I NDIA - S RI L ANKA U NDERSEA HVDC T RANSMISSION L INK - - PowerPoint PPT Presentation
I NDIA - S RI L ANKA U NDERSEA HVDC T RANSMISSION L INK - - PowerPoint PPT Presentation
P OLICY AND R EGULATORY F RAMEWORK AND E NHANCEMENT OF E LECTRICITY T RADING IN S OUTH A SIA Damitha Kumarasinghe Director General Public Utilities Commission of Sri Lanka 15 January 2016 S RI L ANKA E LECTRICITY I NDUSTRY S TRUCTURE GOSL /
SRI LANKA ELECTRICITY INDUSTRY STRUCTURE
2
LECO IPP Consumers
GOSL / Cabinet of Ministers
GOSL / Cabinet of Ministers Transmission CEB Generation Minister of Power and Energy Minister of Finance and Planning
Public Utilities Commission of Sri Lanka (Regulator) D1
D2 D3 D4
Corporate
SRI LANKA POWER SYSTEM
Generation Capacity (3,602 MW)
Large Hydro 1,361 MW CEB Thermal 1,103 MW IPP Thermal
771 MW
NCRE
367 MW (271 MW mini-hydro, 78 MW Wind)
Peak Demand
– 2,100 MW (excluding NCRE)
Sales
– 10,500 GWh
Consumers
– 5.5 Million
CEB Transmission System 220kV and 132 kV CEB does 85% of distribution, rest by LECO
3
PUBLIC UTILITIES COMMISSION OF SRI LANKA
PUCSL established under Act No. 35 of 2002 PUCSL empowered to regulate the electricity industry under
Sri Lanka Electricity Act, No. 20 of 2009
4
PUBLIC UTILITIES COMMISSION IN ELECTRICITY INDUSTRY
acts as Economic, Technical and Safety Regulator Advice Government on all matters related to the
Industry
Exercises Licensing, Inspecting, Standardizing, etc of
- f the Industry
Regulate Tariffs Efficiency promotion and information dissemination Has to ensure coordinated, efficient, economical
and uninterrupted supply at all times throughout Sri Lanka
5
LEGAL POSITION
GENERATION
License required and Government shareholding
required for plants above 25MW
Generator requirement need to be identified in LT
plan
Competitive Bidding
TRANSMISSION
License required; Ceylon Electricity Board (CEB)
by the Act.
DISTRIBUTION
License Required; four Licenses to CEB and one
for its subsidiary- LECO
Private companies can get License - require >50%
Gvt ownership
TRADING
A function of Transmission Licensee – single buyer
6
MARKET RISK
No (minimum) risk
Single buyer model Government Guaranteed contracts Minimum Dispatch Requirements Fuel supply risk with Government/ CEB
7
OPERATOR VIABILITY AND RIGHTS
Legally ensured Required to allow recovery of all reasonable costs of a
Licensee
Minimum fixed return on Investment as per PPA Stringent procedure to issue enforcement orders Revocation of License is difficult- Provide Certainty
Minister Concurrence Public Notice
8
AREAS TO IMPROVE IN RELATION TO CROSS BORDER TRADE
Open access would attract investment- but
require amendments to Law
Handling Trading and related dispatch in the
event of International Trading
Private parties that intend to invest in
Generation (>25 MW) will have to have a Government share, this might not be attractive
9
INDIA - SRI LANKA UNDERSEA HVDC TRANSMISSION LINK
Pre-feasibility done 2002 and 2006 Originally planned for 500 MW
upgradable to 1,000MW
Agreement signed to conduct a detailed
feasibility – collaboration with Power Grid India and Ceylon Electricity Board
10
Madurai-
Anuradhapura selected
285 km 50km undersea ±400kV USD 800 Mn
11
POWER TRADING THROUGH INDIA- SRI LANKA LINK
Opportunity
power deficits at various time intervals Large scale Transmission network developments in India Very attractive peak prices observed in the Indian Power Exchange Potential savings by spinning reserve reduction on both sides Few large Coal Power plants being built in the country- base load
may not be sufficient
One 250 MW x 2 coal plant proposed in the East coast in collaboration with NTPC, India
Large Renewable Energy potential in Northern part of the country All depends on Indian/ Sri Lankan policy
12
SRI LANKA ELECTRICITY LAW AND REGIONAL INTERCONNECTION
Open Access is not allowed All trading has to go through CEB- Transmission
Licensee (Single Buyer)
Any Generation procurement to be included in
Least Cost Long Term Generation Expansion Plan- Ensure least cost criteria
13
THANK YOU
14