SLIDE 1
Kuparuk Gas Lift Optimizer February 2006 Kenneth Lloyd Martin
SLIDE 2
- Kuparuk Production/ Gas Lift System
- Development of Model
- Operation
- Results
SLIDE 3
Kuparuk Kuparuk
SLIDE 4 Kuparuk Kuparuk Gas System Gas System
Drill Site Manifold
Gas Lift Compressors Gas Injection Compressors (MI)
1400 psi Separation
MI to injection wells at 3900 psi
Lift Gas to Wells
NGL’s
Central Production Facility
SLIDE 5
CPF3 Production Lines CPF3 Production Lines
SLIDE 6 Drill Sites and Wells Drill Sites and Wells
- 6 Drill Sites with automated gas lift chokes
- 9 Drill Sites with manual gas lift chokes
- About 160 gas lifted wells
- 1 ESP
- 4 Reverse-Flow Jet Pumps with water as
power fluid
SLIDE 7 Existing Method for Gas Lift Existing Method for Gas Lift Optimization Optimization
- Equal-Slope (IGOR) Method based on KWPS
“Rate Tables” (performance curves)
- Single target IGOR for all wells at each facility
(or by DS if automated)
- Board operator reviews “space”, changes
target IGOR on DS’s
- Trial and Error on rate using SCADA executed
calculation
See 2003 ASME GL Kuparuk Presentation (Martin, Nations)
SLIDE 8
Rate Table Curves (PC Rate Table Curves (PC’ ’s) s)
SLIDE 9 Equal Equal-
- Slope Gas Lift Optimization
Slope Gas Lift Optimization (and allocation) (and allocation)
SLIDE 10 Project Scope Project Scope
- Build production gathering network model
- Include common lines & history match ∆P
- Incorporate well performance curves from KWPS
- Implement optimization to maximize oil rate
- Integrate network models with SCADA (SetCim) for
- n-line use
- Add temporary pressure instrumentation for tuning
SLIDE 11 Project Goal Project Goal
- To develop a near-real time system which
will increase Kuparuk production by modeling the surface hydraulics, which will in turn allow improved optimization of the current facilities.
- Provide a planning tool for maintenance,
debottlenecking, and expansion.
SLIDE 12 Project Plan Project Plan
- Develop single Drill Site model as test of
hydraulics and for vendor/company understanding of model
- Develop single Facility (CPF3) model and
test for results
- Develop CPF1 and CPF2 models and
planning tools
SLIDE 13 Project Execution Project Execution
– APA Petroleum Consultants
- Petroleum Experts Software
– GAP for Optimizer – OpenServer for data transfer – In-house KWPS for performance curves
– Glacier Services
- In-house developments on SCADA
SLIDE 14
Operator Interface Operator Interface
SLIDE 15
Temperature Impacts Temperature Impacts
20F 20F 15 MMSCF 15 MMSCF
SLIDE 16
SLIDE 17
SLIDE 18 Optimization Run Optimization Run
– Water, Oil, Formation Gas, Total Gas – Individual well minimum/maximums
– Maximum Oil Rate
SLIDE 19
Setcim Setcim Engineer Engineer’ ’s COE s COE Machine Machine KIOS. KIOS. Office Office /GAP /GAP Principal Server Principal Server FTP Server FTP Server CPF3 Model Server CPF3 Model Server KIOS.MS KIOS.MS / GAP / GAP KIOS. KIOS. PS PS UDP UDP Control Room Control Room
SLIDE 20
SLIDE 21
SLIDE 22
SLIDE 23
SLIDE 24
SLIDE 25
SLIDE 26
Comparison of Upstream Pressures Comparison of Upstream Pressures
SLIDE 27
Planning Interface Planning Interface
SLIDE 28 Model Model Maint
- Maint. / Engineering Interface
. / Engineering Interface
SLIDE 29
SLIDE 30
SLIDE 31
SLIDE 32
Mapping Equipment Mapping Equipment
SLIDE 33
Well Data Well Data
SLIDE 34
SLIDE 35 Results Results
- Expectations
- Benefits
- Challenges
SLIDE 36 Kuparuk INM Benefit Predictions Kuparuk INM Benefit Predictions
- Vendor Predictions 8% to 15%
- Gas lift production increases achieved in other
automated fields using integrated models 1% to 3%
- Potential GKA Target:
- Internal predictions: 500-4000 BOPD increase
(0.25%-2.0%)
- CPF3 detailed project estimate 200 BOPD (0.4%)
SLIDE 37
Initial Install Benefit Initial Install Benefit
205 BOPD Predicted Benefit 205 BOPD Predicted Benefit
SLIDE 38 Oil Rate
30000 32000 34000 36000 38000 40000 42000 44000 46000 48000 50000 20-May 3-Jun 17-Jun 1-Jul 15-Jul 10 20 30 40 50 60 70 80 GASOPT KINM Temperature 24 per. Mov. Avg. (Temperature) Linear (KINM) Linear (GASOPT) SD-TAPS Proration-WW
First Install First Install
SLIDE 39
Going Going “ “to model to model” ” after 10 days off after 10 days off
165 BOPD 165 BOPD
SLIDE 40
Compression Utilization Compression Utilization
SLIDE 41 Other Benefits Other Benefits
- Identified well with high velocity through flowline,
likely erosion concerns
- Identified at least 10 wells and headers with
inaccurate instrumentation
- Provided estimates of impacts for new well drilling
- Used with Prosper for downhole choke designs
- Provided estimates of impacts of 3rd party facility
use
- Developed better visualization tool for operators.
- Identified loss in compressor rates due to forest
fire smoke
SLIDE 42
- Difficult mix: troubleshooting vs. confidence
- 90/10 rule is no joke
– 6 months from approval for CPF3 to initial install – Still debugging 8 months later!
Lessons Learned Lessons Learned
SLIDE 43 Project Difficulties Project Difficulties
– Change is smaller than hourly variation in field rate. – Step changes only work when going “to model”
- Unable to keep model tuned with existing
instrumentation – Drifts of up to 20 psi during periods of low gas rates – Requiring large investment in additional instrumentation
- Rapid optimization software version changes
– Significant time required to review version for “bugs” – Revisions are not all “backward-compatible”
SLIDE 44 Existing Challenges Existing Challenges
- Computing time is issue during rapid
temperature changes
- Sensitive to small errors in PC’s
- At low total gas rates, ignores minimum LG
requirements
- In new version, either minimum lift rate
constraint or allow SI not both
- Errors are difficult to trace because code is
proprietary so don’t know what’s “under the hood”
SLIDE 45 Major Expenditures Major Expenditures
- Optimization Developers
- Automation Developers
- Project Engineering
- Software
- Computers
- Pressure Gauges
SLIDE 46 Annual O&M Costs Annual O&M Costs
- Software Licenses
- Automation Maintenance
1 month/yr
1 month/yr
1 day/mo/CPF
- Engineering Well Models *
1 hr/day/CPF
4 mh/tr/3yr * Existing Cost
SLIDE 47 Successful? Successful?
- Met Benefit Estimate
- I/O with SCADA working well
- Better Operator Visualization
– Operator focus on compressor rates, in addition to “gas handling available”
- Long development-Ongoing troubleshooting
- Operator acceptance
SLIDE 48 Acknowledgements Acknowledgements
- CPF3 Production Staff
- Network Model User’s Group
- COP Knowledge Sharing Network Members
- APA Petroleum Engineering, Calgary and
Dallas
- Glacier Services, Joe Griffo/Alex Charyna
- Others at CPAI and BPXA