Long-Baseline Neutrino Facility LBNF
LBNF Horns Update Cory Crowley BIWG December 05, 2019 Outline - - PowerPoint PPT Presentation
LBNF Horns Update Cory Crowley BIWG December 05, 2019 Outline - - PowerPoint PPT Presentation
LBNF Long-Baseline Neutrino Facility LBNF Horns Update Cory Crowley BIWG December 05, 2019 Outline Horn A Design Status Horn Design Considerations for B & C Module Design Status Upcoming Work 12.05.19 Cory Crowley | LBNF
LBNF
Outline
12.05.19 Cory Crowley | LBNF Horns Update 2
- Horn A Design Status
- Horn Design Considerations for B & C
- Module Design Status
- Upcoming Work
LBNF
Horn Design – Horn A FEA
3
- Inner & Outer Conductors Analyzed Last Year
– Acceptable max temperatures of 65C & min S.F. of 2.2 w/6061-T6. Increase to 2.8 w/6013-T6 due to fatigue life increase (124MPa vs. 97MPa). – Should take advantage of better materials on inner conductor & high-stress stripline regions.
- Stripline
– Analyzed for temperature & stress concerns, basic modal
- analysis. Must be experimentally tested & verified.
FEA Credit: Zhijing Tang / Ang Lee
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Revision in Progress
4 12.05.19 Cory Crowley | LBNF Horns Update
Make this 400mm?
- Requested change per RAL integration meeting 12/4/19.
- John Back is currently analyzing & this will likely be a reality by next
week.
LBNF
Still Gauging Impact of Updates
5
- Most significant update is different target design.
– Shorter target length (~150cm) & no D.S. target mount needed. – Cone transition on U.S. end (which horn A must mimic) to reduce deflection.
- Should reduce horn EDEP further on D.S. end where most problematic.
- Stress / erosion concerns arose after NuMI Horn prototype disassembly.
– Found that wear resistant nickel coating wore through in several areas.
- Horn A inner conductor changed from 2mm thick to 2.5mm thick to allow
more material for stress distribution / reduced joule heating / Safety Factor.
- Endcap had to be stiffened throughout analysis iterations due to high
magnetic stresses from 300kA pulse.
- Thicker wall also helps keep circularity requirements due to 30cm
diameter cone on U.S. end & keep conservative design with unknown erosion effects, 300kA pulse, variability in cooling, etc…
- Still need to document heat input into horn A I.C. from hot target tube.
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Horn Design – Current Design Status (Horn A)
6 12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Horn Design – Current Design Status (Horn A)
7 12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Horn A Design Prototypes – Water Ports
8
- LBNF Horns pursue a revision of port design as
compared to NuMI / BNB. Different from T2K as well.
- Small footprint, inexpensive, immediate assembly,
higher pressure rating, & reduced component count.
- Required prototype testing in preparation for design
review & to verify resilience of concept.
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Horn A Design Prototype – Conductor Supports
9
- Conductor supported by 3 rods in tension as opposed to compression.
- Tension method required for larger horns due to L^2 term in critical
buckling denominator. ~1.5m diameter horns would need large spacers if using available designs.
- Desire to make a resilient, minimal mass, universal conductor support.
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Horn A Design Prototype – Conductor Supports
10
- Prototype / Design Advancement
– Full thermal, stress / cyclic fatigue, & water flow analysis. – Built mockup for technician assembly training / design review aid. – Electrical analysis remains for ~800V.
Print Credit: Quinn P. FEA Credit: Ang Lee & Jacob Kintner
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Horn Design – Considerations for Horns B & C
11
Max V @PS Max Allow. E Field Max Isolator Path Length Potential Horn A ΔV Horn B ΔV Horn C ΔV ~3700V 35V/.001” 5V/.001” ~550V ~1550V ~1050V
EE Credit: Ken Quinn
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Horn Design – Horns B & C FEA
12
- Inner & Outer Conductors
– Very resilient designs utilizing 6061-T6. Max conductor temp 28C, need to incorporate equalization sections (80C) into actively cooled conductor volume.
- Stripline
– Analyzed temperature & stress, basic modal analysis. Must also be experimentally tested & verified. B & C design should be a mirror.
FEA Credit: Zhijing Tang / Ang Lee
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Design Plan
13 12.05.19 Cory Crowley | LBNF Horns Update
- Would like to confirm:
– Outer conductor diameter is large enough that incorporation of equalization sections has no impact. – Flaring of I.C. to reach O.C. outside of advertised focal length has trivial impact on physics.
- Good models will take a little time, but I could provide dimensions for
flux simulations that would be on par with what Laura used for
- ptimization effort. Is this of use? Or better to wait?
LBNF
Module Design – Horn Integration
14
- Mainframe Placement
– Endwalls & stripline shielding block (SLB).
- Challenging SLB Connection
– Increased clamping surface area. – Increased voltage potential at Horn C (3.7kV). – Increased reusability / resilience.
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Module Design – Horn & Target Integration
15
- Challenges
– SLB Connection – Utility feedthroughs – Voltage Issues – More and more and more…..
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Module Design – Mainframe & Motion Control
16
- Construction
– Plate frame, pinned & bolted. – Select areas of stainless steel where required. – Allows for ¾” gap to all shield blocks for remote alignment of horn. – Designed for life of facility.
- Motion Control Concept
– Simple sliding block & pad joints for horizontal translation. – Vertical actuation internal to module mainframe.
Design Credit: Mike Campbell
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Major Push: Standardization of Ancillary Structures
17
- Everything needs to have identical distance to beam centerline.
– Stripline block pads. – Carriage Support Beams. – Stripline Connection Point to Horns.
12.05.19 Cory Crowley | LBNF Horns Update
LBNF
Working Towards Improving Cartoons
18
- Engineering placeholders need to be improved.
– Conductor Profiles – Stripline Design – Water tanks – Connections to Modules
12.05.19 Cory Crowley | LBNF Horns Update
Design Credit: Mike Campbell
LBNF
Summary
19
- Horn & Support Structure design progressing according to plan.
- Roughly 1 year remaining on final design of Horn A, followed by
fabrication start of conductors & stripline components.
- Anticipating additional prototyping:
- Critical stripline ceramics (~1000+).
- Horn A + Stripline.
- Horn B & C Stripline.
- Need to advance Horn B & C conductor design to help advance
target chase / modules / simulations...
- Likely going to re-analyze Horn A stripline due to design
changes, but Horn A conductor analysis still valid after transition to cone on U.S. end. Should be judicious with FEA (Time / $$$).
- What should I provide? Horn B & C revised equalization specs?
12.05.19 Cory Crowley | LBNF Horns Update