I-SEM Senior Stakeholder Forum 15 th February, 2018 Ballymascanlon - - PowerPoint PPT Presentation

i sem senior stakeholder forum 15 th february 2018
SMART_READER_LITE
LIVE PREVIEW

I-SEM Senior Stakeholder Forum 15 th February, 2018 Ballymascanlon - - PowerPoint PPT Presentation

I-SEM Senior Stakeholder Forum 15 th February, 2018 Ballymascanlon House Hotel Welcome 2 Agenda Welcome and introductory remarks Programme Update and Market Readiness (RAs) Programme Update and Market Readiness (TSOs) Market


slide-1
SLIDE 1

I-SEM Senior Stakeholder Forum 15th February, 2018

Ballymascanlon House Hotel

slide-2
SLIDE 2

Welcome

2

slide-3
SLIDE 3
  • Welcome and introductory remarks
  • Programme Update and Market Readiness (RAs)
  • Programme Update and Market Readiness (TSOs)
  • Market Participants Perspective (EAI)
  • Q & A Session
  • Close
  • Informal discussion over coffee

Agenda

slide-4
SLIDE 4
  • Capacity Market
  • State Aid approval of the Capacity Market

design

  • Completion of the T-1 Auction
  • Trading Arrangements
  • Day Ahead Market - Euphemia bid types

confirmed

  • Intra Day Auctions – Timing confirmed
  • Balancing Market – Balancing Market

Principles Code of Practice published

  • Licencing Framework
  • TSO / MO / Generation & Supply Licences
  • Market Trial
  • Entry to trial on schedule
  • In 9th week of trial
  • 4 weeks from Unscripted
  • 14 weeks from Go-Live

Progress since last meeting

slide-5
SLIDE 5

FTR Auction Delivery Timeline

slide-6
SLIDE 6
  • Market Trial
  • System and Processes continue to bed down and progress towards the unscripted

phase

  • ROI Generation and Supply Licence Appeal & Judicial Review
  • Not showstoppers – intention is to proceed towards go-live
  • Process is on-going
  • Impact of T-1 Auction Results
  • Outcomes have resulted in generation closure announcements and these are being

progressed

  • Planning of Future T-1 and T-4 Auctions
  • On-going with initial timetable to be published shortly

On-going activities

slide-7
SLIDE 7

Indicative Go Live Decision Process

Governance Framework Participant Assurance

 ISEM Steering Group will make recommendation  Go Live Decision made by SEMC  The SEMC will make an announcement approximately [two weeks] prior to Go Live

Market Trial Report

Indicative Go Live Decision Timeline

SEMC 26th April

Complete Market Trial & Readiness Activities

Formally Confirm Go Live ETA Go- Live D-x

Gate Opening

Cutover Preparation Confirm Intention to Go Live

TSO/MO/IC Assurance

slide-8
SLIDE 8
  • Readiness Issues / on-going readiness c
  • Internal system & process testing & trialling
  • Staff training
  • Commercial readiness
  • Detailed Cutover planning

8

Participant Assurance

 Participant Readiness will continue to be monitored via the TSO’s Market Readiness Assessment (MRA) process  Go Live Decision will be informed by the final MRA returns

  • We understand there remain significant readiness activities
  • Type 3 Interfaces
  • Market Systems stability
  • Defect resolution
  • Settlement validation
slide-9
SLIDE 9
  • Planning of Future T-1 and T-4 Auctions
  • On-going with initial timetable to be published shortly
  • RA oversight of the market
  • Market Monitoring
  • Modifications to the Trading and Settlement Code/Capacity Market Code
  • Compliance of TSO/MO with licence obligations – Audits, Reports
  • Directed Contracts
  • Systems Release Plan
  • Discussions underway with the TSOs on the release plan for Day 2 issues

Beyond Go-Live

The RAs are preparing for our “business as usual” activities: