Kendall Bay Sediment Remediation Project Community Information and - - PowerPoint PPT Presentation
Kendall Bay Sediment Remediation Project Community Information and - - PowerPoint PPT Presentation
Kendall Bay Sediment Remediation Project Community Information and Feedback Session 29 July 2014 Presentation overview Project update Technical assessments for the Environmental Impact Statement preliminary findings Q and A 2
Presentation overview
- Project update
- Technical assessments for the Environmental Impact
Statement – preliminary findings
- Q and A
2
Project update
- Jemena Limited (Jemena) intends to secure development
consent to remediate two defined areas within Kendall Bay bordering the former Mortlake Gasworks site
- The key objectives of the Project are as follows:
– Jemena to fulfil their obligations under their VRA with the EPA – to alleviate the current risk to human health associated with the contaminated sediments within the remediation areas – to alleviate adverse ecological impacts caused from the contaminated sediments
3
Project update and timelines
- Currently awaiting outcome of Jemena’s State Significant
Development application as well as updated Environmental Assessment Requirements (EARs)
- Subject to the above, it is planned to lodge the EIS during
Sept 2014, to the Department of Planning & Environment (DP&E), for the test of adequacy
- The EIS will subsequently be placed on public exhibition –
proposed 4th Quarter 2014
4
Project area
5
Impact assessment methodology
6
Source: ERM 2012
Acoustic impact assessment Hydrology assessment Air quality/odour assessment Landscape & visual impact assessment Ecological impact assessment Social impact assessment Environmental hazard assessment Soil & water assessment Health risk assessment Traffic impact assessment Heritage impact assessment
7
Technical studies for EIS
Summary of noise assessment
Methodology
- 1. Baseline studies and data
- Baseline noise monitoring (Sept 2012 and Nov/Dec 2013) to establish
existing noise conditions at sensitive receptor locations
- Noise source data collected for all project plant and equipment – noise
modelling to assess impact of remediation works on background (existing) noise levels
- 2. Impact Assessment
- Noise modelling across all project phases (site establishment,
remediation and decommissioning)
- Predicted noise levels compared against noise assessment criteria at
sensitive receptor locations
- 3. Mitigation Measures
- Appropriate mitigation/ management measures devised to manage
impacts
8
9
Summary of noise assessment
Impact Mitigation Measures Significance of Impact with Mitigation
The proposed works will result in an increase in noise at sensitive receptor locations adjacent to Kendall Bay (5 – 15 decibel increase) Noise levels remain under the maximum guidelines allowed for construction (75 decibels)
- Implement best practice noise control
measures
- Community Consultation
- Noise Management Plan
Moderate Traffic noise from heavy vehicle movements will be up to 1 decibel above existing background noise levels
- Community Consultation
- Noise Management Plan
- Limited construction Hours
Minor
Summary of air quality/odour assessment
Methodology
- 1. Baseline studies and data
- Baseline odour monitoring (early 2014) at sensitive receptor locations
- Baseline sampling from sediments collected from remediation areas
- Review of existing meteorological conditions to inform air quality
modelling
- 2. Impact Assessment
- Odour and dust dispersion model predicts odour and dust levels at
sensitive receptor locations
- Odour and dust levels compared against EPA assessment criteria at
the sensitive receptor locations
- 3. Mitigation Measures
- Appropriate mitigation/ management measures devised to manage
impacts
10
Summary of air quality/odour assessment
11
Impact Mitigation Measures Significance of Impact with Mitigation
Odour concentrations below the assessment criteria* identified at sensitive receptor locations No emissions which are detrimental to human health will be released during the remediation works
- Odour control tent and pressurised
industrial building
- Cap excavated area during extraction of
sediment in the exposed shoreline area
- Covered skip bin during marine transport
- Odour suppressant foam
Minor Dust concentrations below the assessment criteria^ at sensitive receptor locations
- Dust suppressant sprays
- Covered skip bin during marine based
transport Minor
*Assessment criteria for odour is two units below the level set by the NSW EPA ^Assessment criteria for dust is two units below the level set by the NSW EPA
Summary of transportation assessment
Methodology
- 1. Baseline studies and data
- Traffic counts undertaken over a seven day period at three locations:
− Staging site (28 vehicle movements/day) − Tennyson Road (1,257 vehicle movements/day) − Hilly Street (1,183 vehicle movements/day)
- Review of all public transport and pedestrian access in the vicinity to the
Project
- 2. Impact Assessment
- Assessment of traffic impact on local roads - volumes, safety and efficiency
- Assess intersection impacts and level of service post project
- Identification of preferred and alternative haulage routes
- Assessment of cumulative traffic impacts associated with traffic volumes for
future developments in Breakfast Point
- 3. Mitigation measures
- Devise appropriate mitigation/ management measures
12
Additional traffic from remediation works
13
Stage Duration
- No. of Heavy
Vehicle Movements per Day Average Additional Heavy Vehicle Movements per Day Site establishment ~3 months 11 1 movement per hour Remediation ~6 months 22 2 movements per hour Site De-mobilisation ~3 months 11 1 movement per hour
Summary of transportation assessment
Summary of transportation assessment
Cumulative Impacts
- The assessment of the cumulative volume of traffic generated from both
the Project and the new developments in Stage 2 of Breakfast Point indicates the Project will create approximately 2% of the additional traffic
- n the surrounding road network
14
Location Anticipated Daily Traffic Generation Proportion of Additional Traffic Generation
Staging Site Up to 22 heavy vehicle movements per day 1% Staging Site Up to 20 light vehicle movements per day (construction workers) 1% Surrounding Developments 2,014 vehicle movements per day 98%
Summary of transportation assessment
15
Impact Mitigation Measures Significance of Impact with Mitigation
Increase in heavy vehicle movements causing traffic, operational and/or safety impacts
- Construction Transportation
Management Plan (CTMP)
- Traffic Control Plan (TCP)
Negligible 10 car spaces onsite will reduce to 5 - potential overflow in the vicinity of the staging site
- CTMP
- TCP
- Provision of additional on-
site parking Negligible Potential disruptions to local transport
- ptions/ routes in the vicinity of the
staging site and wider Project Area
- No management/ mitigation
measures identified Negligible Disruptions to marine recreational use in Kendall Bay
- Notice to Mariners
- Vessel speeds
Negligible
Summary of ecological assessment
Methodology
- 1. Baseline studies and data
- Review of literature including relevant database searches
- Habitat assessment including two field surveys to identify threatened
species, communities, benthic organisms, populations and their habitat
- 2. Impact Assessment
- Assessment of Impacts on flora and fauna in accordance with NSW
and Federal legislation and NSW Planning Instruments
- 3. Mitigation Measures
- Appropriate mitigation/ management measures devised to manage
potential impacts
16
Options for mangrove stand in Remediation Area A
Summary of ecological assessment
17
Option 1 Option 2 Option 3 Retain all or part of the mangrove stand Remove the sediment while maintaining the mangroves in situ Remove the mangroves and contaminated sediment from remediation Area A Finding: Remediation cannot occur without removing/ damaging the existing mangrove
- colony. No practical solution is available to allow retention of mangroves and
remediation of sediment on Area A. Option 3 is the only practical approach. Mitigation measures:
- Develop a mangrove management plan to prepare area for biodiversity re-
establishment and management of progress of mangrove re-colonisation
- Monitor progress to employ adaptive measures if necessary
Summary of ecological assessment
18
Impact Mitigation Measures Significance of Impact with Mitigation
Impacts on threatened or protected fauna species from loss of preferred habitat
- Marine habitat monitoring
plan Negligible Physical loss of mangroves habitat
- Mangrove management plan
- Re-establishment of
mangroves Negligible Altered water quality as a result of the re- suspension of sediments during dredging
- Water quality management
plan Negligible Water quality impacts from accidental hydrocarbon spills from plant, equipment or pipeline failure
- Use of silt curtains.
- Visual inspection of pipeline
Negligible Impacts to the seabed and marine ecology during removal of contaminated sediments
- None identified
Positive
Q and A Session
19
Thank you and close
Next Steps
- Display and presentation materials from the session will be
uploaded to the website for broader interest
- Await outcome of Jemena’s State Significant Development
application as well as updated Environmental Assessment Requirements (EARs) (expected Q3 2014)
- Subject to the above, EIS to be lodged Q3 2014
- Public Exhibition Q4 2014/ Q1 2015
20