i 290 construction approach
play

I-290 Construction Approach April 2016 1 AGENDA Project Process - PowerPoint PPT Presentation

I-290 Construction Approach April 2016 1 AGENDA Project Process - Phase I, II, & III Overall guiding principles I-290 construction approach I-290 construction schedule Construction mitigation Best Practices 2


  1. I-290 Construction Approach April 2016 1

  2. AGENDA  Project Process - Phase I, II, & III  Overall guiding principles  I-290 construction approach  I-290 construction schedule  Construction mitigation  Best Practices 2

  3. CONSTRUCTION CONSIDERATIONS BY PHASE  Phase I – Planning – Basic constructability and construction sequence – Right of way and traffic management – Letter of Intent  Conceptual outline of commitments & costs 3

  4. CONSTRUCTION CONSIDERATIONS BY PHASE  Phase II – Design – Geotechnical/soils surveys (used to refine structural design and identify any special circumstances) – Detailed engineering plans  Detailed construction staging plan  Specifications – project community context  Refine cost estimates – Intergovernmental agreements  Details and refined costs 4

  5. CONSTRUCTION CONSIDERATIONS BY PHASE (CON’T)  Phase III - Construction – Implement project plans and specifications – Adjust to field conditions as appropriate – Communicate status and coordinate construction activities with communities 5

  6. OVERALL CONSTRUCTION GUIDING PRINCIPLES  Provide safe & efficient work zones during construction  Minimize adverse effects to the traveling public: – Pedestrian, transit, bicycle, and auto  Implement strategies to minimize community disruptions  Inform surrounding communities and affected users of impacts & available travel options 6

  7. I-290 CONSTRUCTION APPROACH  Early improvements prior to mainline construction – Off system roadway improvements:  Offers additional travel options  Local community benefits 7

  8. ADVANCE WORK/IMPROVEMENTS  Advanced work – I-55 Express Toll Lane (I-355 to I-90/94) – Off-System Arterial Improvements 8

  9. CONCEPTUAL CONSTRUCTION SCHEDULE  8 year construction schedule estimate (Phase III) – 4 years advance work – 4 years mainline construction  Local cross-road & pedestrian bridges  Expressway (some periods of 4 lane (as practical) operation)  Major interchanges  CTA, CSX, IHB railroad bridges  Mainline drainage  Utilities & retaining walls (as practical)  Retaining walls & noise walls 9

  10. CONCEPTUAL CONSTRUCTION SCHEDULE  8 year construction schedule estimate (Phase III) – 4 years advance work – 4 years mainline construction  Local cross-road & pedestrian bridges  Expressway (some periods of 4 lane (as practical) operation)  Major interchanges  CTA, CSX, IHB railroad bridges  Mainline drainage  Utilities & retaining walls (as practical)  Retaining walls & noise walls 10 10

  11. I-290 CONSTRUCTION STAGING  Implement construction staging to minimize disruptions – Advance local improvement projects prior to mainline – Minimize duration of mainline construction (4 years) – Minimize duration & extent of mainline lane closures – Avoid closing two consecutive interchange/access points  25 th Avenue & 1 st Avenue  Harlem Avenue and Austin Boulevard  Central Avenue and Lamarie/Cicero Avenue – Avoid full closure of two consecutive cross roads – Maintain one entrance to each Blue Line platform 11 11

  12. CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK Advance Work: Year 1 & 2 12 12

  13. CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK Advance Work: Year 2 & 3 13 13

  14. CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK Advance Work: Year 3 & 4 14 14

  15. CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK Mainline Work: Year 4 & 5 15 15

  16. CONCEPTUAL CONSTRUCTION SCHEDULE OAK PARK Mainline Work: Year 6 thru END 16 16

  17. CONSTRUCTION SCHEDULE SUMMARY  8 Year Construction Schedule – 4 years for advance work/improvements – 4 years for mainline construction  Key Schedule Drivers – IHB Railroad, CTA, and CSX Railroad bridges – Utility relocations 17 17

  18. CONSTRUCTION EFFECTS / MITIGATION CONCEPTS Effect General mitigation strategy Specifications – construction methods Vibration/settlement – monitoring Noise Specifications – restrictions as appropriate Specifications – water trucks Dust – demolition methods Specifications – restrictions as appropriate Traffic patterns – hotline Time of day Specifications – restrictions as appropriate Nighttime mainline work Materials storage Specifications – restrictions as appropriate  Overall project balance  Community, safety, cost, schedule 18 18

  19. VIBRATION / SETTLEMENT  Vibration/settlement specifications – No driven shafts allowed  Monitoring – Identified locations and predefined threshold values – Monitoring of locations during construction – Corrective action and equipment shutdowns in areas if thresholds are exceeded 19 19

  20. NOISE  Construction noise – Type of work – Day or night – Contractor means and methods – Balance 20 20

  21. DUST  Contracts include pay item for dust control  Reduced vehicle speed on unpaved surfaces  Cover haul vehicles  Erosion control measures 21 21

  22. BEST PRACTICES  Detailed analysis & Coordination (design – phase II) – Sequence of work in each community – Likely construction effects and mitigation strategies – Local traffic patterns – Construction phase coordination/communication plan 22 22

  23. BEST PRACTICES  Communication (construction – phase III) – Local point of contact – Full time IDOT contact – Weekly contractor meetings (work to date, upcoming work) – Project hotline – Website – Flyers and signage 23 23

  24. Discussion 24

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend