction - - PowerPoint PPT Presentation

leveraging technology to design deliver manufactured
SMART_READER_LITE
LIVE PREVIEW

Leveraging Technology to Design + Deliver Manufactured Construction - - PowerPoint PPT Presentation

Leveraging Technology to Design + Deliver Manufactured Construction in Healthcare Manufactured Construction 101 Erika Washington Director, Alberta Infrastructure, Edmonton Region Kristin Moore Director of Healthcare, DIRTT June 2 nd


slide-1
SLIDE 1

Leveraging Technology to Design + Deliver Manufactured Construction in Healthcare Manufactured Construction 101

June 2nd 2016, Vancouver BC

Erika Washington – Director, Alberta Infrastructure, Edmonton Region Kristin Moore – Director of Healthcare, DIRTT

slide-2
SLIDE 2

Conventional Construction

slide-3
SLIDE 3

Changing Behaviours - Prefab

slide-4
SLIDE 4

Changing Behaviours - Prefab

slide-5
SLIDE 5

Changing Behaviours – Yet Interiors Still Stick Built

slide-6
SLIDE 6

CUSTOM CONSTRUCTION MASS PRODUCTION What if Interiors Were the Best of Both Worlds?

slide-7
SLIDE 7

CUSTOM CONSTRUCTION MASS PRODUCTION MANUFACTURED CONSTRUCTION What if Interiors Were the Best of Both Worlds?

slide-8
SLIDE 8

Manufactured Approach – Leverage Technology

3week

target (or better)

slide-9
SLIDE 9

Disruptive Technology - ICE

9

PICTURE OF THE DIFFERENT OUTPUTS OF ICE

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

12

slide-13
SLIDE 13

13

slide-14
SLIDE 14

Manufactured Approach – Fully Integrated BIM Platform

slide-15
SLIDE 15

Construction Sequencing

slide-16
SLIDE 16

The Space 20,000 sq. ft. empty graded slab on the 1st floor of a five floor building Design called for 35 rooms including exam rooms, offices, utility rooms, storage, staff lounge, conference and lobby DIRTT solution included Walls, Millwork, and Power

slide-17
SLIDE 17

The Build – April 2nd

Rough Space Preparation + Trenching for Drains

slide-18
SLIDE 18

The Build – April 6th

With the trenching filled in, core and shell materials are staged.

slide-19
SLIDE 19

The Build – April 10th

The conventional walls for 10% of space laid out and bulkhead framing commences. MEP starts.

slide-20
SLIDE 20

The Build – April 20th

Conventional framing is complete, and conventional electrical is roughed in.

slide-21
SLIDE 21

The Build – May 7th

Gyprock, mud, sanding and primer commence on conventional walls. .

slide-22
SLIDE 22

The Build – May 17th

Plenum layout is complete, ceiling grid is installed, insulated plumbing for clinic’s entire water supply complete and capped above sink locations, vent stacks are complete and floor covering starts.

slide-23
SLIDE 23

The Build – May 20th

Flooring installed. Not cutting around stud construction – less material waste, less labour required

slide-24
SLIDE 24

The Build – May 26th

DIRTT insulated frames are delivered to the site and are immediately stood in place. DIRTT Power for both medical and utility are already engineered within the walls.

slide-25
SLIDE 25

The Build – June 6th

DIRTT Walls and Power are connected, linked and leveled. Walls tiles are installed, plumbing is run vertically to plenum, electrical connections are wired to the building, sound masking is installed, ceiling tile is dropped in place and lighting is connected

slide-26
SLIDE 26

The Build – June 29th

The space is complete! All cable and IT infrastructure are installed and tested, sinks hung and connected, equipment mounted, millwork installed, mechanical balanced, doors hung with hardware and artwork is installed

slide-27
SLIDE 27

The Build – July 1st

slide-28
SLIDE 28

Children’s Hospital of Colorado Multi Disciplinary Clinic, Denver CO

slide-29
SLIDE 29

29

Children’s Hospital of Colorado Multi Disciplinary Clinic, Denver CO

slide-30
SLIDE 30

Cost

Conventional Manufactured Construction

slide-31
SLIDE 31

Cost

Conventional Manufactured Construction

slide-32
SLIDE 32

Cost

Conventional Manufactured Construction

slide-33
SLIDE 33

33

DD Budget with Manufactured Construction $2,382,866

Final Pricing $2,229,699

SD Budget Conventional $2,443,342

slide-34
SLIDE 34

34

Total Savings : $213,643 or 8.7% of construction costs

slide-35
SLIDE 35

Savings

.

Additional Benefits

  • Trash hauling reduced by 55%
  • Construction waste reduced by 65%
  • Smart planning reduced construction schedule by 20% or more
  • Construction work flow efficiencies increased
  • Promoted LEAN construction and maximized Integrated Project Delivery
  • Trade efficiencies – 110 minutes per trade person per day – 23% productivity increase
  • Architectural RFIs from GC decreased by 50% = less time required by GC and architect
  • Realistic construction cost savings between 5% and 12%
  • Pre-fab interior construction reduced damages to architectural finishes by 65%
  • Punch list reduced by 60%, saving GC and architect non-billable hours for additional

time/trips

slide-36
SLIDE 36

Ease of Access

slide-37
SLIDE 37

Supporting the Environment From the Wall

slide-38
SLIDE 38

Supporting the Environment in the Wall

slide-39
SLIDE 39

Integrating Technology

slide-40
SLIDE 40

Product Neutral

slide-41
SLIDE 41

41