PacifiCorp Stakeholder Meeting on Regional Independent System Operator Integration
June 24, 2016
1
Independent System Operator Integration June 24, 2016 1 - - PowerPoint PPT Presentation
PacifiCorp Stakeholder Meeting on Regional Independent System Operator Integration June 24, 2016 1 Housekeeping matters Welcome Logistics and safety moment Introductions Agenda 2 Agenda Time Subject Presenter 10:00 10:10
1
2
3
Time Subject Presenter 10:00 – 10:10 Introduction/Safety/Overview Sarah Edmonds 10:10 – 10:20 Regional ISO Process and SB350 Studies Phil Pettingill 10:20 – 10:30 PacifiCorp Contracts and Framework for the day Sarah Edmonds 10:30 – 11:00 Terminology and Agreements PacifiCorp will continue to administer Deb Le Vine 11:00 – 11:30 Agreements transitioning to ISO tariff service Deb Le Vine 11:30 – 12:30 Lunch Break 12:30 – 1:30 Existing transmission contracts under ISO’s tariff Deb Le Vine 1:45 – 2:00 Break 2:00 – 2:45 Examples Deb Le Vine 2:45 – 3:00 Wrap-up and Next Steps Sarah Edmonds
4
5
6
The October 2015 study of integrating PacifiCorp and ISO systems results in
Savings in 2015$ Billions and incremental to EIM benefits
The study quantifies benefits in four areas:
Area Low High PacifiCorp $1.6B $2.3B ISO $1.8B $6.8B Combined Benefit: $3.4B $9.1B
7
Senate Bill 350 requires the California ISO to conduct studies to determine if
The California ISO will conduct stakeholder initiatives over the next two years
PacifiCorp will seek regulatory approvals from all six states where its serves
Full integration by combining the balancing authority areas into Regional ISO is
8
air pollutants
benefits to the California economyy
elsewhere
renewable energy resources 6
9
10
Contract data based on the PacifiCorp Q4 2015 EQR
11
12
Agreements PacifiCorp will continue to administer
Transitioning to ISO Service
Existing transmission contracts
13
14
15
Non-PTO Service Area
Transmission Interconnection Transmission Interconnection
16
Existing Contracts will continue to be honored for the duration of those
PacifiCorp is required to attempt to negotiate changes to Existing Contracts to
PacifiCorp is required to ensure that Existing Contracts do not pay twice for
17
18
19
20
specific transmission service
discussed further in Section 5.2 of the paper)
RTUs, relays, etc.)
negative generator and not subject to the firm load interconnection process of its PTOs
21
OATT transmission service agreements executed on or after July 9, 1996
New generator interconnection agreements
22
until an amendment is needed to the agreement
– The QF will execute a three party LGIA or SGIA that includes the ISO – The QF will execute a separate power purchase agreement for the energy sale
three party agreements
Generators
– SC would schedule gross generation and load so that if the generator trips the system is
aware of the load that it may need to carry
– In after-the-fact settlements, ISO will adjust the gross award based upon the non-market
resource and calculate the expected energy or “Net” value.
– ISO charges are assessed on the Net value – Ancillary services can be self-provided or procured from the market
23
The ISO’s “OATT” transmission service is governed by terms and conditions
A Scheduling Coordinator provides bids or self-schedules in the day-ahead
Bids can be for:
Self-schedules are balanced – generation/import with load/export
24
deliverability status
25
Generator interconnection agreement
Queue Management
26
Legacy Transmission service agreements (non-OATT) Operating agreements that include transmission service Storage and interchange agreements that include transmission service Wheeling and transfer agreements that provide transmission service Legacy transmission service and operating agreements Emergency service agreements Joint ownership transmission and operating agreements
27
28
29
30
31
32
procedures
holder
provisions of the Existing Contract
– contract reference numbers – timing of the instructions – day-ahead, hour-ahead, etc. – point(s) of receipt / Point(s) of delivery – capacity – curtailment implementation – pro rata, priority, etc. – forecasted annual usage patterns – self-provide ancillary services – other special considerations
33
delivery of Energy to and from the ISO Controlled Grid, and that provides regulated retail electric service to Eligible Customers, as well as regulated procurement service to those End-Use Customers who are not yet eligible for direct access, or who choose not to arrange services through another retailer
Agreement to allow the R-ISO to understand the customer’s system and provide a mechanism for operational coordination
utility, water district, irrigation district, state agency or federal power marketing authority subsumed within the ISO Balancing Authority Area
34
35
BAA1 BAA2
36
BAA4
Load3
37
BAA6
Load5
BAA7 BAA8
38
Gen Load
39
question on
the paper and presentations