DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
Development of High Temperature Insulated Bus Pipe (HTIBP) for High Energy Naval Systems
A Path Forward Plan – Update Rick Worth/NSWCPD, Code 322
December 09, 2015
Insulated Bus Pipe (HTIBP) for High Energy Naval Systems A Path - - PowerPoint PPT Presentation
Development of High Temperature Insulated Bus Pipe (HTIBP) for High Energy Naval Systems A Path Forward Plan Update Rick Worth/NSWCPD, Code 322 December 09, 2015 DISTRIBUTION STATEMENT A. Approved for public release; distribution is
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
December 09, 2015
DISTRIBUTION STATEMENT A. Approved for public release; distribution is unlimited.
distribution product that has been in use in Foreign Navy and Commercial Cruise Ships
– Inner solid copper core or aluminum conductor surrounded by an epoxy resin encased by stainless steel shell that is touch safe – Capable of distributing power at greater densities than conventional cable technologies
products for future CVN shipboard use
– Samples from 2 vendors failed Navy 3 hour Gas Flame Circuit Integrity (GFCI) testing (FY 2005) – Technical challenges and risk proved too great and project put on hold – Subsequently, RFI, SBIR, NSRP Special Project (FY 2009-2013) further investigated HTIBP
developed a 3 and 1 phase HTIBP product (using higher temperature insulation)
– 3 phase passed 3 hour GFCI test Nov 2014, Single phase HTIBP sample passed June 2015 ‒ ATK Corp reps visited Tefelen in Germany Nov 2015 Set up a plan to build US HTIBP production facility early 2016 located near Rocket Center WV – NSWCPD reps in discussion with SEA 05Z TWH to finalize HTIBP Navy cert test program
Overview/Summary:
Connecting Methods for 2 or more HTIBP Sections Standard Bolted Connection Flexible Welded Connection Rigid Welded Connection
– Hybrid Ship Propulsion utilizes electrical energy as a conversion medium – Directed Energy Weapons utilize electrical power vice explosive propellants – Increased surveillance capability needs result in higher electrical power requirements – EMALS allows for sophisticated launch control, uses electrical power vice steam
current (1000 amps and higher) at medium voltages (4 kV and higher)
radius, no tangle-box)
costs
submarines and weapons systems
flame integrity and emergency repair)
525mm 250 500mm 600 mm
7 – 8 cables per phase for 11 kV at 4000 Amps per phase. Therefore space of saving of 1.12 m² representing a 42 % difference.
commercial Insulated Buspipe (IBP) products from two foreign vendors. Testing that was performed in FY 2005 provided good results with the exception of flame / heat resistance. The samples failed to pass the Naval 3 hour Gas flame Circuit Integrity (GFCI) test.
temperature (HT) insulation (N07-201, UniTech LLC). A polyamide resin developed by NASA called RP-46 was used as the insulation material. RP-46 Insulation curing issues are still unresolved. UniTech LLC completed Phase II without positive results. The SBIR Project has not been extended at this time.
Methods’ was completed. A follow on NSRP Special Project was initiated to identify potential HTIBP vendors. With no vendors ready to produce ‘production’ level parts, this special project was cancelled.
322 funding to identify and investigate other vendor’s products and to perform testing on any promising products identified.
Tefelen GmbH has a 3 phase IBP product that uses high temperature
high temperature rated.
GFCI testing. It passed the GFCI test on November 18, 2014. Based on the success of that test, Tefelen developed and shipped a single phase high temperature IBP sample for additional GFCI testing
June 4, 2015. NSWCCD was funded by National Ship Research Program (NSRP) to perform Navy 3 hour GFCI testing on the 3 phase Tefelen provided
passed this test.
followed for this testing in June 2015 at AeroNav Lab in College Point, NY.
three phases of the Tefefen sample. A Hi- pot was used to provide the 8 kV to the center terminal, while the outer two terminals were connected to the return ground of the Hi-pot. The leakage current was monitored by the meter on the Hi-pot and cannot exceed 250mA..
is determined by the capacitance of the
exceeded 10 mA. It Passed Figure 1: Set up showing 1 Phase HTIBP sample, Gas piping, and electrical connections.
test, Tefelen is presently in discussions with ATK in West Virginia to set up a production facility in early 2016.
prepared and presented to the NAVSEA electrical tech warrant holder for
fund this effort.
Two Tefelen Single Phase HTIBP (White) rated at 15 kV at 1300 Amps. And one 600 V rated at 1300 amps (Black)
Tefelen HTIBP Connecting Tube prepared for GFCI Testing
Telefen HTIBP samples
June 2015 - 6 Month Effort WAS COMPLETED
approval by SEA 05Z TWH (G. Blalock) – 1 Year Effort
filters of AIM motor. – 6 Month Effort
– Design approach is different – Material cost is likely higher
Ready
– Develop requirements for DC systems in parallel
– Avoid unique parts for each builder / ship class
Power Utilities to harden substations – Navy will not be the only customer)
Use is becoming common in Military and Commercial ships
– High Power circuits require multiple conductors – Dangerous and time consuming to install / connect – Bend radii are large, compartments are dedicated to changing direction
– Accepted to reduce weight and space claims – Can be installed as part of blocks/modules and then connected – Turns are prefabricated, thus small radii are possible
exception of flame / heat resistance
temperature insulation (N07-201, UniTech LLC)
– Insulation curing issues are still unresolved – Phase II complete without positive result – Project was not extended at this time
– ‘Insulated Buss Pipe Installation Methods’
– Cancelled, no vendors ready to produce ‘production’ level parts
pursue IBP to address both schedule risk and cost issues
provided $38 K for this effort in FY15.
(1580.1), many shipbuilders are participating
HTIBP.
– Test not correctly performed, they are seeking funding to perform ‘Navy Test’ – German Company with US production facilities planned for Fall 2015 – Tefelen’s website: www.Tefelen.com – Tefelen shipped HTIBP samples to NSWCCD/Philly and AeroNavy for Gas Flame Test
documentation for a proposed NSRP/PEO Ships Effort to take HTIBP from TRL 3/4 to 7/8
Heat Rejection wrapped sample performed successfully for 4 hours energized at 24 kV.
– Criteria for IBP Utilization – Standardized Part Recommendations – Design Standards – Installation / Repair procedures
– Difference in design details – Difference in installation labor – Difference in material costs (complete installation) – Secondary impacts
in the test plan. Then the Hi-pot was energized and set to 8 kV. The initial leakage current was 7.6 mA. If the leakage current exceeds 250 mA, the sample is considered to have failed the test.
sample began to burn slightly. It probably would have been better to have used a sample that was 2 feet longer to have prevented that. Those Raychem sleeve areas would normally be covered/protected by a connecting tube in an installation.
then gradually increased to 10 mA, which was the final reading. At 1429, the test was complete with the sample passing. Photos of the test are presented below:
Figure 2: Hi-Pot used to provide 8 kV to sample Figure 3: Yellow flame from Raychem Sleeve burning.
Photos of Test (cont):
Figure 4: The heat rejection wrapping “puffed up” when exposed to the flame Figure 5: The heat rejection wrapping worked well to protect the electrical insulation.