installation issues and solutions
play

Installation Issues and Solutions Andreas Agostin Industrial - PowerPoint PPT Presentation

Installation Issues and Solutions Andreas Agostin Industrial Network Sales Specialist Asia Pacific MTL Instruments Singapore, part of Cooper Crouse-Hinds 22.02.2012 Kuala Lumpur 1 1 Successful Implementation & Improved Operation


  1. Installation – Issues and Solutions Andreas Agostin Industrial Network Sales Specialist Asia Pacific MTL Instruments Singapore, part of Cooper Crouse-Hinds 22.02.2012 Kuala Lumpur 1 1 Successful Implementation & Improved Operation

  2. Introduction Fieldbus is in use since 1998 1 , yet still new for many customers today. This presentation will look at the installation issues and the “lessons learned”, so that you can benefits from their experience. 1 Shell Malampaya is one of the early, larger projects. 1600 FF instruments are in use. The project produced first gas in Oct 2001. Source: J. Seaver , Shell Philippines Exploration B.V., “ Malampaya Deep Water Gas-to-Power Project: Malampaya Subsea Development”, Offshore Technology Conference, 6 May -9 May 2002, Houston, Texas. 2 2 Successful Implementation & Improved Operation

  3. Introduction  The pictures you will see are collected from “real” projects; they are neither simulated nor “demo”.  We will look at – Control room: cabinet design and wiring – Field: Wiring, field junction boxes, field device installation.  Processes typically involve explosion protection methods “intrinsic safety” (I.S. / Ex i; energy limitation by a „barrier‟) or “explosion proof” (Ex d; protection by explosionproof enclosure). Many examples use “IS” as this is a key product of my company and that is where I get involved. 3 3 Successful Implementation & Improved Operation

  4. Disclaimer All products shown serve as EXAMPLE only. In particular, problems shown in conjunction with a product serve as example only. The brand/make/model of the product serving as example is IRRELEVANT . Problems highlighted serve as example only, are do in no way express problems with a particular product, model or brand. 4 4 Successful Implementation & Improved Operation

  5. The conventional system 5 5 Successful Implementation & Improved Operation

  6. Control room – Conventional wiring 2 nd level 1 st level Marshalling junction box Control system and barrier 6 6 Successful Implementation & Improved Operation

  7. Control room – Conventional wiring Marshalling: to group AI / AO / DI / DO / etc 7 7 Successful Implementation & Improved Operation

  8. Control room – Conventional wiring 8 8 Successful Implementation & Improved Operation

  9. Control room – Conventional wiring Long wires, standard length  Allows pre-fabrication of wire  (ferrules, mounting) Conventional signals (4-20mA,  RTD, thermocouple, 0- 5V/10V/24V) – slow, hardware filtered, length less important 9 9 Successful Implementation & Improved Operation

  10. Field – Conventional wiring  Quality (material)  Safety  Location / access  Weight/size, … 10 10 10 Successful Implementation & Improved Operation

  11. Fieldbus versus conventional 11 11 Successful Implementation & Improved Operation

  12. Control room – DCS wiring EXAMPLES Fieldbus Conventional 12 12 Successful Implementation & Improved Operation

  13. Control room – DCS wiring EXAMPLES Installations do not have to look messy. They can be very nice, too. Conventional Fieldbus 13 13 Successful Implementation & Improved Operation

  14. Control room – DCS wiring EXAMPLES Conventional Fieldbus 14 14 Successful Implementation & Improved Operation

  15. Control room – DCS wiring EXAMPLES Fieldbus Fieldbus 15 15 Successful Implementation & Improved Operation

  16. Control room – DCS wiring Important: do not use individual wires to wire cabinet. Use fieldbus cable and shield properly. Why? Higher signal frequency – protect ? them against disturbances. Individual wires will cause crosstalk from one wire to another – communication faults can occur. 16 16 Successful Implementation & Improved Operation

  17. Fieldbus Cable Recommended: Type A cable: Shielded twisted pair Other cable is possible, but there are limitations in terms of achievable cable distance and electromagnetic compatibility (EMC). Fieldbus is a digital “high speed” (31kBit/s) communication, a current modulated signal superimposed on the DC power. 17 17 Successful Implementation & Improved Operation

  18. Fieldbus Cable SWA Multi-pair SWA Shielded pair Foil Foil plus principle shield braided shield Multi-pair (multi-trunk) 18 18 Successful Implementation & Improved Operation

  19. Please not this way Images obscured – Brand is irrelevant. 19 19 Successful Implementation & Improved Operation

  20. Control room – DCS wiring 20 20 Successful Implementation & Improved Operation

  21. Fieldbus system – Field wiring ? • Parallel wiring (terminals) • special wiring blocks • (daisy chaining) 21 21 Successful Implementation & Improved Operation

  22. Fieldbus system – Field junction boxes Principle of wiring distribution in junction box: all devices are in parallel Source: FF AG 140 Rev. 1 22 22 Successful Implementation & Improved Operation

  23. Fieldbus system – Field junction boxes Please not this way 23 23 Successful Implementation & Improved Operation

  24. Fieldbus system – Field junction boxes Use dedicated wiring blocks with built-in electronic short circuit protection. LEDs: - built-in s/c protection 24 24 24 Successful Implementation & Improved Operation

  25. Good Wiring Practices  Test segment wiring before connecting components  Avoid damaging the wire when removing insulation  Ground the cable shield only at one point (at the control room end)  Insulate the ungrounded end of the cable shield (at the instrument)  Ground armor on both sides (potential equalization)  Use crimp ferrules – Ferrule diameter must fit wire – Crimp tool must fit ferrule – Ferrule must fit terminals  Maintain polarity and associated color codes throughout the segment 25 25 Successful Implementation & Improved Operation

  26. Good Wiring Practices Choose right size  Lessons learned:  Torque screwdriver  Wire end ferrules  Right (!) wire strippers  Fieldbus tester Harms wire strands 26 26 Successful Implementation & Improved Operation

  27. Fieldbus Design Tools (Examples) 27 27 Successful Implementation & Improved Operation

  28. Project Procedure Best practice:  Bench test Functional tests and interoperability test  FAT  SAT 28 28 Successful Implementation & Improved Operation

  29. Installation Guidelines  Cable Tests – Experience has shown that new cable irregularities are so infrequent that it is more efficient to check cable after installation  Cable Installation – Verify that cable is properly installed, bypassing impact from wiring components  Segment Checkout – Check of proper wiring of wiring components  Device installation – Check of proper device installation  Loop checkout – Functional test 29 29 Successful Implementation & Improved Operation

  30. Installation tools Portable fieldbus diagnostic test equipment (Handhelds)  Measures relevant fieldbus parameters  Establish baseline after commissioning 30 30 Successful Implementation & Improved Operation

  31. Handheld diagnostic tools 24VDC Host Device Coupler FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator T (non-IS) Spurs H1 Interface Handheld Diagnostic Tool Device 1 Device 2 Device 3 Connect at respective location to obtain accurate measurement. 31 31 Successful Implementation & Improved Operation

  32. Handheld diagnostic tools 24VDC Host Fieldbus barrier FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator Fieldbus barrier Fieldbus T barrier Intrinsically H1 Interface Safe Spurs Handheld Diagnostic Tool Device 1 Device 2 Device 3 To measure at fieldbus barrier/IS segments, Handheld needs to be Ex i approved. Important since the galvanic isolation of fieldbus barrier impacts on measurement. 32 32 Successful Implementation & Improved Operation

  33. Earthing/Grounding  Grounding in the control room  One point grounding only  Continuous shield from control room to the field  Shield not connected at the field instrument  Connect cable armor at both ends (potential equalization) 33 33 Successful Implementation & Improved Operation

  34. Earthing/Grounding 24VDC Host Wiring Block FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator T H1 Interface Device 1 Device 2 Device 3 34 34 Successful Implementation & Improved Operation

  35. Earthing/Grounding 24VDC Host Fieldbus barrier FF Power Supply Computer & Terminator FFPS & Conditioner T &Terminator Fieldbus barrier Fieldbus T barrier Intrinsically H1 Interface Safe Spurs Device 1 Device 2 Device 3 35 35 Successful Implementation & Improved Operation

  36. Local field junction box for 4 instruments. Rust prevented proper grounding, so that separate ground connection was required 36 36 Successful Implementation & Improved Operation

  37. Field – Fieldbus wiring Green: fieldbus Red: Power (Motors, etc) For easy maintenance 37 37 Successful Implementation & Improved Operation

  38. Troubleshooting 38 38 Successful Implementation & Improved Operation

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend