lesson learnt from last
play

Lesson Learnt From Last Assessment & Response ND Incidents - PowerPoint PPT Presentation

Lesson Learnt From Last Assessment & Response ND Incidents Bamyan Province April 2016 Assessment of villages per time threshold Heavy Rainfall & Flood - April 2016 Assessment Timeliness Total No affected villages 58 Time


  1. Lesson Learnt From Last Assessment & Response ND Incidents – Bamyan Province April 2016

  2. Assessment of villages per time threshold Heavy Rainfall & Flood - April 2016 Assessment Timeliness Total No affected villages 58 Time Threshold Waras Panjab Shibar Bamyan Center Total Precentage 11-15 0 8 0 0 8 14% 6-10 16 1 3 2 22 38% 1-5 1 13 0 14 28 48% Challenges: • Wrong initial information (Assessment initiated based on petitions received by ANDMA) • Late call of PDMC/DDMC meetings • Low participations to RAF by Government and NGOs • Remoteness of areas

  3. Affected vs non Affected village Assessment per affected vs Non Affected villages Waras Panjab Shibar Bamyan Center Total Precentage Non Affected vlg 10 1 0 8 19 33% Affected vlg 7 21 3 8 39 67% IOM, IR, SCI, SI, ARCS, IR, IOM, SCI, ARCS, IR, IOM, SCI, ARCS, IR, IOM, SCI, ADRA, Action Aid, Action Aid, FAO, 3Ws Medair, AKF, OHW, AKF, OHW, MOVE, CRS, FAO, AKF, OHW, AKF, OHW, MOVE, MOVE, Baran Baran Baran, Shohada, Baran MOVE, Challenges: • Wrong initial Information's • Affected villages are not prioritized

  4. Response Timeliness Response Timeliness Time Threshold Waras Panjab Shibar Bamyan Center Total Precentage 21-25 7 13 0 0 20 51% 16-20 0 1 3 0 4 10% 11-15 0 7 0 7 14 36% 5-10 0 0 0 1 1 3% Challenges: • Late compile of RAF • Uncomplete RAFs received by partners • Delay of response by authority

  5. Recommended Solutions Recommended Solutions Challenges: WHO Assessment Response Wrong initial information (Assessment initiated based Prioritized petitions - ANDMA on petitions received by ANDMA) Late call of PDMC/DDMC meetings Ontime call of meetings ANDMA Low participations to RAF by Government and NGOs/ Pro-active in allocating resources for Partners Low resources undertaking assessment Remoteness of areas Increasing participations Early informing of beneficiaries ANDMA/ DDMC . Providing of complete RAFs Late compile of RAF IOM . Access to MS-RAF DB . Partners to submit correct and Uncomplete RAFs received by partners Partners complete RAFs . Response coordination meeting and Delay of response by authority ANDMA developing joint response plan

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.