ISLAIS CREEK MOTOR COACH MAINTENANCE & OPERATIONS FACILITY - PowerPoint PPT Presentation

ISLAIS CREEK MOTOR COACH MAINTENANCE & OPERATIONS FACILITY Phase II Lisa Chow Project Manager 1 Construction of a two-story, 66,000 square foot operations and maintenance facility for the diesel-electric hybrid articulated buses. 2


  1. ISLAIS CREEK MOTOR COACH MAINTENANCE & OPERATIONS FACILITY Phase II Lisa Chow Project Manager 1

  2. Construction of a two-story, 66,000 square foot operations and maintenance facility for the diesel-electric hybrid articulated buses. 2

  3. Progress: • Perform utility relocation • Drive piles for the north and south buildings • Began erecting steel for south building Next Steps: • Continue with pile cap and grade beam, and electrical pullbox installation and erection of steel structure. 3

  4. Pile Driving 4

  5. General Excavation 5

  6. Pile Installation 6

  7. Pile Cap Excavation 7

  8. Electrical Pullbox Installation 8

  9. Steel Erection 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.