Indonesia Clean Energy Development Project (ICED) Lessons Learned - - PowerPoint PPT Presentation

indonesia clean energy development project iced
SMART_READER_LITE
LIVE PREVIEW

Indonesia Clean Energy Development Project (ICED) Lessons Learned - - PowerPoint PPT Presentation

Indonesia Clean Energy Development Project (ICED) Lessons Learned Development, Construction and Operations MHP in Indonesia June 2014 1a Common Problems/Lessons Learned Hydrology and Energy Project Layout Water Conveyance Construction


slide-1
SLIDE 1

Indonesia Clean Energy Development Project (ICED)

Lessons Learned Development, Construction and Operations MHP in Indonesia

June 2014

1a

slide-2
SLIDE 2

Common Problems/Lessons Learned

Hydrology and Energy Project Layout Water Conveyance Construction Problems Contracting and Risk Allocation Operations Experiences

2

slide-3
SLIDE 3

Hydrology and Energy – PROBLEMS

Daily versus Monthly or Periodic Averages Analysis too simple Estimates of losses Grid stability? Water conveyance? Efficiency Estimates

3

slide-4
SLIDE 4

The Importance of Daily Flow Analysis

4

slide-5
SLIDE 5

Hydrology and Energy SOLUTIONS

Use method for energy not dam construction or irrigation Analysis too simple- Use details Need to test hydrology Run actual daily data with specific losses and efficiency Estimates of losses Grid stability? Water conveyance? Efficiency Estimates

5

slide-6
SLIDE 6

Project Layout Potential power abandoned due to layout of : Powerhouse Intake Flushing gates Desanders Velocity and Hydraulic Losses Head Pond Hydraulics Tailrace Construction

6

slide-7
SLIDE 7

Project Layout – Powerhouse Elevation PROBLEM – Design sacrifices head and energy

Most projects are Francis Turbines Applications Frequently, an open powerhouse in a horizontal orientation is designed Well above tailwater Well above flood level Barrier is placed in tailrace to provide backwater pressure More efficient layout is “Vertical Powerhouse” Equipment is placed in a pit, well below powerhouse openings River tailwater sets the back water level Gates used to isolate

7

slide-8
SLIDE 8

Example of Vertical Orientation Powerhouse

8

slide-9
SLIDE 9
slide-10
SLIDE 10

10

slide-11
SLIDE 11

Project Layout – PROBLEM Intake Design

11

slide-12
SLIDE 12

Project Layout - Problems with Intake PROBLEM – DEBRIS PROBLEMS AND HEAD LOSS Make entire river make a right turn Enter Gates Make another right turn Adjacent to flushing- All debris pulled towards Power Intake

slide-13
SLIDE 13

Project Layout – Proposed Intake Improvements SOLUTIONS: Open up intake to river with lower velocity Keep intake above river bottom as possible Keep higher than flushing gates Use tainter gate for flushing Avoid “bending flow as possible

slide-14
SLIDE 14

Project Layout - Flushing Gates PROBLEM – INADEQUATE FLUSHING AND DAMAGE Standard is Leaf or Sluice gate Usually too small and not strong Gates Jam or get damaged Debris is not passed

14

slide-15
SLIDE 15

Project Layout - Flushing Gates SOLUTIONS?

  • Use tainter gate if possible
  • Double gating for sluice or leaf gates
  • Provide for stop logs
  • Use multiple gates and large gates

15

slide-16
SLIDE 16

Tainter Gate

slide-17
SLIDE 17

Project Layout – Silt Chambers or Desanders PROBLEM – High Cost – Questionable Value Not all projects need them They are expensive Primary use – keep sand and abrasive material from the turbine What is at risk? Runner and seal wear in the turbine

17

slide-18
SLIDE 18

Project Layout – Silt Chambers or Desanders SOLUTIONS: ASK - Do you need one at all? Is sand present? Will proposed structure remove it? Is it less expensive to have turbine spares? Use the diversion pond as primary desander Use a head pond as secondary desander

18

slide-19
SLIDE 19

Layout: Flow Velocity and Losses PROBLEMS: Some velocities in canal and penstock are too high Excessive losses – Unstable flow Surge problems Losses often not correctly calculated Surge relief for penstocks inadequate

19

slide-20
SLIDE 20

Layout: Flow Velocity and Losses SOLUTIONS Pay strict attention to designs Double check hydraulic losses and surge Canal Velocity should be 0.7 m/sec and no more than 1 m/sec Double check any calculations for penstock surge Check Turbine Manufacturer for pressure rises

  • n trips

20

slide-21
SLIDE 21

Project Layout – Head Pond Hydraulics PROBLEMS:

Head ponds are not designed adequately:

  • Inadequate submergence of penstock opening
  • Hydraulically unfriendly

Result:

  • Vortices
  • “Starved” intakes

= LOST ENERGY

slide-22
SLIDE 22

Project Layout – Head Pond Hydraulics SOLUTIONS:

  • Substantial submergence for penstock inlet
  • Hydraulic transition at penstock intake
  • Large head pond to still flow and maintain operations
  • Have head pond reviewed by experienced hydraulic engineer
slide-23
SLIDE 23

Project Layout – Tailrace Construction PROBLEM:

  • Like Powerhouse – Tailrace well above river level
  • Barrier in tailrace to produce back pressure

Result – Lost potential energy from the site

SOLUTION:

  • Tailrace should be set by river level with gates to shut off

turbines for maintenance and repair.

slide-24
SLIDE 24

WATER CONVEYANCE – Canals, Penstocks, Tunnels PROBLEM: Significant construction cost over runs and other difficulty in constructing canals

  • Excavation Materials unknown
  • Massive cuts without sufficient spoil areas
  • Unstable slopes
slide-25
SLIDE 25

WATER CONVEYANCE – Canals, Penstocks, Tunnels PROBLEM: Significant construction cost over runs and other difficulty in constructing canals

  • Canal Design and Cost Estimates leave out:
  • Geotechnical Exploration
  • Slope Stability
  • Drainage crossing
  • Public safety
  • Foundation stabilization
  • Rock excavation
  • Structural lining
  • Proper Spoil
  • Room for Access Road
slide-26
SLIDE 26

WATER CONVEYANCE – Canals, Penstocks, Tunnels PROBLEM: Canal Dynamics make Complex Operations

  • Flow changes cannot be made quickly
  • Instrumentation is often missing
  • Elevation changes in head pond/canal/intake only

way to change flow

  • Inefficient operations when not at full output
slide-27
SLIDE 27

Project Elements – Diversion and Intake

27

slide-28
SLIDE 28

WATER CONVEYANCE – Canals, Penstocks, Tunnels SOLUTIONS:

  • Buried Penstocks- reduce cut and slope problems
  • Tunnels where feasible
  • Combination of canal/Tunnel
  • Use all costs in selecting conveyance design
  • Consider operating efficiency
  • Penstocks and tunnels can operate under

pressure and simplify operations

slide-29
SLIDE 29

WATER CONVEYANCE – Canals, Penstocks, Tunnels ADVANTAGES OF PRESSURIZED SYSTEM

  • Only handle/clean water once
  • Eliminate head pond
  • Simplify operations
  • Quick response by system to river change
slide-30
SLIDE 30

WATER CONVEYANCE – Canals, Penstocks, Tunnels DISADVANTAGES OF PRESSURIZED SYSTEM

  • Cost might be higher
  • Surge relief still needed for Francis Turbines
  • Underground works (tunnel) also have

construction risk

slide-31
SLIDE 31

Construction Issues

PROBLEM: Construction Contracts do not Allocate Risk Contractors do not provide fixed cost contracts

  • Project not well defined before “EPC”
  • Owners do not provide detailed information to fix

prices;

  • Owners do not want to pay contractors risk

premium;

  • Cost expectations of projects are not realistic
slide-32
SLIDE 32

Construction Issues

PROBLEM: Construction Contracts do not Allocate Risk

RESULT:

  • Cost Over-Run
  • Schedule delay
  • Changes in middle of construction
  • Disappointing Quality
  • Little control by Owner over Contractor
slide-33
SLIDE 33

Construction Issues

SOLUTIONS – Contracts that Allocate Risk

  • Contractors are in the best position to manage it
  • Sufficient information from the developer is

necessary – more details than now provided

  • Risk Premium included in pricing
  • Negotiations for risk understanding and sharing
slide-34
SLIDE 34

Construction Issues– Environmental Damage

PROBLEM: Poor Protection of Environment

RESULT:

  • Poor practices result in landscape scars
  • Accidents and landslides

SOLUTIONS

  • Diligence on part of Owner’s team
  • Contract for and enforce Environmental

Protection

  • Penalty Clauses
slide-35
SLIDE 35

Construction Issues

SOLUTIONS:

  • Better Project Preparation
  • Analysis of Water Conveyance Options
  • Discussion of Risk Allocation with Contractors
  • Develop proper bid documents that allocate risks
  • Negotiate Risk Sharing
  • Keep Design Engineer involved
  • Site Presence by Owner and Design Engineer
  • Formal Quality Control Program
slide-36
SLIDE 36

Allocating Risk in Civil Contracting In order for an Owner to allocate risk to a Good Contractor:

  • Define EPC clearly
  • Provide a performance specification and

definition

  • Clarify project constraints
  • Substantial topography, cleared areas and good

geotechnical data. EXACTLY WHAT ARE YOU BUYING?

slide-37
SLIDE 37

EQUIPMENT CONTRACTING PROBLEM: Poor E&M Equipment or Controls = Excessive Outage

  • “Project can’t afford expensive equipment”
  • “Instrumentation not necessary”
  • Components and auxiliaries questionable quality
  • High outage rates and marginal efficiencies are

not economic

  • Replacement of equipment prematurely is very

expensive

slide-38
SLIDE 38

EQUIPMENT CONTRACTING SOLUTIONS:

  • Develop relationships with better manufacturers
  • Equipment quality not by country of origin but by

manufacturer

  • If there is any question, go see installation
  • Provide clear specifications of what is needed

including quality

  • Ask for instrumentation to operate plant
  • Know bill of materials before signing the contract
slide-39
SLIDE 39

EQUIPMENT CONTRACTING SOLUTIONS:

  • Buy internationally available components
  • Buy components by manufacturers with

reputations

  • Put instrumentation in the project
  • Automate as possible – it is inexpensive
  • Electronic components continue to get cheaper
slide-40
SLIDE 40

Excitation 1990 Excitation 2012

slide-41
SLIDE 41

OPERATIONS ISSUES

  • Cooling water systems
  • Poor equipment components
  • Limited operation information
  • Grid Connection and Quality
  • High outage rates
  • Spare Parts
slide-42
SLIDE 42

Operations – Cooling Water System PROBLEM: Cooling water system shuts down causing

  • utage
  • Usually once-through cooling water is designed
  • Water is warm and has many micro organisms
  • Filters clog regularly

SOLUTION: Implement a recirculating system from the beginning

slide-43
SLIDE 43

Operations: Poor equipment components PROBLEM: Poor components cause shutdown, high maintenance, damage to other components, questionable efficiency SOLUTIONS:

  • Most post-commissioning problems are painful to

solve

  • Replace poor parts with higher quality
  • Avoid these problems by paying for good value
slide-44
SLIDE 44

Operations: Limited data for Operations PROBLEM: Actually knowing site operation efficiency is impossible SOLUTIONS:

  • Level sensors at key components, diversion,

desander, head pond

  • Instrumentation for pressures and temperatures
  • SCADA system
  • Automation
slide-45
SLIDE 45

Operations: Grid Connection Quality and Issues PROBLEM: High transmission losses and outage rates

  • Voltage and frequency changes
  • Long 20 KV interconnection
  • Generating unit cycling off and on

SOLUTIONS:

  • Interconnection Guidelines
  • Help PLN have a stable line
  • Provide good controls for reaction of generator
slide-46
SLIDE 46

Operations: Spare Parts PROBLEM: Plant outage without proper spares SOLUTIONS:

  • Do risk analysis of components to consider what to

buy

  • Insist on internationally available components
  • Replace spares as used
  • Have suppliers on hand for emergency needs
slide-47
SLIDE 47

SMALL HYDROPOWER SECTOR FIVE UNIQUE OPPORTUNITIES IN INDONESIA

1. Huge resource of good sites 2. Power is needed and

  • ffsetting expensive

power 3. Capital is available 4. Permitting reasonably easy 5. Getting a PPA is relatively simple

47

slide-48
SLIDE 48

Successful Risk Management = Long Term Asset

48