KAGRA 2015 December 18 27 - - PowerPoint PPT Presentation

kagra
SMART_READER_LITE
LIVE PREVIEW

KAGRA 2015 December 18 27 - - PowerPoint PPT Presentation

KAGRA 2015 December 18 27 @ , 1 0. Abstract Here, I explain 1. Cryostat installation


slide-1
SLIDE 1

1

山元 一広

KAGRAの低温懸架系

2015 December 18 平成27年度東京大学宇宙線研究所共同利用研究成果発表会 @東京大学柏キャンパス, 柏市、千葉

slide-2
SLIDE 2

2

  • 0. Abstract

Here, I explain

  • 1. Cryostat installation at KAGRA site
  • 2. Cryogenic payload
  • 3. Sapphire suspension
slide-3
SLIDE 3

3

Contents

  • 1. Introduction
  • 2. Cryostat installation
  • 3. Cryogenic payload
  • 4. Sapphire suspension
  • 5. Summary
slide-4
SLIDE 4

4

  • 1. Introduction

4

Mozumi Y-end Sakonishi X-end Atotsu Center

Vibration isolation system (Type A), Cryocooler unit, Cryostat, Cryogenic payload Schematic view of KAGRA interferometer Four mirrors of arm cavity will be cooled. First km scale cryogenic interferometer Kamioka mine (Underground site)

slide-5
SLIDE 5
  • 1. Introduction

5

Thermal noise : Fundamental noise Suspension thermal noise : mirror position fluctuation (vibration of suspension for mirror) Mirror thermal noise : mirror surface fluctuation (elastic vibration of mirror itself)

slide-6
SLIDE 6
  • 1. Introduction

6

Fluctuation-Dissipation Theorem Relation between thermal noise and mechanical loss in suspension and mirror Amplitude of thermal noise is proportional to

(T/Q)1/2.

In general, Q (inverse number of magnitude of dissipation) depends on T (temperature). KAGRA sapphire mirror is at 20K.

slide-7
SLIDE 7
  • 1. Introduction

7

3rd generation : 10 times better sensitivity Cryogenic techniques will be adopted. Einstein Telescope (Europe), Voyager (U.S.A.)

Einstein Telescope

slide-8
SLIDE 8

8

to SAS

Remote valve unit

4 Low vibration cryocooler unit

Cryostat Stainless steel t20mm Diameter 2.6m Height ~ 3.6m M ~ 10 ton Cryo-coolers Pulse tube, 60Hz 0.9 W at 4K (2nd) 36 W at 50K (1st)

Outline of cryostat

Cryogenic payload Mirror

  • 1. Introduction
  • S. Koike
slide-9
SLIDE 9
  • 1. Introduction

9

Pulse tube cryocoolers Pulse tube cryocoolers Sapphire suspension Sapphire mirror (About 20K) Sapphire fiber Cryo-payload Schematic view of cryostat and cryo-payload

slide-10
SLIDE 10
  • 1. Introduction

10

Pulse tube cryocoolers Pulse tube cryocoolers Schematic view of cryostat and cryo-payload Cryo duct for 300 K radiation

slide-11
SLIDE 11
  • 2. Cryostat installation

11

Installation of cryostat is a hard mission ! Cryostats are carried along 3 km tunnel !

slide-12
SLIDE 12

12

BS 3 km 3 km

IXC

IYC EYC EXC

Assembled Cryostat Photos

EYC

  • N. Kimura

All four cryostats were installed.

slide-13
SLIDE 13
  • 2. Cryostat installation

13

Cryo ducts are connected to two cryostats in the center room.

slide-14
SLIDE 14

Progress of the cryostat assemble;

  • EXC & EYC were assembled as vacuum vessels

without duct shields and cryo-coolers from the end of 2014.11 to the end of 2015.1.

  • IYC & IXC were assembled with all of components

such as duct shields and cryo-cooler units

from the end of 2015.2 to the mid of 2015.4.

EYC EXC IXC IYC

  • Duct Shield
  • 12 mL vacuum duct
  • 6 mL +6 mL vacuum duct
  • Cryostat
  • Gate Valve

BS 3 km 3 km Cryo‐cooler unit installation

  • N. Kimura
slide-15
SLIDE 15

15 15

Outline of vibration isolation and cryostat

15 15 15 15 15

Pulse tube cryocoolers Pulse tube cryocoolers

  • 3. Cryogenic payload

Vibration isolation, adjustment, control, damping, … Cryo-payload

slide-16
SLIDE 16

16 16 16

Design Almost all parts were designed.

  • A. Hagiwara
  • 3. Cryogenic payload
slide-17
SLIDE 17
  • 3. Cryogenic payload

17 17

Prototype test of cryogenic payload Cooling test on December

slide-18
SLIDE 18

18 18

“Sapphire monolithic lop-eared suspension” One of the most important parts of KAGRA : Main sapphire mirrors are included. All parts are made from sapphire. Sapphire lop-eared suspension

  • 4. Sapphire suspension

fiber break Hydroxide Catalysis Bonding

Full size suspension as prototype

slide-19
SLIDE 19

19 19 19 19 19 19 19 19 19

Sapphire cylinder with flat cuts as dummy mirror Blade spring

  • 4. Sapphire suspension

Ears Fibers with nail head

Full size suspension as prototype All sapphire parts for full size prototype have already been delivered (IMPEX and Shinkosha).

slide-20
SLIDE 20

20 20 20 20 20 20 20 20 20

Jigs to assemble full size prototype is being prepared.

  • 4. Sapphire suspension

Full size suspension as prototype Some parts were delivered.

slide-21
SLIDE 21

21 21 21

Measurement of shape of sapphire bulk and ears For precise position of ears, the geometrical shape and ears were measured (by K. Enami, Mechanical Engineering Center, KEK).

  • 4. Sapphire suspension

Full size suspension as prototype

slide-22
SLIDE 22

22

  • 5. Summary

Cryostat installation All four cryostats were installed ! Connection to cryo duct are in progress. Cryogenic payload Almost all parts were designed. Cooling test of prototype will be started soon ! Sapphire lop-eared suspension All sapphire parts for full size prototype are delivered. Assembly jig for full size prototype are being prepared.

slide-23
SLIDE 23

23 23 23 23 23

KAGRA Cryogenics Group

Toshikazu SUZUKI

EO and SEO member KEK, Senior Fellow

Nobuhiro KIMURA

Cryostat sub‐chief KEK, Assoc. Prof.

Kazuhiro YAMAMOTO

Cryo‐Payload sub‐chief ICRR, Assist. Prof.

Takayuki TOMARU

Chief KEK, Assoc. Prof.

Tatsuya KUME

Surveying, Alignment KEK, Assoc. Prof.

Rahul KUMAR

Simulation, Payload KEK, PD

Ayako HAGIWARA

CAD KEK, Technical Staff

Shinichi TERASHIMA

Machining KEK, Technical Staff

Iwao MURAKAMI

Welding, Assembly KEK, Technical Staff

Hiroki TANAKA

Cryo‐Payload, Q ICRR, Grad. Student

Takahiro MIYAMOTO

Cryo‐Payload ICRR, Grad. Student

Suguru TAKADA

Cryogenics NIFS, Assist. Prof.

2015.Oct.16 By T. Tomaru (Revised by K. Yamamoto)

Kieran CRAIG

Payload ICRR, PD

slide-24
SLIDE 24

24 24 24

Acknowledgement

24

Supported by Mechanical Engineering Center, KEK Machine shop, The Institute for Solid State Physics, The University of Tokyo

slide-25
SLIDE 25

25 25

Thank you for your attention !

slide-26
SLIDE 26

26 26 26

Acknowledgement

26

ELiTES: ET-LCGT interferometric Telescope Exchange of Scientists Grant for collaboration about cryogenic between KAGRA and ET European 7th Framework Programme Marie Curie action (Mar. 2012 - Feb. 2017) European people can visit Japan for KAGRA.

slide-27
SLIDE 27

27 27 27

Acknowledgement

27 27 27 27 27 27

1st : 3 Oct 2012 2nd : 4 Dec 2013 ELiTES meeting

slide-28
SLIDE 28

28 28 28

Acknowledgement

28 28 28 28 28 28

3rd : 9 Feb 2015 4th : 2 Dec 2015 ELiTES meeting