Perkins Coie LLP
Interconnection Issues with Distributed Energy Resources
Wisconsin Public Utility Institute June 25, 2019 Andrew Hanson, Senior Counsel
Interconnection Issues with Distributed Energy Resources June 25, - - PowerPoint PPT Presentation
Wisconsin Public Utility Institute Interconnection Issues with Distributed Energy Resources June 25, 2019 Andrew Hanson, Senior Counsel Perkins Coie LLP Overview Status of DER Deployment Federal Policies and FERC Orders on DER
Perkins Coie LLP
Wisconsin Public Utility Institute June 25, 2019 Andrew Hanson, Senior Counsel
Perkins Coie LLP | PerkinsCoie.com
2
Perkins Coie LLP | PerkinsCoie.com
3
Perkins Coie LLP | PerkinsCoie.com
4
5
6
7
Source: https://www.greentechmedia.com/articles/read/distributed-energy-poised-for-explosive-growth-on-the-us-grid
Perkins Coie LLP | PerkinsCoie.com
8
Source: FERC, Distributed Energy Resources: Technical Considerations for the Bulk Power System, Staff Report, Docket No. AD18-10-000, February 2018, quoting Navigant, Take Control of Your Future, Part II: The Power of Customer Choice and Changing Demands, May 9, 2016, available at https://www.navigantresearch.com/blog/take-control-of-your-future-part-ii-the-power-of-customer-choice-and-changing-demands
9
Source: U.S. Energy Information Administration, Release Date: February 2017 for December 2016 data, available at https://www.eia.gov/electricity/reports.php#/T194
Perkins Coie LLP | PerkinsCoie.com
10
Perkins Coie LLP | PerkinsCoie.com
11
superconducting magnetic energy, flywheels, and batteries;
Perkins Coie LLP | PerkinsCoie.com
12
50 MW, intended to provide voltage support and address thermal overload situations.
wholesale transmission facilities; but FERC’s holding was limited to the facts presented by Western Grid.
functions or even load.”
storage could be a transmission asset on a case-by-case basis.
Perkins Coie LLP | PerkinsCoie.com
13
CAISO in a similar manner to the way in which high-voltage wholesale transmission facilities are operated by PTOs under the direction of the CAISO. Western Grid will operate the Projects, at the CAISO’s direction, only as transmission assets.
characteristics with capacitors.
maintenance, communication, and system emergencies. Most importantly, Western Grid would be responsible for energizing the NaS batteries used in the Projects.
Perkins Coie LLP | PerkinsCoie.com
14
physically operating them when they are being charged and discharged.
Western Grid would not retain revenues outside of the transmission access charge, and would credit any revenues it may accrue as a result of charging/discharging the Projects through its PTO tariff.
charge and discharge of that pumped hydro storage facility, and there was no mechanism with potential costs and revenues from market operations.
Perkins Coie LLP | PerkinsCoie.com
15
and Small Generating Interconnection Agreement (SGIA), which establish the terms and conditions under which public utilities must provide interconnection service to Small Generating Facilities of no more than 20 MW.
https://www.eia.gov/todayinenergy/detail.php?id=37952
Perkins Coie LLP | PerkinsCoie.com
16
result in double recovery of costs by ESR;
independence.
Perkins Coie LLP | PerkinsCoie.com
17
Double recovery:
reduce the revenue requirement.
No risk of adverse impacts to wholesale electric markets:
market-based revenues on the theory that having dual revenue streams undermines competition, we would need to revisit years of precedent allowing such concurrent cost- based and market-based sales to occur as described above.”
RTO/ISO Independence:
storage resource owner or operator, rather than the RTO/ISO, to ensure RTO/ISO independence.”
Perkins Coie LLP | PerkinsCoie.com
18
Perkins Coie LLP | PerkinsCoie.com
19
Perkins Coie LLP | PerkinsCoie.com
20
Perkins Coie LLP | PerkinsCoie.com
21
Perkins Coie LLP | PerkinsCoie.com
22
Perkins Coie LLP | PerkinsCoie.com
23
Perkins Coie LLP | PerkinsCoie.com
24
Perkins Coie LLP | PerkinsCoie.com
25
Perkins Coie LLP | PerkinsCoie.com
26
both a wholesale seller and wholesale buyer.
scheduled resources.
response times, and limited energy and allows for greater grid efficiency, greater competition, and downward pressure on wholesale prices and system costs.
Perkins Coie LLP | PerkinsCoie.com
27
be dispatchable and able to set the wholesale market clearing price as a buyer and a seller, RTO/ISOs must allow make-whole payments when:
price; or
conditions as other resources that may cause them to be dispatched out-of- market and unable to recover their operating costs.”
Perkins Coie LLP | PerkinsCoie.com
28
Perkins Coie LLP | PerkinsCoie.com
29
Perkins Coie LLP | PerkinsCoie.com
30
behavior is similar to other [LSEs], and we find that applicable transmission charges should apply.”
frequency regulation or a downward ramping service) are not required to pay the same transmission charges as load during the provision of that service.
service would create a disincentive to provide that service.
Perkins Coie LLP | PerkinsCoie.com
31
Perkins Coie LLP | PerkinsCoie.com
32
distribution-connected ESRs will not be charged twice for the same charging energy (both retail and wholesale).
complexity in managing and scheduling software changes, among other work.
Perkins Coie LLP | PerkinsCoie.com
33
Perkins Coie LLP | PerkinsCoie.com
34
interconnection facilities and network upgrades rather than requiring new ones;
the more efficient use of surplus existing interconnection capacity, and
as ESRs that may be able to easily tailor their use of interconnection service to adhere to the limitations of the surplus interconnection service that may exist.
Perkins Coie LLP | PerkinsCoie.com
35
Perkins Coie LLP | PerkinsCoie.com
36
37
38
39
Perkins Coie LLP | PerkinsCoie.com
40
Perkins Coie LLP | PerkinsCoie.com
41
Perkins Coie LLP | PerkinsCoie.com
42
Perkins Coie LLP | PerkinsCoie.com
43
Perkins Coie LLP | PerkinsCoie.com
44
because they are modeled and dispatched as part of the market’s economic clearing mechanism.
and metering and not necessarily reported to RTO/ISOs, which in turn limits RTO/ISO operational awareness of those ESRs.
ESRs and will increase visibility and RTO/ISO situational awareness, but imposes a cost on ESR
requirements that can be used in lieu of direct metering by RTO/ISO.
facilities above 200 kW. (PSC 119.20(14))
Perkins Coie LLP | PerkinsCoie.com
45
requirements as large generators to ride through abnormal frequency and voltage events (i.e. not disconnect during voltage events).
that its order would be helpful to states when updating their rules for interconnection to the distribution system.
Perkins Coie LLP | PerkinsCoie.com
46
wholesale LMP for energy to charge the ESR?
utilities to assess a wholesale distribution charge on ESRs.
status as a seller or buyer, arguing that states and distribution utilities should retain authority to manage this aspect of ESRs.
BTM ESRs to buy electricity at wholesale.
Perkins Coie LLP | PerkinsCoie.com
47
wholesale market; but if it does and will resell back to the market, it must be at the wholesale LMP.
to pay the LMP for their charging energy, it does not address whether they can pay some other rate, such as the retail rate or charging off of co-located generation.”
LMP can enter into bilateral transactions to hedge the purchase of that energy.
Perkins Coie LLP | PerkinsCoie.com
48
Perkins Coie LLP | PerkinsCoie.com
49
Perkins Coie LLP | PerkinsCoie.com
50
33 E Main St Ste 201 Madison, WI 53703-3095