kendall bay sediment remediation project
play

Kendall Bay Sediment Remediation Project Community Information and - PowerPoint PPT Presentation

Kendall Bay Sediment Remediation Project Community Information and Feedback Session 29 July 2014 Presentation overview Project update Technical assessments for the Environmental Impact Statement preliminary findings Q and A 2


  1. Kendall Bay Sediment Remediation Project Community Information and Feedback Session 29 July 2014

  2. Presentation overview • Project update • Technical assessments for the Environmental Impact Statement – preliminary findings • Q and A 2

  3. Project update • Jemena Limited (Jemena) intends to secure development consent to remediate two defined areas within Kendall Bay bordering the former Mortlake Gasworks site • The key objectives of the Project are as follows: – Jemena to fulfil their obligations under their VRA with the EPA – to alleviate the current risk to human health associated with the contaminated sediments within the remediation areas – to alleviate adverse ecological impacts caused from the contaminated sediments 3

  4. Project update and timelines • Currently awaiting outcome of Jemena’s State Significant Development application as well as updated Environmental Assessment Requirements (EARs) • Subject to the above, it is planned to lodge the EIS during Sept 2014, to the Department of Planning & Environment (DP&E), for the test of adequacy • The EIS will subsequently be placed on public exhibition – proposed 4 th Quarter 2014 4

  5. Project area 5

  6. Impact assessment methodology Source: ERM 2012 6

  7. Technical studies for EIS Acoustic impact Hydrology assessment assessment Air quality/odour Landscape & visual impact assessment assessment Ecological impact Social impact assessment assessment Environmental hazard Soil & water assessment assessment Health risk assessment Traffic impact assessment Heritage impact assessment 7

  8. Summary of noise assessment Methodology 1. Baseline studies and data • Baseline noise monitoring (Sept 2012 and Nov/Dec 2013) to establish existing noise conditions at sensitive receptor locations • Noise source data collected for all project plant and equipment – noise modelling to assess impact of remediation works on background (existing) noise levels 2. Impact Assessment • Noise modelling across all project phases (site establishment, remediation and decommissioning) • Predicted noise levels compared against noise assessment criteria at sensitive receptor locations 3. Mitigation Measures • Appropriate mitigation/ management measures devised to manage impacts 8

  9. Summary of noise assessment Impact Mitigation Measures Significance of Impact with Mitigation • Implement best practice noise control The proposed works will result in an increase in noise at measures sensitive receptor locations • Community Consultation adjacent to Kendall Bay (5 – 15 • Noise Management Plan Moderate decibel increase) Noise levels remain under the maximum guidelines allowed for construction (75 decibels) • Community Consultation Traffic noise from heavy vehicle movements will be up to 1 • Noise Management Plan decibel above existing Minor • Limited construction Hours background noise levels 9

  10. Summary of air quality/odour assessment Methodology 1. Baseline studies and data • Baseline odour monitoring (early 2014) at sensitive receptor locations • Baseline sampling from sediments collected from remediation areas • Review of existing meteorological conditions to inform air quality modelling 2. Impact Assessment • Odour and dust dispersion model predicts odour and dust levels at sensitive receptor locations • Odour and dust levels compared against EPA assessment criteria at the sensitive receptor locations 3. Mitigation Measures • Appropriate mitigation/ management measures devised to manage impacts 10

  11. Summary of air quality/odour assessment Impact Mitigation Measures Significance of Impact with Mitigation • Odour control tent and pressurised Odour concentrations below the assessment criteria* industrial building identified at sensitive • Cap excavated area during extraction of receptor locations sediment in the exposed shoreline area Minor No emissions which are • Covered skip bin during marine transport detrimental to human health • Odour suppressant foam will be released during the remediation works • Dust suppressant sprays Dust concentrations below the assessment criteria^ at • Covered skip bin during marine based sensitive receptor locations transport Minor *Assessment criteria for odour is two units below the level set by the NSW EPA ^Assessment criteria for dust is two units below the level set by the NSW EPA 11

  12. Summary of transportation assessment Methodology 1. Baseline studies and data • Traffic counts undertaken over a seven day period at three locations: − Staging site (28 vehicle movements/day) − Tennyson Road (1,257 vehicle movements/day) − Hilly Street (1,183 vehicle movements/day) • Review of all public transport and pedestrian access in the vicinity to the Project 2. Impact Assessment • Assessment of traffic impact on local roads - volumes, safety and efficiency • Assess intersection impacts and level of service post project • Identification of preferred and alternative haulage routes • Assessment of cumulative traffic impacts associated with traffic volumes for future developments in Breakfast Point 3. Mitigation measures • Devise appropriate mitigation/ management measures 12

  13. Summary of transportation assessment Additional traffic from remediation works Stage Duration No. of Heavy Average Additional Vehicle Movements Heavy Vehicle per Day Movements per Day Site establishment ~3 months 11 1 movement per hour Remediation ~6 months 22 2 movements per hour Site De-mobilisation ~3 months 11 1 movement per hour 13

  14. Summary of transportation assessment Cumulative Impacts Location Anticipated Daily Proportion of Traffic Generation Additional Traffic Generation Staging Site Up to 22 heavy vehicle 1% movements per day Staging Site Up to 20 light vehicle 1% movements per day (construction workers) Surrounding Developments 2,014 vehicle movements 98% per day • The assessment of the cumulative volume of traffic generated from both the Project and the new developments in Stage 2 of Breakfast Point indicates the Project will create approximately 2% of the additional traffic on the surrounding road network 14

  15. Summary of transportation assessment Impact Mitigation Measures Significance of Impact with Mitigation • Construction Transportation Increase in heavy vehicle movements causing traffic, operational and/or Management Plan (CTMP) Negligible safety impacts • Traffic Control Plan (TCP) • CTMP 10 car spaces onsite will reduce to 5 - potential overflow in the vicinity of the • TCP Negligible staging site • Provision of additional on- site parking • No management/ mitigation Potential disruptions to local transport options/ routes in the vicinity of the measures identified Negligible staging site and wider Project Area • Notice to Mariners Disruptions to marine recreational use in Kendall Bay Negligible • Vessel speeds 15

  16. Summary of ecological assessment Methodology 1. Baseline studies and data • Review of literature including relevant database searches • Habitat assessment including two field surveys to identify threatened species, communities, benthic organisms, populations and their habitat 2. Impact Assessment • Assessment of Impacts on flora and fauna in accordance with NSW and Federal legislation and NSW Planning Instruments 3. Mitigation Measures • Appropriate mitigation/ management measures devised to manage potential impacts 16

  17. Summary of ecological assessment Options for mangrove stand in Remediation Area A Option 1 Option 2 Option 3 Retain all or part of the Remove the sediment Remove the mangroves mangrove stand while maintaining the and contaminated mangroves in situ sediment from remediation Area A Finding: Remediation cannot occur without removing/ damaging the existing mangrove colony. No practical solution is available to allow retention of mangroves and remediation of sediment on Area A. Option 3 is the only practical approach. Mitigation measures:  Develop a mangrove management plan to prepare area for biodiversity re- establishment and management of progress of mangrove re-colonisation  Monitor progress to employ adaptive measures if necessary 17

  18. Summary of ecological assessment Impact Mitigation Measures Significance of Impact with Mitigation • Marine habitat monitoring Impacts on threatened or protected fauna species from loss of preferred habitat plan Negligible • Mangrove management plan Physical loss of mangroves habitat Negligible • Re-establishment of mangroves • Water quality management Altered water quality as a result of the re- suspension of sediments during dredging plan Negligible • Use of silt curtains. Water quality impacts from accidental hydrocarbon spills from plant, equipment or Negligible • Visual inspection of pipeline pipeline failure • None identified Impacts to the seabed and marine ecology during removal of contaminated sediments Positive 18

  19. Q and A Session 19

  20. Thank you and close Next Steps • Display and presentation materials from the session will be uploaded to the website for broader interest • Await outcome of Jemena’s State Significant Development application as well as updated Environmental Assessment Requirements (EARs) (expected Q3 2014) • Subject to the above, EIS to be lodged Q3 2014 • Public Exhibition Q4 2014/ Q1 2015 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend