manufactured system design
play

Manufactured System Design w w w. t r a n s p o r t a t i o n . o h - PowerPoint PPT Presentation

Manufactured System Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 1 Manufactured Systems L&D Vol. 2 Section 1117.1 Provides quality treatment only w w w. t r a n s p o r t a t i o n . o h i o . g o v 2 Manufactured System


  1. Manufactured System Design w w w. t r a n s p o r t a t i o n . o h i o . g o v 1

  2. Manufactured Systems L&D Vol. 2 Section 1117.1 Provides quality treatment only w w w. t r a n s p o r t a t i o n . o h i o . g o v 2

  3. Manufactured System Treatment Processes w w w. t r a n s p o r t a t i o n . o h i o . g o v 3

  4. Design Process Treatment Goals Siting Analysis Manufactured System Sizing Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 4

  5. Design Process Treatment Goals Siting Analysis Manufactured System Sizing Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 5

  6. Project Example Intersection improvement Add turn lane All within existing right-of-way w w w. t r a n s p o r t a t i o n . o h i o . g o v 6

  7. Project Example w w w. t r a n s p o r t a t i o n . o h i o . g o v 7

  8. Project Example – Treatment Goals Project EDA = 2.28 ac All within existing right-of-way A ix = 2.28 ac; A in = 0.0 ac T% = [(A ix x 20)+(A in x 100)] / (A ix + A in ) T% = [(2.28 x 20)+(0.0 x 100)] / (2.28 + 0) T% = 20% 20% x 2.28 ac = 0.46 ac w w w. t r a n s p o r t a t i o n . o h i o . g o v 8

  9. Project Example – Treatment Goals Project EDA = 2.28 ac >= 1 ac Need a post-construction BMP All redevelopment Need to treat 0.46 ac (20%) All in existing right-of-way All existing right-of-way considered impervious Therefore no “new impervious area in new permanent right-of-way” Water quality treatment only required w w w. t r a n s p o r t a t i o n . o h i o . g o v 9

  10. Design Process Treatment Goals Siting Analysis Manufactured System Sizing Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 10

  11. Siting Analysis Manufactured systems near storm sewers Avoid underground utilities Avoid pipes at depths greater than 10 ft Avoid trunk lines (pipes with WQ F greater than 6 cfs) Site system outside of paved areas for maintenance w w w. t r a n s p o r t a t i o n . o h i o . g o v 11

  12. Footprint w w w. t r a n s p o r t a t i o n . o h i o . g o v 12

  13. Maximum Depth w w w. t r a n s p o r t a t i o n . o h i o . g o v 13 Contech CDS Model 4045-8-C

  14. Maximum Depth w w w. t r a n s p o r t a t i o n . o h i o . g o v 14 Image: Contech

  15. No Trunk Lines w w w. t r a n s p o r t a t i o n . o h i o . g o v 15

  16. Siting Analysis Tributary area = 12.42 ac Trib. Area within R/W = 1.94 ac w w w. t r a n s p o r t a t i o n . o h i o . g o v 16

  17. Design Process Treatment Goals Siting Analysis Manufactured System Sizing Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 17

  18. Manufactured System Sizing Design after January 2019 Water Quality Flow (WQ F ): Q = CiA Calculate time of concentration to determine i T c = overland + shallow conc. + pipe flow T o = 16 min T s = 7 min T p = 2 min T c = 16 + 7 + 2 = 25 min w w w. t r a n s p o r t a t i o n . o h i o . g o v 18

  19. w w w. t r a n s p o r t a t i o n . o h i o . g o v 19

  20. Manufactured System Sizing Design after January 2019 Water Quality Flow (WQ F ): Q = CiA C = 0.41 i = 1.13 in/hr A = 12.42 ac. WQ F = 0.41 * 1.13 in/hr * 12.42 ac WQ F = 5.75 cfs ODOT Type 4 w w w. t r a n s p o r t a t i o n . o h i o . g o v 20

  21. Manufactured System Sizing w w w. t r a n s p o r t a t i o n . o h i o . g o v 21

  22. w w w. t r a n s p o r t a t i o n . o h i o . g o v 22

  23. BMP Calcs Spreadsheet w w w. t r a n s p o r t a t i o n . o h i o . g o v 23

  24. Design Process Treatment Goals Siting Analysis Manufactured System Sizing Other Considerations w w w. t r a n s p o r t a t i o n . o h i o . g o v 24

  25. Sample Plan Note W103 w w w. t r a n s p o r t a t i o n . o h i o . g o v 25

  26. Manufactured System Considerations Vacuum truck maintenance every 4 – 12 months Access and safety for maintenance crew Need to close lanes Max. depth of vac truck suction (~20 ft) Max. flow 6 cfs May need to separate off-site flows w w w. t r a n s p o r t a t i o n . o h i o . g o v 26

  27. Manufactured System Considerations ODOT Qualified Products List – 31 Products Manufactured Water Quality Structure (SS- 995) Advance Drainage AquaShield Bio Clean Contech Environment 21 Hydro Int. All hydrodynamic separators w w w. t r a n s p o r t a t i o n . o h i o . g o v 27

  28. Manufactured System Considerations Some Cartridge Filters: 80% TARP TSS Distribution Hydrodynamic Separators: 80% ODOT Sand, 50% TARP Catch Basin Inserts: May Capture > 200 microns Cartridge (Contech) Hydro. Sep. (Contech) Basin Insert (Contech) w w w. t r a n s p o r t a t i o n . o h i o . g o v 28

  29. Research: Particle Size Distribution w w w. t r a n s p o r t a t i o n . o h i o . g o v 29 Image: 3P Technik UK

  30. Research: Particle Size Distribution Sediment Particle Distributions 100 90 NJDEP 80 Test Percent Finer 70 US Silica 60 OK110 50 40 US Silica 30 F110 20 80% TSS 10 Removal 0 1 10 100 1,000 Particle Size (µm) w w w. t r a n s p o r t a t i o n . o h i o . g o v 30

  31. Questions ? Jon Prier, P.E. jonathan.prier@dot.ohio.gov 614-644-1876 w w w. t r a n s p o r t a t i o n . o h i o . g o v 31

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend