joint wastewater master plan
play

Joint Wastewater Master Plan Stage 4 Final Plan Executive - PowerPoint PPT Presentation

Joint Wastewater Master Plan Stage 4 Final Plan Executive Committee June 11, 2018 Agenda Overview Progress Engagement Issues and Opportunities Themes Capital Improvements Recommendations 2


  1. Joint Wastewater Master Plan Stage 4 – Final Plan Executive Committee June 11, 2018

  2. Agenda • Overview • Progress • Engagement • Issues and Opportunities – Themes • Capital Improvements • Recommendations 2

  3. Organization Alignment  Abbotsford  Mission 3

  4. Progress 4

  5. Engagement STAGE 1 Farmers Market (Abbotsford and Mission) Canada Day Council Joint Shared Service Committee (JSSC) PUBLIC Stage 1 – Sept. 14, 2017 Stage 2 – Nov. 9, 2018 EVENTS Stage 3 – Mar. 22, 2018 STAGE 2 Stage 4 – May 17, 2018 Abbotsford Seven Oaks Mall Mission Leisure Centre STAGE 3 Abbotsford Clearbook Library Mission Leisure Centre 5

  6. Purpose PHASEABLE, AFFORDABLE, RESILENT, SUSTAINABLE, INCREMENTAL, FLEXIBLE AND GRANTABLE 6

  7. Issues and Opportunities 1 2 3 4 5 6 7

  8. Themes BUILDING CAPACITY 6 4 RESOURCE RECOVERY 2 3 SUSTAINABLE COMMUNITY 1 RESILIENT SYSTEM 8 5

  9. Building Capacity • Support residential, industrial, commercial and institutional growth for the next 25 years • Identify system upgrades and timing • Review extra strength loading and rates – Consult with industries on potential rate adjustments and options to address growth 9

  10. Resource Recovery • Review biosolids issue and opportunity – Request for proposals (RFP to continue with land application (early 2019) – RFP for biosolids master plan • Review biogas opportunity – Issue RFP for interest in either sale of excess biogas or provide district heat to nearby industrial or agricultural buildings – Seek grant opportunities for cogeneration 10

  11. Sustainable community • Review odour issue – Continuous monitoring at the Plant to achieve the goal of good neighbour and non-detectable odours off the Plant property 11

  12. Resilient System • Proposed Master Plan will incorporate seismic and floodproofing considerations – Maximize usage on existing assets towards end of life – New plant will be constructed on secured ground – Plant will be brought up to 12.2 m elevation 12

  13. Proposed Upgrades Liquid Train Roadmap Inlet and Primary Treatment Upgrade Secondary Solids Handling treatment & Digester upgrade Upgrade ($54M) ($124M) Secondary Clarifiers Upgrade ($48M) Plant has adequate capacity Enhanced Primary for next 5-10 years Treatment ($1M) 2016 2021 2026 2031 2036 2041 (Resiliency) Phosphorus/Orthophosphate: (Resiliency) preparation • preparation West Site East Site – Additional monitoring – Phosphorus management plan 13

  14. Proposed Annual Capital Expenditures (2018 dollars) $250 MILLIONS New Digesters & $200 Solids Handling ANNUAL EXPENDITURE (MILLIONS) New Liquid $54M Treatment Plant Ground Ground (West Site) $150 Improvement & Improvement $124M Flood proofing & Flood proofing (West Site) (East Site) $88M $83M $100 New Secondary Enhanced Clarifiers primary treatment $48M $50 $1M Approved Budget Items $0 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 Potential grant (2/3 project costs) Ground Improvements Liquid Train New Secondary Clarifiers Solids Handling 2017 Approved Budget 15

  15. Highlights • Seismic and Flood proofing ~$141 M – West and East sites Proposed capital plan (to 2041): • – Proposed new plant ~$260 M – Current capital plan (Renewal and replacements) ~$155 M Grants will be sought for major projects. • Future master plans (every 5 years) to • * review innovative technologies *Only if required 16

  16. Recommendations • THAT the Joint Wastewater Master Plan, be adopted; and THAT it be used to develop a long term financial plan. • 17

  17. QUESTIONS / COMMENTS ? 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.