Tom Røtjer, Head of Internal Task Force 9 April, 2018
Internal Task Force Tom Rtjer, Head of Internal Task Force 9 April, - - PowerPoint PPT Presentation
Internal Task Force Tom Rtjer, Head of Internal Task Force 9 April, - - PowerPoint PPT Presentation
Internal Task Force Tom Rtjer, Head of Internal Task Force 9 April, 2018 The refining process to extract alumina The input factors, processes and output at the Alunorte alumina refinery The refining process Bauxite Caustic Water soda
The refining process to extract alumina
The input factors, processes and output at the Alunorte alumina refinery
2 Bauxite Pressure vessel 170-180 oC Crystall- ization Rotating
- ven
Filtering
Caustic soda
Bauxite residue
Crushing Milling
Water
- 2.4 kilo bauxite is turned into 1 kilo
alumina and 1.4 kilo bauxite residue
- Stored in bauxite residue deposits
- Process water treated before release
The refining process
Bauxite Alumina
Bauxite Alumina
Bauxite residue
The bauxite residue deposits (1 and 2)
4
5
Effluent water treatment plant (Area 82) Area 45 DRS1 (Bauxite residue deposit 1) Albras (primary aluminium plant) Alunorte alumina refinery area Alunorte bauxite and coal storage area Canal Novo and Canal Velho Pará river Mixing box
24 February, 2018
Rainfall volumes
The event of intense rainfall 16-17 February 2018 resulted in 231mm in 12hr and 239mm in 24hr. Total February rainfall was 901mm
Key findings
- Extreme rainfall resulting in large amounts of
water needing treatment upon release
- Internal power outage due to lightning reducing
water treatment capacity
- External power voltage dip into refinery caused
a spill of process water containing caustic soda inside the process area, that impacted the effluent water treatment plant capacity
6
319.4mm
6 days
Daily rainfall in mm
Alunorte Effluent Water Treatment System
Measurements in Pará River within average pH and Suspended Solids limits
7
Canal Velho DRS2 effluent steel pipe DRS1 effluent concrete pipe DRS1 effluent concrete pipe
Effluent water treatment plant
Alunorte/Albras
X
X
Measurement point
Mixing box
Outlet from Alunorte
Pará River
Gate
- Process area water
- Stormwater
X
Gate
Return to process area Canal Novo
X
Measurement point
Area 45 storm water flooding
- Used for contractors and laydown area.
- As part of the Alunorte Water Management
improvement project that is already sanctioned, a new storm water system including new holding pond and sufficient pumping system will be constructed in Area 45 Flooding contained within the walls of the surrounding pipe channels
8
No overflow from DRS1
Freeboard development during event
9
- Water retained in DRS1 in order to let Effluent
Treatment Plant prioritize plant area
No overflow from DRS2
Freeboard development during event
10
Alleged «overflow» - photo «evidence» used in media to «prove» spillover from DRS2. The same «overflow» showing that water moves from a dry zone to a wet zone within the deposit, as it is supposed to.
- DRS2 had good capacity, and DRS2 basins
contributed to relieving pressure on DRS1
4,01 4,09 3,89 2,83 2,79 2,73 2,55 2,20 2,11 1,98 1,66 1,63 1,60 1,60 1,40 1,40 1,76 1,86 2,14 2,31 2,41 2,70 2,83 3,03 3,26 3,38 0,00 0,50 1,00 1,50 2,00 2,50 3,00 3,50 4,00 4,50 5,00
15-fev 16-fev 17-fev 18-fev 19-fev 20-fev 21-fev 22-fev 23-fev 24-fev 25-fev 26-fev 27-fev 28-fev 1-mar 2-mar 3-mar 4-mar 5-mar 6-mar 7-mar 8-mar 9-mar 10-mar 11-mar 12-mar 13-mar 14-mar 15-mar 16-mar 17-mar 18-mar 19-mar 20-mar 21-mar 22-mar 23-mar 24-mar 25-mar 26-mar 27-mar 28-mar 29-mar 30-mar 31-mar
Borda livre m
Borda livre DRS2 (m)
Real Previsão chuva extrema Previsão base chuvas clima tempo Alvo
Summary
- The operational integrity of the bauxite residue
deposits 1 and 2 was maintained during the event, and there were no overflow from the deposits
- In order to avoid risks of harm to the
environment, not fully treated effluent was released through Canal Velho into the Para River − Average effluent concentration in the river was within
the prescribed limits between pH 6-9
- Recommendations have been identified to
increase capacity and improve the integrity of the
- verall effluent water treatment system of
Alunorte No overflow from the Bauxite residue deposits
11
Recommendations
12
Increase effluent treatment capacity:
- By 50% before next rainy season
- Holding basin and pump capacity Area 45
- New transfer pipes and pumping facilities
(DRS1 to ETP)
- Integrate holding basins at the Bauxite
Residue deposits
- Upgrade mixing box system
- Better separation of clean storm water from
water needing treatment
New Water Balance Study Update emergency plans and training Finalize closure of DRS1 Ensure good dialogue with authorities
Plant improvements Environmental improvements
Initiate and perform an environmental baseline and effect study as basis for future monitoring Invite academia in Pará Brazil/Norway to high quality environmental R&D program Review and improve the environmental monitoring Reduce external water consumption through reuse of internal water
Follow us on:
13