Mack Mackenzie V enzie Valle lley Land and W Land and Water Boar r Board Public Hearing Public Hearing Closure and R Closure and Reclamation Plan Par clamation Plan Part 2 2 and Monit and Monitoring ring Januar January 2020 y 2020
Mack Mackenzie V enzie Valle lley Land and W Land and Water Boar - - PowerPoint PPT Presentation
Mack Mackenzie V enzie Valle lley Land and W Land and Water Boar - - PowerPoint PPT Presentation
Mack Mackenzie V enzie Valle lley Land and W Land and Water Boar r Board Public Hearing Public Hearing Closure and R Closure and Reclamation Plan Par clamation Plan Part 2 2 and Monit and Monitoring ring Januar January 2020 y 2020
2
Water and r and Monit Monitoring at ring at Giant Mine Giant Mine
- Baker Creek
- Existing effluent treatment plant (ETP)
- New water treatment plant (WTP)
- Effluent quality criteria (EQC)
- Aquatic effects monitoring program (AEMP) and other
aquatic monitoring
- Air quality and greenhouse gas emissions
3
Bak Baker Creek r Creek
Reach 0 Reach 1 Reach 2 Reach 3 Reach 4 Reach 5 Reach 6
4
- Flooding
- Exposure to Contamination
- Flooding of underground via pits
- Exposure to contamination
Bak Baker Creek – r Creek – Risks Risks
5
Bak Baker Creek – r Creek – Mitigations itigations
- Contaminated sediment removal
- Floodplain improvements – probable maximum flood
6
Flood that comes from the most severe weather that can be imagined Extremely unlikely to happen
What is the Pr What is the Probable Maximum Flood (PMF)?
- bable Maximum Flood (PMF)?
Reviewer comments ORS 5; YDFKN 21
7
Develop estimate for the worst storm that could happen given where the site is located For Baker Creek:
- Estimated 30cm of rain in 48 hours
- Assumed much snow on the ground had fallen
(1‐in‐100‐year snowpack)
- Roughly the same as assuming the amount of snow and rain
that falls in Yellowknife in one year had fallen in two days on top of a record‐year snowpack
Ho How Do W w Do We Estimat Estimate The PMF? The PMF?
8
PMF for Baker Creek would be the same as the North Saskatchewan River, in Edmonton, or 5 times the average flow in the Yellowknife River
Bak Baker Creek – r Creek – PMF MF
9
- Baker Creek will have a channel and a floodplain
- Regular flow will be confined to the channel
- Extreme floods will flow in the channel and floodplain
- Heavy rock protection will be built on the edges of the
floodplain where needed to prevent erosion
Bak Baker Creek – r Creek – Designed f esigned for the PMF r the PMF
10
Proponent Position The probable maximum flood is very conservative The Baker Creek design provides protection from even the most extreme flood events Details regarding freeboard for each pit will be provided in the Design Plan
Recommendation AN 5
Int Intervention – ention – Additional F dditional Freeboar eeboard
11
Proponent Position Proposed closure activities for Baker Creek will fulfill the promises of the Developer’s Assessment Report Criteria BC 5‐2 and BC 5‐3 are under‐development and specific to benthics and fish Criteria will be informed by engagement with stakeholders in 2020 and by guidance provided by Fisheries and Oceans Canada through Fisheries Act authorization process GMRP has committed to pre‐engagement on all criteria under‐development with the Working Group
Recommendations CoY 8, YKDFN 2
Int Intervener Theme – ener Theme – Bak Baker Creek Crit r Creek Criteria and Pr eria and Productivity
- ductivity
12
Proponent Position Priority must be given to conveying the PMF – alignment is dictated by geometry and topography Impacts to operations to Yellowknife Historical Society will be minimized where possible
Recommendations YKHS 3, 4
Int Intervention Bak ention Baker Creek and Im r Creek and Impacts t pacts to T Townsit wnsite Area Area
13
Water T r Treatment eatment
14
- Minewater is treated with existing
effluent treatment plant (ETP) built in 1981
- Seasonal discharge to Baker Creek
- Continued use of the existing ETP for
next several years, no major upgrades proposed
- A new long‐term Water Treatment
Plant (WTP) will be built onsite
Existing Ef Existing Effluent T fluent Treatment Plant eatment Plant
15
- Proposed effluent quality criteria for the ETP
reflect existing treatment technology
- Reviewer comments incorporated through
water licence process
- Metal and Diamond Mining Effluent
Regulations (MDMER) limits used to start
- If past/predicted concentrations were well
below the MDMER limits, EQC lowered
- New EQC for nitrate, ammonia, sulphate
and chloride
- From two intervenors: the proposed EQC are
“adequately protective of Baker Creek”, and “the rationales for proposed criteria seem reasonable”
Existing Ef Existing Effluent fluent Treatment Plant eatment Plant
16
A new WTP will be commissioned by approximately 2026 The new plant will:
- Operate in the central core area of site
- Continue to pump from the underground
- Discharge year‐round to Yellowknife Bay
via nearshore outfall
- Discharge much lower arsenic than ETP
(10 µg/L compared to 300 µg/L from ETP)
Ne New W w Water T r Treatment Plant (W eatment Plant (WTP) TP)
17
- Proposed a combined mixing
zone (Baker Creek and WTP)
- One set of water quality
- bjectives (WQOs) to be met at
the edge of the mixing zone
- In the future, concentrations
expected to:
- Decrease rapidly with
distance from the breakwater
- Meet WQOs at the mixing
zone boundary and into Yellowknife Bay
Water T r Treatment Plant eatment Plant
18
Parameter Existing ETP New WTP Maximum Average Concentration Maximum Grab Concentration Maximum Average Concentration Maximum Grab Concentration
pH 6.5 to 8.5 6.5 to 8.0 TSS, mg/L 15 30 15 30 Sulphate, mg/L 1310 1440 ‐ ‐ Chloride, mg/L 660 720 ‐ ‐ Nitrate, mg‐N/L 13 25 13 25 Total Ammonia (variable), mg‐N/L pH 6.5 3.1 6.2 10.9 22 Refer to Table 7 in IR Response #06 from Tech Session 2 pH 8.5 0.51 1.0 ‐ ‐
Total antimony, mg/L ‐ ‐ 0.2 0.3 Total arsenic, mg/L 0.3 0.6 0.01 0.02 Total copper, mg/L 0.03 0.06 0.024 0.033 Total lead, mg/L 0.003 0.006 0.003 0.008 Total nickel, mg/L 0.10 0.20 0.10 0.15 Total zinc, mg/L 0.10 0.20 0.08 0.16 Total petroleum hydrocarbons, mg/L 3 5 3 5 Un‐ionized ammonia, mg‐N/L* 0.5 1.0 0.5 1.0 Radium‐226, Bq/L* 0.37 1.11 0.37 1.11 Cyanide, mg/L* 0.03 0.06 0.5 1
*EQC included only to align with MDMER limits, parameters not identified as COPC
Pr Proposed EQC
- posed EQC
19
Proponent Position Effluent quality criteria for chloride and sulphate for water treatment plant are not required
- Low discharge volume
- High assimilative capacity
- Low concentrations of chloride and sulphate at mixing zone boundary
(< 10 and 20 mg/L respectively, well below WQOs) In lieu of setting EQC for chloride and sulphate for the WTP:
- Monitor influent and effluent
- Track against predictions
- Report results in Surveillance Network Program and AEMP
Recommendations GMOB 13, SEC 10
Int Intervener Theme – ener Theme – Effluent Crit luent Criteria f eria for W r WTP
20
Monitoring now and in the future will be both:
- Site‐wide
- Yellowknife Bay
Monit Monitoring ring
21
See Standard Operating Procedures for Details
- Stations, description, project phase,
rationale, frequency, parameters
SNP 43‐5
Trapper Creek Pocket Lake Baker Pond ETP discharge
P‐LA SNP 43‐11 SNP 43‐16 SNP 43‐1 Baker Creek Exp Pt SNP 43‐23 (new)
Monitoring across the Site—Current and Future
- Runoff
- Trapper Creek
- Pocket Lake
- Baker Creek (upper,
middle, lower)
- Ponds
- TCAs
- Sumps
- Groundwater
- Mine pool
- ETP/WTP inflow
and outflow
Site te-Wide W Wate ter M Monito toring
22
Proponent Position GMRP does not consider more frequent sampling necessary:
- The current water quality sampling regime for
Baker Creek downstream of discharge is bi‐ monthly during the open water season
- The ETP discharges seasonally, typically from
July to September
- The creek freezes to the bottom in many places
during the winter
Int Intervention – ention – Wat ater Quality Sam er Quality Sampling ling Freq equency of Bak uency of Baker Creek r Creek
Recommendations NSMA 3, 5
23
Proponent Position GMRP does not consider more frequent sampling necessary:
- Effects of existing contamination on Baker
Creek are well understood
- Frequency is standard for environmental
effects monitoring under MDMER and AEMP
Recommendation NSMA 5
Int Intervention – ention – Fish and Fish and Benthics Benthics Sam Sampling F ling Freq equency uency
24
Proponent Position The GMRP uses a standard, comprehensive suite of parameters at all water quality monitoring stations. Details are provided in the standard
- peration procedures
Parameters recommended by Alternatives North are already included in the standard suite of parameters
Recommendation AN 13
Int Intervention – ention – Monit
- nitoring Parame
- ring Parameters
25
MDMER/EEM OMP SNP
Surface W Wate ter M Monito toring
- Surveillance network program (SNP)
stations
- Surface Runoff Stations sampled under
- perational monitoring program
- Details are provided in the standard
- perating procedures document submitted
as part of the GMRP water licence application
26
Yellowknife River Behind and beyond the breakwater Near the proposed outfall
Dettah
Near old townsite Back Bay North Yellowknife Bay Near Dettah
Stations throughout Yellowknife Bay
Near City Pumphouse 2 Near Ndilǫ
Yellowknife
Yello llowknif wknife Ba Bay – y – Special Study pecial Study Existing Conditions Existing Conditions
27
Int Intervener Theme – ener Theme – Runof unoff Monit f Monitoring ring and Crit and Criteria eria
Proponent Position The existing runoff monitoring network includes the monitoring tributaries upstream of Baker Creek GMRP commits to re‐evaluating runoff criteria submitted in the water management and monitoring plan The GMRP will develop action levels for runoff from engineered covers
Recommendations GMOB 10, 11; ECCC 2, SEC 3
28
Int Intervention – ention – Yello ellowknif wknife Ba Bay Sam Sampling F ling Freq equency uency
Proponent Position
GMRP does not consider more frequent monitoring necessary :
- GMRP has enough existing data to understand
seasonal trends
- GMRP has proposed sampling that captures early
- pen‐water season, late open‐water season, and
under‐ice conditions
- GMRP expects a formal plume study for discharge
to Yellowknife Bay
Recommendations NSMA 3, 4
29
Proponent Position The GMRP has committed to engage further on Aquatic Effects Monitoring Program GMRP is developing a coordinated approach to engaging on:
- Fisheries Act authorization
- Baker Creek design
- AEMP
- Community‐based Monitoring
Program GMRP has proposed an Aquatics Engagement Group GMRP welcomes input from the YKDFN and notes that there will be
- pportunities to improve the AEMP
throughout the term of the Water Licence
Int Intervener Theme – ener Theme – Stak takeholder In holder Input put to to t the A AEMP
Recommendations ECCC 3; YKDFN 6, 10
30
Proponent Response GMRP agrees to an approach with one AEMP, with a shift in focus from Baker Creek to Yellowknife Bay at the time of WTP transition Propose approval of the “Baker Creek” AEMP study design Subsequent re‐evaluations will allow for change in focus to Yellowknife Bay
Int Intervener Theme – ener Theme – Single ingle AEMP AEMP
Recommendations SEC 9, GMOB 15
31
Int Intervener Theme – ener Theme – AEMP t EMP to Measure Measure Im Impr provem ements ents
Recommendations GMOB 16, SEC 9
Proponent Position Improvements to the aquatic environment will not be realized until later in the remediation project GMRP has committed to providing a Table of Contents for the Post‐Closure Monitoring and Maintenance Plan in 2025 Multiple AEMP re‐evaluations between now and end
- f remediation
32
Air Quality and Greenhouse Gases Air Quality and Greenhouse Gases
33
Int Intervention – ention – CAA AAQS and QS and Mitigation Mitigation Measures F Measures For An A r An Activ tive F Freeze eeze
Proponent Posion GMRP will continue to follow the GNWT standards If GNWT adopts Canadian Ambient Air Quality Standards (CAAQS), GMRP will follow Not necessary to include mitigation measures for an active freeze system and associated emissions, passive system proposed in the CRP
Recommendation ECCC 4
34
Int Intervener Theme – ener Theme – Greenhouse Gases reenhouse Gases
Proponent Position GMRP considers it important to look for ways to reduce its greenhouse gas (GHG) emissions All significant decisions on closure options and activities are complete, therefore the GMRP does not see a benefit of an assessment of GHG emissions related to options selection Investigation of alternative energy sources is underway GMRP will continue to look for ways to reduce the carbon footprint of the Project i.e. efficient use of borrow and reducing haul distances where possible
Recommendations AN 7, GMOB 17
35
- The Giant Mine Remediation
Project’s Closure and Reclamation Plan is a comprehensive document based on many years of study and engagement
- Remediation of the Giant Mine is
important to reduce risks to the environment and health and safety for people in the Yellowknife area
- Further revisions and submissions
- f the CRP will only lead to delays
to mitigating risks
- The GMRP has proposed a process
to allow for review and approval of final design details
Summar Summary
36
The Project will result in long‐term improvements of the soil, water, sediment and create a safer community The GMRP team looks forward to continuing to working with our stakeholders to deliver this important project
Summar Summary
37