injectors lhc report
play

Injectors & LHC report S. Baird and M. Bernardini on behalf of - PowerPoint PPT Presentation

Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 16/08/2013 LSC - S. Baird, M. Bernardini 1 AD EN/EL : cabling AD-target : pulling completed and connections in progress. Some tests remains TE/VSC :


  1. Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 16/08/2013 LSC - S. Baird, M. Bernardini 1

  2. AD EN/EL : cabling AD-target : • pulling completed and connections in progress. Some tests remains – TE/VSC : • Cryo pumps and sensors are now installed on UHM3107 and UVM3207 – tanks. Some tests still to be realized. Ion pump change is almost finished in sector 2. Some delay on other – places as extremely delicate manipulations. Gauges upgrade progresses well. – BE/BI + TE/VSC : • Ion pump installation none of the MTV screen was replaced, as degasing test slows down the – planning (and there are some problems with the test bench). But not critical for the moment. BHN06: new CERN visit to manufacturer for first coil test. Decision • will be taken by end next week. A plan-B is going to be considered as well in case of further delay. TE/ABT : 1 month additional delay announced for the 2 KFI tanks • (installation postponed at the end of October). Girder line 7000: good progress by design office • 16/08/2013 2 LSC - S. Baird, M. Bernardini

  3. LEIR EN/EL : • cabling FO (fibres optiques) for PSS project is completed and – tested. Other cables (BIW + stopper) are installed. To be tested. – TE/MSC + TE/VSC : • removal of DHV12 on 1/8 was successful. Excellent support – from EN/HE as well. (see picture) BE/BI : • MTV screens are ready, then degasing tests. – Should all be fine for the installation scheduled early October. Removal DHV12 PSS : New access point waiting to be put in service • BE/BI : • last-minutes request to intervene on the 2 BIPM (Beam – Ionisation Profile Monitor) on vacuum sector 5. We plan therefore to open this sector week 35. In preparation. 16/08/2013 LSC - S. Baird, M. Bernardini 3

  4. PS Done • CV Consolidation program: the last Asbestos part removed Zone 12 - – final elbow and valves in PS (Chilled water program) is completed In Progress • CV Consolidation program: cabling started, racks delivered – PS PSS Safety and Access System Installation – Installation of sector zone is progressing. • New access doors will be put in service from week 34 to week 36 • Valves installation on chilled water The Septum 16 External Shielding program: – The earth work is completed, and 2 weeks of Stand-by done • The work of 29 stakes installations is starting. 2 seismograph have been placed • in the PS ring Forecast • EN-EL cabling campaign will start week 34 – Ready for starting the installation of stakes 16/08/2013 LSC - S. Baird, M. Bernardini 4

  5. PSB In progress • Beam Dump Replacement: – Extraction & Disposal of Dump C ore + Beam Pipe → • Done Week 32 Preparation + Test of the Extraction & Disposal of • S hielding → Ongoing Week 33 Extraction & Disposal of S hielding → foreseen end of • Week 33 and Week 34 CV consolidation and maintenance of CV, kickers, – Septa, vacuum beam instrumentation, Magnet and Beam Dump automatic cutting machine Beam stopper, cabling campaign Unexpected Failure • Ring2: Pick-Up Wide Band (BR2.WCM8L1) Vacuum – Leak → 29/07/13 Vacuum Display Leak not repairable (→ due to Titanium-Inox brazing) • New Vacuum Chamber to manufacture + new design • Recovery expected for March/April 2014 • Vacuum Leak 16/08/2013 LSC - S. Baird, M. Bernardini 5

  6. SPS EL cabling works in progress • All transformers are replaced • between BA3 and CCC. MKP disconnected and pumped out, All new transformers in place to prepare the irradiated cable campaign All other works progressing on • schedule. Everything is removed in • LSS1 for the irradiated cabling campaign but 2 shielding and the MAL. Transport and Handling • need to be more studied before intervention. 16/08/2013 LSC - S. Baird, M. Bernardini 6

  7. TT10 Civil Engineering Works Beamline and general services cleared where • necessary and tunnel ready for consolidation works to begin. Support beams already delivered to CERN. • End plates foreseen 20th August. • Chosen contractor (Concrete Repairs Ltd) • preparing teams, training courses, etc. GS-SE preparing planning and method statements • in accordance with tests performed. Installation of beams to commence beginning of • Support delivered September (estimated ~4 weeks work). 16/08/2013 LSC - S. Baird, M. Bernardini 7

  8. LHC - P1  P2 R2E – Pt1: • Left: Piping finalized and cabling started, 3 – weeks ahead of schedule Right: piping just started, 1 week delay, will – be recovered, no impact on end task date UL14 – piping LSS1: • 600A upgrade completed – Survey HLS maintenance in progress – DFBX: consolidation of current leads – AIV magnet test in progress Start of the survey smoothing soon – Arc 12: • Exchange of cryo-magnets in progress – all are connected, electrical tests done; • IC W openings in progress – 16/08/2013 LSC - S. Baird, M. Bernardini 8

  9. LHC - P2  P3 Point 2 • Cooling tower maintenance in progress – Cryogenic maintenance in progress – AUG test realized with positive result – LSS2 • Completion of the cabling campaign – Arc 23 • Preparation for the modification of the HRL valves (UJ32) – Cryogenics consolidation in progress – Vacuum consolidation in progress – Magnet reconnection in progress: all new magnets installed – DN200: partial opening and installation in progress – LSS3 • End of cable pulling to P3.2 – Preparation for the cable campaign: installation of the cable trays – DFBA: Intervention on the Thermoswitch ongoing – Water cooled cables of the DFBAE dismounted – Opening of the vacuum sub-sector for the future new passive absorbers (TCAP) – 16/08/2013 LSC - S. Baird, M. Bernardini 9

  10. LHC - P3  P5 Arc 34 • QRL– compensator removed – Optical fiber replaced – Magnet replacement in progress  Quadrupoles out – QRL compensator from P4 and dipoles from PMI2 removal Vacuum consolidation activities in progress – VSC beam vacuum blowing activities in progress – Walkway installation in progress – LSS4 & P4 • Flexwell campaign complete in underground – Completion of the cabling campaign 22R4, header C – Water cooled cables consolidation in progress – RF maintenance and upgrade – Arc 45 • Magnet exchange in progress, all magnets removed, last – magnet will be installed next week QRL X ray campaign in progress (header C, all QRL) – new – deformed, not leaky compensator on header C Test for MAFI passage through P5 and P3 realised – on 9 th august -->  16/08/2013 LSC - S. Baird, M. Bernardini 10 Passage MAFI P5

  11. LHC – P5  P6 LSS5: • Modification of the cabling for TOTEM ongoing – Completion of the DFBAJ consolidation – R2E – P5 • UJ56/machine side – 6 ducts − Safe-room structure done − Drilling: all ducts are drilled, smoothing in progress − Civil engineering: 1w ahead of schedule UL55 – safe room Arc 56 • QRL xray campaign in progress, all headers, H vacuum SS – SMACC – DFBAK  deformed compensator  2 month delay • Compensator deformed DFBAK M weld in progress (~80%) • W closure will start next week: 2weeks ahead of schedule • Vacuum leak test in progress • Diodes in progress • LSS6 & P6 • Maintenance of cooling tower in progress – MKD-MKB tests on going on beam1 – Cabling campaign started on right side – Consolidation of the DFBA ongoing – 16/08/2013 LSC - S. Baird, M. Bernardini 11

  12. LHC – P6  P7 Arc 67 • SMACC in progress: – 80% shunt installed • DFBA consolidation – TZ76 – Fire Detection equipment supports R2E – P7: • TZ76 – vault painting done – Cable trays installed and rack installation just started – Smoke detector in RR installed, and in progress in TZ76 – LSS7 • Vacuum sectors ready for the new doors project: – 4x collimators and 2x correctors magnet removed Consolidation of the DFBA ongoing – 13kA & 600A upgrade will start soon – LSS 7: Magnet removal 16/08/2013 LSC - S. Baird, M. Bernardini 12

  13. LHC - P7  P1 Arc 78 • DN200 – finished – M opening finished – Desoldering BB started – DFBAN consolidation in progress – LSS8 &P8 • Consolidation of the DFBA ongoing – R2E @P8 • Ventilation control cabinet to be – rescheduled Cryo activities ahead of schedule – Arc 81 • - DFBAP consolidation in progress - Cryo module consolidation in progress - M opening in progress: IC train started - DN200 installation in progress 16/08/2013 LSC - S. Baird, M. Bernardini 13

  14. General infrastructures Sunrise upgrade postponed in Sept 2013 • Demineralised water available: work is being • finalized 400kV & 66kV maintenance and • consolidation – Maintenance finished, no more power limitation: some additional tests will be performed in sept, no impact. Fire safety wall – RTE auto-transfert test postponed in September (before Open days) – Meyrin site powered off during 10’ 66kV maintenance 16/08/2013 LSC - S. Baird, M. Bernardini 14

  15. Overall progress Injectors: on schedule, but to follow • AD – BHN06 coil manufacturing – LHC on schedule • R2E - On schedule – SMACC – to follow – Good progress M line welding • DFBA schedule • General infrastructures: good progress • Impact of summer holidays will be assessed in September • 16/08/2013 LSC - S. Baird, M. Bernardini 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend