Injectors & LHC report
- S. Baird and M. Bernardini
- n behalf of OSS members
16/08/2013 LSC - S. Baird, M. Bernardini 1
Injectors & LHC report S. Baird and M. Bernardini on behalf of - - PowerPoint PPT Presentation
Injectors & LHC report S. Baird and M. Bernardini on behalf of OSS members 16/08/2013 LSC - S. Baird, M. Bernardini 1 AD EN/EL : cabling AD-target : pulling completed and connections in progress. Some tests remains TE/VSC :
16/08/2013 LSC - S. Baird, M. Bernardini 1
– pulling completed and connections in progress. Some tests remains
– Cryo pumps and sensors are now installed on UHM3107 and UVM3207
– Ion pump change is almost finished in sector 2. Some delay on other places as extremely delicate manipulations. – Gauges upgrade progresses well.
– none of the MTV screen was replaced, as degasing test slows down the planning (and there are some problems with the test bench). But not critical for the moment.
will be taken by end next week. A plan-B is going to be considered as well in case of further delay.
(installation postponed at the end of October).
16/08/2013 LSC - S. Baird, M. Bernardini 2 Ion pump installation
– cabling FO (fibres optiques) for PSS project is completed and tested. – Other cables (BIW + stopper) are installed. To be tested.
– removal of DHV12 on 1/8 was successful. Excellent support from EN/HE as well. (see picture)
– MTV screens are ready, then degasing tests. Should all be fine for the installation scheduled early October.
– last-minutes request to intervene on the 2 BIPM (Beam Ionisation Profile Monitor) on vacuum sector 5. We plan therefore to open this sector week 35. In preparation.
16/08/2013 LSC - S. Baird, M. Bernardini 3 Removal DHV12
– CV Consolidation program: the last Asbestos part removed Zone 12 - final elbow and valves in PS (Chilled water program) is completed
– CV Consolidation program: cabling started, racks delivered – PS PSS Safety and Access System Installation
– The Septum 16 External Shielding program:
in the PS ring
– EN-EL cabling campaign will start week 34
16/08/2013 LSC - S. Baird, M. Bernardini 4 Ready for starting the installation of stakes Valves installation on chilled water
– Beam Dump Replacement:
Done Week 32
Shielding → Ongoing Week 33
Week 33 and Week 34
– CV consolidation and maintenance of CV, kickers, Septa, vacuum beam instrumentation, Magnet and Beam stopper, cabling campaign
– Ring2: Pick-Up Wide Band (BR2.WCM8L1) Vacuum Leak → 29/07/13
16/08/2013 LSC - S. Baird, M. Bernardini 5
Vacuum Display
Beam Dump automatic cutting machine Vacuum Leak
between BA3 and CCC.
schedule.
16/08/2013 LSC - S. Baird, M. Bernardini 6
LSS1 for the irradiated cabling campaign but 2 shielding and the MAL.
need to be more studied before intervention.
All new transformers in place MKP disconnected and pumped out, to prepare the irradiated cable campaign
necessary and tunnel ready for consolidation works to begin.
preparing teams, training courses, etc.
in accordance with tests performed.
September (estimated ~4 weeks work).
16/08/2013 LSC - S. Baird, M. Bernardini 7 Support delivered
– Left: Piping finalized and cabling started, 3 weeks ahead of schedule – Right: piping just started, 1 week delay, will be recovered, no impact on end task date
– 600A upgrade completed – Survey HLS maintenance in progress – DFBX: consolidation of current leads in progress – Start of the survey smoothing soon
– Exchange of cryo-magnets in progress
– IC W openings in progress
16/08/2013 LSC - S. Baird, M. Bernardini 8 UL14 – piping AIV magnet test
– Cooling tower maintenance in progress – Cryogenic maintenance in progress – AUG test realized with positive result
– Completion of the cabling campaign
– Preparation for the modification of the HRL valves (UJ32) – Cryogenics consolidation in progress – Vacuum consolidation in progress – Magnet reconnection in progress: all new magnets installed – DN200: partial opening and installation in progress
– End of cable pulling to P3.2 – Preparation for the cable campaign: installation of the cable trays – DFBA: Intervention on the Thermoswitch ongoing – Water cooled cables of the DFBAE dismounted – Opening of the vacuum sub-sector for the future new passive absorbers (TCAP)
16/08/2013 LSC - S. Baird, M. Bernardini 9
– QRL– compensator removed – Optical fiber replaced – Magnet replacement in progress Quadrupoles out from P4 and dipoles from PMI2 – Vacuum consolidation activities in progress – VSC beam vacuum blowing activities in progress – Walkway installation in progress
– Flexwell campaign complete in underground – Completion of the cabling campaign – Water cooled cables consolidation in progress – RF maintenance and upgrade
– Magnet exchange in progress, all magnets removed, last magnet will be installed next week – QRL X ray campaign in progress (header C, all QRL) – new deformed, not leaky compensator on header C – Test for MAFI passage through P5 and P3 realised
16/08/2013 LSC - S. Baird, M. Bernardini 10 Passage MAFI P5 QRL compensator removal 22R4, header C
– Modification of the cabling for TOTEM ongoing – Completion of the DFBAJ consolidation
− Safe-room structure done − Drilling: all ducts are drilled, smoothing in progress − Civil engineering: 1w ahead of schedule
– QRL xray campaign in progress, all headers, H vacuum SS – SMACC
– Maintenance of cooling tower in progress – MKD-MKB tests on going on beam1 – Cabling campaign started on right side – Consolidation of the DFBA ongoing
16/08/2013 LSC - S. Baird, M. Bernardini 11 UJ56/machine side – 6 ducts UL55 – safe room Compensator deformed DFBAK
– SMACC in progress:
– DFBA consolidation
– TZ76 – vault painting done – Cable trays installed and rack installation just started – Smoke detector in RR installed, and in progress in TZ76
– Vacuum sectors ready for the new doors project:
4x collimators and 2x correctors magnet removed
– Consolidation of the DFBA ongoing – 13kA & 600A upgrade will start soon
16/08/2013 LSC - S. Baird, M. Bernardini 12 TZ76 – Fire Detection equipment supports LSS 7: Magnet removal
– DN200 – finished – M opening finished – Desoldering BB started – DFBAN consolidation in progress
– Consolidation of the DFBA ongoing
– Ventilation control cabinet to be rescheduled – Cryo activities ahead of schedule
16/08/2013 LSC - S. Baird, M. Bernardini 13
finalized
consolidation
– Maintenance finished, no more power limitation: some additional tests will be performed in sept, no impact. – RTE auto-transfert test postponed in September (before Open days) – Meyrin site powered off during 10’
16/08/2013 LSC - S. Baird, M. Bernardini 14 Fire safety wall 66kV maintenance
– AD – BHN06 coil manufacturing
– R2E - On schedule – SMACC – to follow
16/08/2013 LSC - S. Baird, M. Bernardini 15