lbnf horns update
play

LBNF Horns Update Cory Crowley BIWG December 05, 2019 Outline - PowerPoint PPT Presentation

LBNF Long-Baseline Neutrino Facility LBNF Horns Update Cory Crowley BIWG December 05, 2019 Outline Horn A Design Status Horn Design Considerations for B & C Module Design Status Upcoming Work 12.05.19 Cory Crowley | LBNF


  1. LBNF Long-Baseline Neutrino Facility LBNF Horns Update Cory Crowley BIWG December 05, 2019

  2. Outline • Horn A Design Status • Horn Design Considerations for B & C • Module Design Status • Upcoming Work 12.05.19 Cory Crowley | LBNF Horns Update 2 LBNF

  3. Horn Design – Horn A FEA FEA Credit: Zhijing Tang / Ang Lee • Inner & Outer Conductors Analyzed Last Year – Acceptable max temperatures of 65C & min S.F. of 2.2 w/6061-T6. Increase to 2.8 w/6013-T6 due to fatigue life increase (124MPa vs. 97MPa). – Should take advantage of better materials on inner conductor & high-stress stripline regions. • Stripline – Analyzed for temperature & stress concerns, basic modal analysis. Must be experimentally tested & verified. 12.05.19 Cory Crowley | LBNF Horns Update 3 LBNF

  4. Revision in Progress • Requested change per RAL integration meeting 12/4/19. • John Back is currently analyzing & this will likely be a reality by next week. Make this 400mm? 12.05.19 Cory Crowley | LBNF Horns Update 4 LBNF

  5. Still Gauging Impact of Updates • Most significant update is different target design. – Shorter target length (~150cm) & no D.S. target mount needed. – Cone transition on U.S. end (which horn A must mimic) to reduce deflection. • Should reduce horn EDEP further on D.S. end where most problematic. • Stress / erosion concerns arose after NuMI Horn prototype disassembly. – Found that wear resistant nickel coating wore through in several areas. • Horn A inner conductor changed from 2mm thick to 2.5mm thick to allow more material for stress distribution / reduced joule heating / Safety Factor. • Endcap had to be stiffened throughout analysis iterations due to high magnetic stresses from 300kA pulse. • Thicker wall also helps keep circularity requirements due to 30cm diameter cone on U.S. end & keep conservative design with unknown erosion effects, 300kA pulse, variability in cooling, etc … • Still need to document heat input into horn A I.C. from hot target tube. 12.05.19 Cory Crowley | LBNF Horns Update 5 LBNF

  6. Horn Design – Current Design Status (Horn A) 12.05.19 Cory Crowley | LBNF Horns Update 6 LBNF

  7. Horn Design – Current Design Status (Horn A) 12.05.19 Cory Crowley | LBNF Horns Update 7 LBNF

  8. Horn A Design Prototypes – Water Ports • LBNF Horns pursue a revision of port design as compared to NuMI / BNB. Different from T2K as well. • Small footprint, inexpensive, immediate assembly, higher pressure rating, & reduced component count. • Required prototype testing in preparation for design review & to verify resilience of concept. 12.05.19 Cory Crowley | LBNF Horns Update 8 LBNF

  9. Horn A Design Prototype – Conductor Supports • Conductor supported by 3 rods in tension as opposed to compression. • Tension method required for larger horns due to L^2 term in critical buckling denominator. ~1.5m diameter horns would need large spacers if using available designs. • Desire to make a resilient, minimal mass, universal conductor support. 12.05.19 Cory Crowley | LBNF Horns Update 9 LBNF

  10. Horn A Design Prototype – Conductor Supports Print Credit: Quinn P. • Prototype / Design Advancement – Full thermal, stress / cyclic fatigue, & water flow analysis. – Built mockup for technician assembly training / design review aid. FEA Credit: Ang Lee – Electrical analysis remains for ~800V. & Jacob Kintner 12.05.19 Cory Crowley | LBNF Horns Update 10 LBNF

  11. Horn Design – Considerations for Horns B & C EE Credit: Ken Quinn Max V Max Allow. Max Isolator Path Horn A Horn B Horn C @PS E Field Length Potential ΔV ΔV ΔV ~3700V 35V/.001” 5V/.001” ~550V ~1550V ~1050V 12.05.19 Cory Crowley | LBNF Horns Update 11 LBNF

  12. Horn Design – Horns B & C FEA FEA Credit: Zhijing Tang / Ang Lee • Inner & Outer Conductors – Very resilient designs utilizing 6061-T6. Max conductor temp 28C, need to incorporate equalization sections (80C) into actively cooled conductor volume. • Stripline – Analyzed temperature & stress, basic modal analysis. Must also be experimentally tested & verified. B & C design should be a mirror. 12.05.19 Cory Crowley | LBNF Horns Update 12 LBNF

  13. Design Plan • Would like to confirm: – Outer conductor diameter is large enough that incorporation of equalization sections has no impact. – Flaring of I.C. to reach O.C. outside of advertised focal length has trivial impact on physics. • Good models will take a little time, but I could provide dimensions for flux simulations that would be on par with what Laura used for optimization effort. Is this of use? Or better to wait? 12.05.19 Cory Crowley | LBNF Horns Update 13 LBNF

  14. Module Design – Horn Integration • Mainframe Placement – Endwalls & stripline shielding block (SLB). • Challenging SLB Connection – Increased clamping surface area. – Increased voltage potential at Horn C (3.7kV). – Increased reusability / resilience. 12.05.19 Cory Crowley | LBNF Horns Update 14 LBNF

  15. Module Design – Horn & Target Integration • Challenges – SLB Connection – Utility feedthroughs – Voltage Issues – More and more and more….. 12.05.19 Cory Crowley | LBNF Horns Update 15 LBNF

  16. Module Design – Mainframe & Motion Control Design Credit: Mike Campbell • Construction – Plate frame, pinned & bolted. – Select areas of stainless steel where required. – Allows for ¾” gap to all shield blocks for remote alignment of horn. – Designed for life of facility. • Motion Control Concept – Simple sliding block & pad joints for horizontal translation. – Vertical actuation internal to module mainframe. 12.05.19 Cory Crowley | LBNF Horns Update 16 LBNF

  17. Major Push: Standardization of Ancillary Structures • Everything needs to have identical distance to beam centerline. – Stripline block pads. – Carriage Support Beams. – Stripline Connection Point to Horns. 12.05.19 Cory Crowley | LBNF Horns Update 17 LBNF

  18. Working Towards Improving Cartoons • Engineering placeholders need to be improved. – Conductor Profiles – Stripline Design – Water tanks – Connections to Modules Design Credit: Mike Campbell 12.05.19 Cory Crowley | LBNF Horns Update 18 LBNF

  19. Summary • Horn & Support Structure design progressing according to plan. • Roughly 1 year remaining on final design of Horn A, followed by fabrication start of conductors & stripline components. • Anticipating additional prototyping: - Critical stripline ceramics (~1000+). - Horn A + Stripline. - Horn B & C Stripline. • Need to advance Horn B & C conductor design to help advance target chase / modules / simulations... • Likely going to re-analyze Horn A stripline due to design changes, but Horn A conductor analysis still valid after transition to cone on U.S. end. Should be judicious with FEA (Time / $$$). • What should I provide? Horn B & C revised equalization specs? 12.05.19 Cory Crowley | LBNF Horns Update 19 LBNF

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend