July 2020 Monthly Update North Dakota Pipeline Authority Justin J. Kringstad July 17, 2020 US Williston Basin Oil Production - 2020 2 2 JJ Kringstad - North Dakota Pipeline Authority Monthly Production Change 3 JJ Kringstad - North Dakota


  1. July 2020 Monthly Update North Dakota Pipeline Authority Justin J. Kringstad July 17, 2020

  2. US Williston Basin Oil Production - 2020 2 2 JJ Kringstad - North Dakota Pipeline Authority

  3. Monthly Production Change 3 JJ Kringstad - North Dakota Pipeline Authority

  4. March to May 75+% M-O-M Oil Drop (Non-Confidential Wells Only) 4 JJ Kringstad - North Dakota Pipeline Authority

  5. Vintage Year of Shut-In Wells – May 2020 (Non-Confidential Wells Only) 5 JJ Kringstad - North Dakota Pipeline Authority

  6. Estimated Williston Basin Oil Transportation May 2020 6 6 6 JJ Kringstad - North Dakota Pipeline Authority

  7. Estimated Williston Basin Oil Transportation 7 7 7 JJ Kringstad - North Dakota Pipeline Authority

  8. Estimated ND Rail Export Volumes 8 8 JJ Kringstad - North Dakota Pipeline Authority

  9. Rail Destinations Market Share (Apr. 2020) Data for Rail Destination Market Share Provided by the US Energy Information Administration 9 9 JJ Kringstad - North Dakota Pipeline Authority

  10. Major Rail Lines and Refineries $23.40 $15.72 $26.28 $16.10 EIA April 2020 Refiner Acquisition Cost $19.41 10 10 JJ Kringstad - North Dakota Pipeline Authority

  11. Crude Oil Prices – July 17, 2020 Brent $43.36 WTI + $2.50 Cushing $40.86 Pricing Data: LLS (Argus) Bloomberg & CME (LLS-Argus) WTI + $1.61 11 JJ Kringstad - North Dakota Pipeline Authority

  12. Williston Basin Truck/Rail Imports and Exports with Canada Data for imports/exports chart is provided by the US International Trade Commission and represents traffic across US/Canada border in the Williston Basin area. 12 12 JJ Kringstad - North Dakota Pipeline Authority

  13. Solving the Flaring Challenge GREEN – % of gas captured and sold Blue – % flared from zero sales wells Orange – % flared from wells with at least one mcf sold. Simple Terms Blue – Lack of pipelines Orange – Challenges on existing infrastructure Statewide May 2020 Data – Non-Confidential Wells 13 JJ Kringstad - North Dakota Pipeline Authority

  14. Solving the Flaring Challenge 14 JJ Kringstad - North Dakota Pipeline Authority

  15. Solving the Flaring Challenge 15 15 JJ Kringstad - North Dakota Pipeline Authority

  16. EIA Oil Price Forecast* *EIA July 2020 SEO and January 2020 AEO Blend 16 JJ Kringstad - North Dakota Pipeline Authority

  17. Solving the Flaring Challenge 17 JJ Kringstad - North Dakota Pipeline Authority

  18. Solving the Flaring Challenge 18 JJ Kringstad - North Dakota Pipeline Authority

  19. Major Gas Pipeline and Processing Infrastructure M.P. WBI Transmission 19 JJ Kringstad - North Dakota Pipeline Authority

  20. Contact Information Justin J. Kringstad, Director North Dakota Pipeline Authority 600 E. Boulevard Ave. Dept. 405 Bismarck, ND 58505-0840 Phone: (701)220-6227 Fax: (701)328-2820 E-mail: jjkringstad@ndpipelines.com Websites: www.pipeline.nd.gov www.northdakotapipelines.com 20 20 JJ Kringstad - North Dakota Pipeline Authority

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.