ITEM 11B. SH 288 TOLL LANES IN HARRIS COUNTY
Texas Transportation Commission Meeting
February 26, 2015
ITEM 11B. SH 288 TOLL LANES IN HARRIS COUNTY Texas Transportation - - PowerPoint PPT Presentation
ITEM 11B. SH 288 TOLL LANES IN HARRIS COUNTY Texas Transportation Commission Meeting February 26, 2015 Footer Text Date Project Scope Design, construct, finance, operate and maintain a 10.3-mile segment of SH 288 from US 59 to the Harris
Footer Text Date
February 26, 2015
February 26, 2015
10.3-mile segment of SH 288 from US 59 to the Harris County line for a 52 year term
– 4-tolled lanes (2 each direction) within existing SH 288 median – New Beltway 8 interchange, all 8 direct connectors (DCs) – Texas Medical Center Connector, 2 DCs – ROW to ROW O&M including General Purpose Lanes
2
SH 288 Toll Lanes Project in Harris County
THE PROJECT
BRAZORIA COUNTY TOLLED LANES FUTURE TOLLED LANES
February 26, 2015
accommodate the Ultimate Configuration
– Improvements to the I-610 interchange – One additional General Purpose Lane
I-610 to Beltway 8
3
SH 288 Toll Lanes Project in Harris County
February 26, 2015
4
SH 288 Toll Lanes Project in Harris County
February 26, 2015
5
SH 288 Toll Lanes Project in Harris County
*alphabetical order
February 26, 2015
6
(Major)
SH 288 Toll Lanes in Harris County
*alphabetical order
February 26, 2015
7
SH 288 Toll Lanes in Harris County
*alphabetical order
February 26, 2015
proposal that offers the best value
Selection Recommendation Committee (ESRC)
recommendation to Commission
8
SH 288 Toll Lanes in Harris County
February 26, 2015
Convenience Fee Score (max. 4 points)
9
SH 288 Toll Lanes in Harris County
Financial 80 points + Technical 20 points
100 points
February 26, 2015
10
SH 288 Toll Lanes in Harris County
February 26, 2015
11
SH 288 Toll Lanes in Harris County
Equity Owner: ACS Servicios y Concesiones, SL, InfraRed Capital Partners Ltd Shikun & Binui Concessions USA, Inc. Major Non-equity Members and other team members:
February 26, 2015
12
SH 288 Toll Lanes in Harris County
February 26, 2015
13
SH 288 Toll Lanes in Harris County
February 26, 2015
14
SH 288 Toll Lanes in Harris County
Agreement (CDA)
approval
to execution of the CDA
finance, operate and maintain the project
February 26, 2015
Administra ration
– Chief Financial Officer – James Bass – Chief Engineer – Bill Hale – Chief Planning and Project Officer - Russell Zapalac
T Strategic ic P Proje jects D Divis isio ion
– Katie Nees – Dieter Billek – Marcus Coronado – Dawn Scheel – Matt McCarter – Bill Reichert – Quincy Allen – Greg Snider – Caleb Bryant
15
SH 288 Toll Lanes in Harris County
DOT Office of Ge Gene neral Co Coun unsel
– Rebecca Bronson – Jim Bailey
ebt Man anagem agemen ent O Office
– Ben Asher – Sara Ulbrich – Sarah Chapa
DOT H Hous uston Di District Office ce
– Mike Alford – Patrick Gant
isio ion O Offic ices
– Dacio Marin (Bridge) – Roland Silva (Toll Operations)
Coun unty (Observers)
– Matt Hanks
visors
– Mayer Brown, KPMG, Jacobs, HNTB
February 26, 2015
16
SH 288 Toll Lanes in Harris County
– Authorize the department to commence and complete negotiations with Blueridge Transportation Group for apparent best value for a project scope that includes:
subject to the conditions of the Minute Order
February 26, 2015
17
SH 288 Toll Lanes in Harris County