Leisure Centre Complex and Bu Project Delivery Level Governan Establishment of Project Workin Presentation to Steering Group 5th March 2018 us Station Project nce ing Groups p and Programme Board
1
Leisure Centre Complex and Bu us Station Project Project Delivery - - PowerPoint PPT Presentation
Leisure Centre Complex and Bu us Station Project Project Delivery Level Governan nce Establishment of Project Workin ing Groups Presentation to Steering Group p and Programme Board 5 th March 2018 1 Contents 1) What are we changing ? 2)
1
2
g Group
gramme emain as
3
Leisure Centre Operator Procurement Leisure Centre Build
Bus Station Build Bus Station Lease Arrangements
Interim Bus Arrangements Remaining Site
4
Long Distances Coaches
g Group
emain as
5
(incl Bus Station Lease and Long distances coaches)
Project Manager : Andrew Goulbourne Client Lead : Jo Yelland
Operator Procurement Remaining Site
Project Manager : Mike Carson Client Lead : Karime Hassan Programme Manager : Justin Pickford Invited Members : Cllr Edwards Cllr Bialyk Cllr Denham Cllr Pearson Programme Manager : Justin Pickford Invited Members : Cllr Edwards Cllr Sutton
Leisure Centre Build Interim Bus Station
Project Manager : Phil Lewis Client Lead : Jo Yelland Programme Manager :
Project Manager : Iain McNeill Client Lead : Karime Hassan
Programme Manager : Justin Pickford Invited Members : Cllr Bialyk Cllr N Vizard
Programme Manager : Justin Pickford Invited Members : Cllr Bialyk Cllr Wardle Bus Station Build (Incl Bus
Station Lease & Long distance coaches)
PM & Prog Man : As above
(Supported by Mike Carson)
Client Lead : Karime Hassan Invited Members : Cllr Bialyk Cllr Wardle
7
8
9
10
This will include:
design
available in the current market (including entering into a P to collaboratively agree outputs) as deemed necessary by
required contingency, risks and programme
exercise and agreed interface works, will need to be broug
s to procure the Bus and Leisure Centres based upon the agreed s to procure the Bus and Leisure Centres based upon the agreed value cost, programme and risk profile for the construction Pre Construction Activity Agreement with the preferred contractor y the PM. ter into a build contract highlighting cost, potential cost and tendered, as subsequently amended by the previous tender ght to the Programme Board for consideration and approval.
11
Enabling works objective is to reduce the risks associated with the likely to be, but not limited to the following:
The final scope of enabling works will be those deemed necessary deliverable within the programme. The PM will then return to Progr construction contract award.
e project for both the Client and the contractor. Identified works are y by the PM to reduce significant risk within final contract scope, ramme Board in October with recommendation for final
12
13
14
Devise and deliver a programme to procure a leisure operato portfolio, in accordance with the requirements of PCR 2015 Inclusive of the following elements, using the professional ju Establish the key deliverables Design and deliver the procurement programme in coordination Lead on the identification and management of project risks, liais Manage the delegated budget for the project, and maintain a cos control Appoint consultants and legal advisors as necessary to deliver Oversee the drafting of a bespoke high quality leisure contract, stakeholder expectations (based upon the SE template, as best Produce the tender documentation to accompany the tender, inc methodology and appointment of individuals to the tender evalu
udgement of the project manager: n with other PM’s and the Project Coordinator ising with colleagues/risk owners as necessary st plan, whilst remaining accountable for effective financial the project, in accordance with ECC procurement rules , inclusive of a detailed service specification, in line with t practice) nclusive of baseline commercial terms, tender evaluation uation process.
15
energy efficiency and capital investment at Riv
2) Return to Programme Board in Summer 2018 for 3) Update the steering group regarding the progres gateways, or as otherwise necessary 4) Return to the Steering Group/ Programme Board
bidder 5) Lead on the deliver of the point appointment pro establishing baseline positions, handovers, fac
g the dialogue stage of the procurement exercise. successful leisure operator in terms of improving verside Leisure Centre
r consent to go to the market, with the draft tender pack ss of the multi stage procurement exercise, at project d (Programme Board/Executive/Council) with the
cilities inductions etc.
17
18