1
I-290 Construction Approach
April 2016
I-290 Construction Approach April 2016 1 AGENDA Project Process - - PowerPoint PPT Presentation
I-290 Construction Approach April 2016 1 AGENDA Project Process - Phase I, II, & III Overall guiding principles I-290 construction approach I-290 construction schedule Construction mitigation Best Practices 2
1
April 2016
2
AGENDA
3
CONSTRUCTION CONSIDERATIONS BY PHASE
4
CONSTRUCTION CONSIDERATIONS BY PHASE
5
CONSTRUCTION CONSIDERATIONS BY PHASE (CON’T)
6
OVERALL CONSTRUCTION GUIDING PRINCIPLES
7
I-290 CONSTRUCTION APPROACH
8
ADVANCE WORK/IMPROVEMENTS
9
CONCEPTUAL CONSTRUCTION SCHEDULE
(as practical)
10 10
CONCEPTUAL CONSTRUCTION SCHEDULE
(as practical)
11 11
I-290 CONSTRUCTION STAGING
12 12
CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK
13 13
CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK
14 14
CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK
15 15
CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK
16 16
CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK
17 17
CONSTRUCTION SCHEDULE SUMMARY
18 18
CONSTRUCTION EFFECTS / MITIGATION CONCEPTS
Vibration/settlement Specifications – construction methods – monitoring Noise Specifications – restrictions as appropriate Dust Specifications – water trucks – demolition methods Traffic patterns Specifications – restrictions as appropriate – hotline Time of day Nighttime mainline work Specifications – restrictions as appropriate Materials storage Specifications – restrictions as appropriate
19 19
VIBRATION / SETTLEMENT
20 20
NOISE
21 21
DUST
22 22
BEST PRACTICES
23 23
BEST PRACTICES
24