! "#$%$ &'(&")
Understanding Key Contract Provisions Jenifer L. Kraemer - - PowerPoint PPT Presentation
Understanding Key Contract Provisions Jenifer L. Kraemer - - PowerPoint PPT Presentation
Understanding Key Contract Provisions Jenifer L. Kraemer
Key Contract Provisions
Schedule Change Orders Deadlines Indemnification Insurance Payment Deficiencies Termination Dispute Resolution Prohibited Terms in Wisconsin
Schedule
Delays and extensions of time
Circumstances justifying extensions of time are
usually quite limited
Owner-caused delays (such as failure to make decisions
promptly, delays by Owner’s own forces, etc.)
Unexpected or hidden conditions (e.g., soil, hazardous
materials, etc.)
Unusual weather conditions Delays in release of plan/bid packages Force majeure events (e.g., acts of God, fire, war, etc.)
Schedule
Subcontracts usually consistent with, or
incorporate, contract between General Contractor and Owner
Subcontractors should be aware of how/when
General Contractor can change subcontractor’s schedule
Subcontractors should be aware of what happens
when subcontractor is delayed by General Contractor or by other subcontractors
Pay attention to deadlines for claims
(discussed in following section)
Schedule
Remedies if behind schedule
Owner’s right to require General Contractor
(or General Contractor to require subcontractor) to work overtime, add labor, expedite deliveries or take other actions to catch up, at General Contractor’s (or subcontractor’s) cost.
Owner’s (or General Contractor’s) right to
take over all or part of the work.
Termination?
Schedule
Liquidated vs. consequential damages
Liquidated = a fixed amount for each day the project is
delayed beyond the completion date.
Consequential = an open ended amount of delays which
could be sought to recover damages that indirectly flowed from a breach of contract that caused a delay.
Standard AIA and ConsensusDocs contracts contain mutual
waiver of consequential damages.
Some contractors/sureties prefer liquidated because known $
- f risk.
Owners often want consequential damages in order to
potentially recover for losses due to delay in project completion.
Likely get passed along to subs if General Contractor agrees
to contract term.
Change Orders
Changed conditions
Site conditions Hazardous materials
Changes in plans or specifications Additional work added to scope Delays
Change Orders
Usually must be in writing, signed by both
parties, prior to work being performed
Risk in proceeding without signature
Try to minimize risk by documenting in some way:
E-mail confirming direction, notice of extra Meeting minutes, project log
General Contract and/or Subcontract may
have deadline for submission of change order requests
Deadlines
Need to carefully review contract
Shop drawings/submittals Requests for payment
Date for submittal/payment
Change order requests
Most often there is a deadline for when change
- rder must be requested after event occurs.
Be aware of any documentation requirements
that must be met.
Deadlines
Claims
Contract should specify deadline for claims for additional
time/money.
A201 Section 15.1.2 requires that general contractors’ claims
be initiated within 21 days after occurrence of the event giving rise to the claim or after the claimant first recognizes the condition giving rise to the claim, unless different deadline is specified.
A401 Section 5.3 requires that subcontractors’ claims be
made by the time specified by the contract, but no later than two (2) working days before the time the claim is due from the general contractor under the general contract (see above).
Statutes of limitations. May be waived if not raised in writing prior to submitting final
pay request.
Indemnification
What is it?
Requiring a party to reimburse the other
party under certain circumstances. Used to allocate risk to party most able to control it.
Often indemnity provisions hidden in
several places:
Broad indemnity Indemnity from liens, etc. Indemnity from hazardous materials
Indemnification
Look at:
When the indemnity obligation is triggered
Loss Claim by a third party Because of:
Anything related to the work Failure to perform in accordance with contract Specific limited circumstances (discovery of hazardous
materials, etc.)
Who is being indemnified
Often includes persons or entities other than the contracting
party.
Architect, general contractor, owner, other contractors/
subcontractors, etc.
Indemnification
Look at extent of obligations
Try to limit to own actions/omissions (or those of a
person or entity who you are responsible for)
“to the extent” – usually indicates a proportional
responsibility
Exceptions referring to the other party’s “sole
negligence” would seem to require you to cover even when the other party was partly at fault
Some states dictate whether/how much liability can
be shifted to another party
Insurance
Coverage
Review with agent to confirm you have
coverage for required events and amounts:
Contractual liability (i.e., indemnity terms) Additional insured provisions Mold
Proof of Insurance
Insurance
Waiver of subrogation
Subrogation is the ability to step into the insured’s
shoes and make a claim against a third party
Waiving it means an insurer who pays out a claim
may not have the right to seek reimbursement from the third party allegedly liable for the loss
Some insurers will refuse to waive
Consistency
Make sure contracts on one project are consistent
Payment
Timing of Payment
Contracts typically take one of two approaches:
Payment due within X days of General’s receipt of payment from
Owner
Provided pay application received by X date of a given month,
then payment due by end of following month
“Pay when paid” is a lawful provision
Retainage
Percentage of retainage varies, but 10% is typical on private
projects
Retainage typically not released until final payment and
acceptance of project by Owner
Subcontracts may require warranty information, O&M manuals,
- etc. to be submitted before retainage due to subs
Payment
Subcontractor typically has contract
- bligation to timely pay its
subcontractors and suppliers, even without payment from General
Could result in liens filed against project Subcontractors should consider flowing-
down payment provisions
Payment
General’s remedies:
Contract typically allows General to withhold
payment if subcontractor not paying its subs and suppliers
Declare subcontractor in default of contract Joint or direct payment agreement
Payment
Liens can have a critical impact on the project:
Owner/Lender will likely withhold payment on draw
request until lien is cleared up
Added costs to resolve
Statute requires general contractor to defend Owner in any
lien action that is not the result of Owner’s failure to pay
Subcontract will, in turn, typically require sub to indemnify
and defend general
Both general contracts and subcontracts also typically
require that liens be bonded-over (statutory procedure to follow)
Payment
Price Escalation Clauses
Allow adjustments to a contract price based on
certain specified events (e.g., labor or material costs rising beyond a specified amount)
Should clearly define the labor or materials in
question, specify when price adjustments are to be made, and clearly describe the process (including baseline, triggering threshold, method of adjustment, any upper cap, and notice and documentation requirements).
Deficiencies
Failure to perform as required
May include:
Deficiencies in the work or defects in materials
provided
Typically General and Architect/Owner have authority
to reject work
Failure to comply with the project schedule Refusal to timely complete punchlist work
Deficiencies
Contractual Notice and Cure
Requirements
Contracts/Subcontracts often require
advance written notice and right to cure
Make sure notice/cure timelines are realistic Make sure to follow required manner of
delivering notices (e.g., certified mail, etc.)
Timely respond, in writing, to any deficiency
notices
Deficiencies
Defects in the work of other contractors
Subcontracts often require inspection of other
contractor’s work where the subcontractor’s work depends on it
Report defects to General prior to performing work Failure to inspect and report defects may be deemed
acceptance of other contractor’s work
How broad is inspection obligation?
In part, depends on subcontract language Certainly applies to obvious defects
Termination
Typical rights granted to Owner/General
Contractor
Right to terminate for breach of contract,
acts of default
Right to terminate for convenience (though
typically requires payment for work already performed, plus contractor’s/subcontractor’s
- ther costs of termination)
Right to assume contracts, if crucial to
project
Termination
Notice
As discussed regarding deficiencies, the
contract/subcontract will usually require written notice of deficiency or intent to terminate, and a cure period
Abide by any requirements for notice recipients,
method of delivery, etc.
Promptly respond to any notices and/or cure
deficiencies
Remedies
If termination is for breach or act of default,
- wner/general contractor typically can correct
deficiencies and deduct the costs from the payments due the general/subcontractor
Termination
Typical rights granted to
general/subcontractor
Right to terminate for same reasons and
circumstances as owner (or in case of subcontractor, same as general contractor’s rights with owner)
General/Subcontractor typically may recover
payment for work performed and related costs, provided termination is for reasons not the fault
- f the contractor or its subs
Dispute Resolution
Arbitration vs. Litigation
Standard AIA documents used to require
arbitration under the Construction Industry Arbitration Rules of the American Arbitration Association
Beginning with the 2007 version of the AIA
documents, litigation is now the default method of dispute resolution, with the option to choose arbitration instead
Dispute Resolution
Arbitration vs. Litigation Considerations
Risk of multiple proceedings
Unless all parties to the dispute are bound to
arbitrate, you could end-up with multiple proceedings
Limits on discovery in arbitration
May be good; may be bad
In arbitration, filing fees can be significant
and you pay the “judge”
Dispute Resolution
Arbitration vs. Litigation Considerations
(continued)
Limited scope of review from unfavorable
arbitration award, but automatic right to appeal unfavorable court judgment
On the other hand, construction arbitrators
may have more experience dealing with construction issues than a judge may have
Dispute Resolution
Attorney’s Fees
Unless the contract provides for recovery of
attorney’s fees, each party pays their own
Contracts may start with a one-way
attorney’s fees recovery provision
Consider the risks of having to pay your own
and/or the other party’s attorney’s fees
Make attorney’s fees recovery reciprocal, if
possible
Prohibited Terms in Wisconsin
Prohibited Terms in Wisconsin (Sec.
779.135)
Lien waiver before payment
Cannot require a potential lien holder to waive its
lien rights or claim against a payment bond, unless the party has been fully paid
BUT, if you do so willingly, your lien rights are waived
Incorporating other state law
Cannot make the contract subject to the laws of
another state or require that dispute resolution
- ccur in another state
Prohibited Terms in Wisconsin
Contingent payment by general contractor to
subs/suppliers
Cannot make a general contractor’s contractual
- bligation to pay its subs/suppliers contingent on
the general contractor first receiving payment from a party with whom the subs/suppliers do not have a contract (“pay if paid”)
However, general contractors may have a provision
entitling them to delay payments to subs/suppliers until they have been paid (“pay when paid”)
! "#$%$ &'(&")