Infrastructure Consolidation of Accelerators Injectors (civil - - PowerPoint PPT Presentation

infrastructure consolidation of accelerators injectors
SMART_READER_LITE
LIVE PREVIEW

Infrastructure Consolidation of Accelerators Injectors (civil - - PowerPoint PPT Presentation

Infrastructure Consolidation of Accelerators Injectors (civil engineering) (civil engineering) Cristiana Colloca GS/SEM ATOP 5th of March 2009 / Cristiana Colloca GS/SEM ATOP MARCH 2009 Contents CONCERNED Surface - Roofs,


slide-1
SLIDE 1

Infrastructure Consolidation

  • f Accelerators Injectors

(civil engineering) (civil engineering)

Cristiana Colloca GS/SEM – ATOP 5th of March 2009 /

Cristiana Colloca GS/SEM – ATOP – MARCH 2009

slide-2
SLIDE 2

Contents

CONCERNED Surface

  • Roofs, façades, floors, windows, sanitary etc. all buildings (machine and tertiary)
  • Roads, parking, green areas, storage surfaces, etc.
  • Cleansing

Underground tunnels Underground tunnels NOT CONCERNED For all the buildings (machine and tertiary) surface and underground: For all the buildings (machine and tertiary), surface and underground:

  • HVAC
  • Heating plants and heating network
  • Electrical equipment
  • Lifting and transport equipment
  • Automatic doors
  • Kitchen equipment
  • Kitchen equipment
  • ...

THESE WORKS ARE NOT CONVERED BY THE NORMAL MAINTENACE

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

THESE WORKS ARE NOT CONVERED BY THE NORMAL MAINTENACE CARRIED OUT EACH YEAR

slide-3
SLIDE 3

References f

DATA AND DETAILS IN SITE CONSOLIDATION ON CIVIL ENGINEERING AND TECHNICAL INFRASTRUCTURE AT CERN AND TECHNICAL INFRASTRUCTURE AT CERN 2008 UPDATE

  • C. Colloca, M. Nonis, P. Pepinster

du 18.08.2008 SITE CONSOLIDATION ON CIVIL ENGINEERING AND TECHNICAL INFRASTRUCTURE AT CERN AND TECHNICAL INFRASTRUCTURE AT CERN 2009 UPDATE

  • C. Colloca, P. Pepinster

du 24.02.2009

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-4
SLIDE 4

Roofs consolidation : criteria Roofs consolidation : criteria

Categories of roofs repair: 1 - Sensitive equipment: roof leaks are ff i h f f i affecting the safety of equipment and/or the running of an accelerator; critical situation; immediate i t ti i i d intervention is required 2 - High frequency leaks: the roof is no more waterproof and leaks are more waterproof and leaks are detected very often; conditions will become critical if an intervention is not taken within a short time not taken within a short time

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-5
SLIDE 5

Roofs consolidation - SENSITIVE Roofs consolidation SENSITIVE

2470/SG4 Point 4 SEXP 1988 532 9 532 Steel panels 106 Location Function Year of Construction Area to be renovated Material Cost Estimate (kCHF) Total area (m2) Total ODM 2004- 2008 Renovated area (m2) Year Building 2470/SG4 LHC/LEP SEXP 1988 532 9 532 Steel panels 106 2285/SX2 Point 2 LHC/LEP SEXP 1988 1800 9 1800 Bituminous flat roof 300 150 Meyrin EXPE 1958 3550 6 430 2005 3120 Asbestos panels 800 156 Meyrin ASSE 1972 398 6 139 2001 259 Plastic panels 72 Point 6 2675/SR6 Point 6 LHC/LEP SSSTA 1986 1834 6 1834 Bituminous flat roof 366 887/EHN1 Prévessin EXPE 1977 14000 6 1000 Bituminous flat roof 200 355 Meyrin SSSTA 1958 2082 4 486 2001 450 Bituminous flat roof 100 181 Meyrin STOC 1969 2865 3 1’432 2002 1432 Bituminous flat roof 300 872/BA5 Point 5 SPS TECH 1974 1100 2 1100 Bituminous flat roof 180 363 Meyrin EXPE 1975 1181 1 188 2004 993 Bituminous flat roof 197 918 Prévessin BULA 1979 942 4 942 Bituminous flat roof 150 2771 1430 TOTAL FOR INJECTORS TOTAL

~51%

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-6
SLIDE 6

Roofs consolidation - FREQUENT Roofs consolidation FREQUENT

Building Location Function Yea of Total area Total ODM Renovated Year Area to be Material Cost Estimate Building Location Function Construction (m2) 2004- 2008 area (m2) Year renovated Material Estimate (kCHF) 867 Prévessin ASSE 1973 11437 20 3100 2001-2006 8337 Bituminous flat roof 1680 904 Prévessin EXPE 1976 950 18 131 2000 819 Bituminous flat roof 900 504 Meyrin HEBE 1971 1465 17 410 1996-1998 1055 Bituminous flat roof 210 866 Prévessin BULA 1973 2630 17 2630 Bituminous flat roof 540 108 Meyrin ATEL 1965 890 15 890 Bituminous flat roof 176 865 Prévessin BULA 1973 2202 14 481 2005 1721 Bituminous flat roof 341 864 Prévessin BULA 14 Bituminous flat roof 540 31 Meyrin BULA 1973 670 13 60 2000 610 Bituminous flat roof 120 102 Meyrin ATEL 1964 1530 12 1530 Bituminous flat roof 300 30 M i BULA 12 186 30 Meyrin BULA 12 186 5 (DEP) Meyrin BULA 12 Rain water drains 60 112 (barracks) Meyrin BULA 10 Bituminous flat roof 60 2 Meyrin BULA 1955 1066 10 1066 Bituminous flat roof 211 2 Meyrin BULA 1955 1066 10 1066 Bituminous flat roof 211 3 Meyrin BULA 1957 1117 10 305 1998 812 Bituminous flat roof 161 5485 3101 TOTAL FOR INJECTORS TOTAL

~57% ~57%

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-7
SLIDE 7

Facades consolidation Facades consolidation

Carbonatation on concrete and corroded steel icing deicing cycles corroded steel, icing-deicing cycles... (spalling phenomena etc.)

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-8
SLIDE 8

Facades consolidation

Building Location Year of Construction Function Problem description Surface to repair [m2] Cost Estimate (kCHF) Priority 255 Meyrin 1960 REFR Concrete carbonatation and steel corrosion 900 317 1 863 Point 6 SPS 1975 REFR Concrete carbonatation and steel corrosion 1320 465 1 30-112 Meyrin 1971 BULA Concrete carbonatation and steel corrosion 6300 1480 1 269 Meyrin 1970 SST A Concrete carbonatation and steel corrosion 150 53 1 36 Meyrin 1969 BULA Concrete carbonatation and steel corrosion 936 330 1 60 Meyrin 1959 BULA Deteriorated concrete façade with steel corrosion (South façade) 250 89 1 Deteriorated concrete façades with steel corrosion (NW 504 Meyrin 1971 HEBE Deteriorated concrete façades with steel corrosion (NW façade and balcony of SW façade) 350 123 1 132 Meyrin 1967 ST OC Concrete carbonatation and steel corrosion 50 18 2 118 Meyrin 1985 AT EL Concrete carbonatation and steel corrosion 221 78 2 168 Meyrin 1968 ASSE Concrete carbonatation and steel corrosion 700 247 2 149 Meyrin 1958 ST OC Concrete carbonatation and steel corrosion 83 294 2 215 M i 1966 SST A C t b t ti d t l i 134 47 2 215 Meyrin 1966 SST A Concrete carbonatation and steel corrosion 134 47 2 203 Meyrin 1965 ST AT Concrete carbonatation and steel corrosion 700 247 2 206 Meyrin 1962 SST A Concrete carbonatation and steel corrosion 155 55 2 286 Meyrin 1970 T ECH Concrete carbonatation and steel corrosion 115 40 2 361 Meyrin 1971 T ECH Concrete carbonatation and steel corrosion 221 78 2 250-258 Meyrin 1959-62 SST A-ST OC Concrete carbonatation, steel corrosion 200 71 2 31 Meyrin 1973 BULA T op edges of facades with spalled concrete over access zone 50 17 2 281 Meyrin 1970 T ECH Deteriorated concrete façades with steel corrosion and spalled concrete 540 190 2 287 Meyrin 1970 T ECH Deteriorated concrete façades with steel corrosion and spalled concrete (NW and SE façades) 300 90 2 102 Meyrin 1964 AT EL Concrete carbonatation and steel corrosion 300 106 3 226 Meyrin 1971 SST A Deteriorated concrete façade with steel corrosion (S and E façades) 100 35 3 25 Meyrin 1975 BULA Deteriorated concrete façades several cracks (SW and SE Façades) 230 81 3 4551 TO TAL 984 TO TAL FO R INJECTO RS

~22%

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-9
SLIDE 9

Other Miscellaneous

Windows claddings

Consolidation Measures - Buildings

Windows, claddings, spalling concrete, painting etc.

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-10
SLIDE 10

Other Miscellaneous Consolidation Measures - Buildings

Building Location Year of Construction Function Problem-Description Surface to repair (m2) Cost Estimate (kCHF) 192 Meyrin 1971 CONT Deteriorated floor and ceiling in main floor 550 95 253 M i 1958 DIST C d d l b f b ildi 165 40 253 Meyrin 1958 DIST Corroded external support beams of building 165 40 291 Meyrin 1969 ACCE Deteriorated wooden floor 100 16 867 Prevessin 1973 ASSE Metal cladding with corroded areas 140 30 112 Meyrin 1971 BULA Metal cladding with scaling paint, some 571 86 112 Meyrin 1971 BULA points of corrosion along facade 571 86 185 Meyrin 1975 EXPE Inside panels (walls and ceiling) containing asbestos are unsecured 450 181 Meyrin 1969 STOC Metal cladding with unfastened panels and corroded areas 500 70 corroded areas 864, 865, 866 Prevessin 1973 BULA Completion of replacement window frames campaign 60 501 Meyrin BULA Terrace repair 250

TOTAL 1097 TOTAL 1097 TOTAL FOR INJECTORS 90

~8%

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-11
SLIDE 11

Cleansing

  • CERN does not comply with

applicable (no mix of clear and waste water and fosses septiques (ex. waste water and fosses septiques (ex. SPS))

  • very bad condition of the

y drainage equipment due to age and progressive invasion of roots penetrating the pipes p g p p

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-12
SLIDE 12

Asbestos removal

The estimated cost for the asbestos removal from civil asbestos removal from civil engineering structures is still kept to 5 MCHF for all CERN site, not including the ancillary work such including the ancillary work such as the relocation in

  • ther

buildings

  • f

the working personnel for the duration of the personnel for the duration of the work. Main works are:

  • Bldg 150
  • PS technical galleries

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-13
SLIDE 13

Consolidation Requests - Surface q f

I t ti T l Overall cost Total cost f 'I j t ’ Proposed Annual Spend Intervention Typology (kCHF) for 'Injectors’ (kCHF) p for ‘Injectors’ (kCHF) Civil engineering Roof (sensitive equipment) 2771 1430 150 Roof (high frequency) 5490 3110 150 Facades 4551 984 500 Windows 4090 60 60 Toilets, sanitary installations 450 200 200 Other interventions 1097 30 30 Roads& Parking areas 1300 500 500 Cleansing 300 120 120 Asbestos removal 5000 4000 800 Asbestos removal 5000 4000 800 TOTAL 25049 10434 2510

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-14
SLIDE 14

Minimal Consolidation Program 2009 g for Injectors - Surface

Intervention Typology Total cost (kCHF) Roofs (EHN1, BA5) 380 Facades (863, 867) 500 Windows (864, 865, 866) 60 Toilets, sanitary installations 50 Roads & Parking areas 100 Cleansing 50 TOTAL 1940

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-15
SLIDE 15

Underground Consolidation *

Previous canalisations of leaks were done i fl ibl PVC b Th d

  • PS, SPS, Booster

using flexible PVC membranes. These need to be changed for the stainless steel channels now used, in order to comply ith t fi with current fire norms.

Cristiana Colloca GS/SEM – ATOP 5th of March 2009 *Contribution of Richard Francis Morton GS/SEM

slide-16
SLIDE 16

Underground Consolidation

A campaign of repainting of the tunnel

g

  • PS, SPS, Booster

p g p g vault is required to reduce the amount

  • f dust and contamination caused by

water ingress and decay of the original

  • paint. This work may also require some

superficial repair to the concrete.

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-17
SLIDE 17

Underground Consolidation - SPS

Significant areas of tunnel floor have been contaminated by hydrocarbons and will require

g

hydrocarbons and will require resurfacing. Additional work is i d t required to ensure construction joints are repaired and levelled to allow transport to pass allow transport to pass.

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-18
SLIDE 18

Underground Consolidation - SPS

Construction of an oil separator at one or more locations

g

underground to allow oil to be removed from the drainage system before it is pumped to surface. A campaign of decalcification and p g cleaning of the central drain is long

  • ver due. This work is currently

hampered by the lack of water supply p y pp y at regular intervals along the tunnel.

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-19
SLIDE 19

Other Miscellaneous Consolidation Measures - Underground

A campaign of repair/replacement of the concrete covers to the technical gallery in the PS is required to make safe the floor technical gallery in the PS is required to make safe the floor. Many of the toilets in the underground SPS complex are in a poor state of repair and require renovation.

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-20
SLIDE 20

Consolidation Requests - Underground

Intervention Typology * Total cost (kCHF)

Consolidation Requests Underground

Replacement PVC Gutters 120 Renovation of Tunnel Vault 150 Renovation of Tunnel Floor 200 Oil Interceptor T.B.A. Drain Decalcification and T B A Cleaning T.B.A. PS Concrete cover renewal T.B.A. Renovation of Underground 120 g Toilets 120 TOTAL 590 *The amount of work possible is entirely a function of access during shutdown. This may mean spreading the work over several shutdowns.

Cristiana Colloca GS/SEM – ATOP 5th of March 2009

slide-21
SLIDE 21

Conclusions

CERN infrastructure (surface and underground) is rapidly deteriorating trends are negative (i e roofs) => overall deteriorating, trends are negative (i.e. roofs) => overall consolidation planning on large scale is a major issue to be treated because of safety, legal, operational and economical reasons Consolidation costs are constantly rising due to the lack of Consolidation costs are constantly rising due to the lack of intervention (ex. Anti-carbonatation treatments) 2009 consolidation program is based on most urgent interventions k t d b t d di known today, but depending on:

  • Budget (available today = 800 kCHF for all CERN (!))
  • Boundary conditions during the approval of the program

y g pp p g (accelerator operation, weather conditions, etc.)

  • Number of FTE assigned to perform the program

Increasing expectation for consolidation activities from CERN Increasing expectation for consolidation activities from CERN community, visible actions need to be done to avoid widespread feeling of frustration

Cristiana Colloca GS/SEM – ATOP 5th of March 2009