san francisco roadway bridges project
play

San Francisco Roadway Bridges Project Dogpatch Neighborhood - PowerPoint PPT Presentation

San Francisco Roadway Bridges Project Dogpatch Neighborhood Association Tuesday, May 13, 2014 Overview Scope & Need Construction Timeline & Sequence Construction Impacts Project Elements Next Steps 2


  1. San Francisco Roadway Bridges Project Dogpatch Neighborhood Association Tuesday, May 13, 2014

  2. Overview • Scope & Need • Construction Timeline & Sequence • Construction Impacts • Project Elements • Next Steps 2

  3. Scope & Need

  4. Project Scope • Remove and replace three existing vehicular/pedestrian bridges over the Caltrain tracks at the following locations: 22 nd Street - 23 rd Street - - Paul Avenue 4

  5. Project Area Replace Three Vehicular/Pedestrian Bridges 5

  6. Background Why do these bridges need to be replaced? • Rapidly aging vehicular/pedestrian bridges • Bridges deemed structurally deficient; do not meet existing seismic safety standards • Must be replaced for the safety of community members and Caltrain customers 6

  7. The E’s of Rail Safety • EDUCATION • ENGINEERING Jerrold Street Bridge - 2011 7

  8. Background • Project cost: $20 million • Paid for by Federal Highway Administration and local funding • Owned by the City of San Francisco • Maintained by Caltrain 8

  9. Construction Timeline & Sequence

  10. Construction Timeline • Schedule – Construction set to begin in Fall 2014 and last until Fall 2016 – Work is expected to last 9 to 12 months per bridge – Work not concurrent 10

  11. Construction Sequence 23 rd Street 22 nd Street Fall 2014-15 Fall 2015-16 11

  12. Construction Sequence Paul Avenue Fall 2014-15 12

  13. Construction Impacts

  14. Construction Impacts • Majority of work done during day • Some night and weekend work required during certain construction activities • Localized noise impacts • Notification process – Mailers sent 14 days before starting construction, loud operations and/or night work – Notices are mailed to residents and businesses located up to a ½ mile from the project site 14

  15. Construction Impacts • Vehicular and pedestrian restrictions will be required and posted at each bridge • During closures at 22 nd and 23 rd streets, detours and shuttle in place during peak AM/PM hours • During closure on Paul Avenue, detours • MUNI coordination 15

  16. Project Elements

  17. Project Elements • Retrofit existing abutments to support new structures • Utility relocations • Temporary street closures • Demolition/construction • Paving and street improvements 17

  18. Next Steps

  19. Community Outreach • Community meetings – Feb. 25 & 27, 2014 - Visitacion Valley Library and Potrero Hill Neighborhood House • Community Based Organizations • Neighborhood Groups • Local Developers • Notification Process - Notices/mailers (residents, businesses, community based organizations) - Special project Web page www.caltrain.com/SFRB, with subscribe option - Social media (Facebook & Twitter) - Responses to individual public requests and questions - News releases 19

  20. Next Steps • Advertise and award of construction contract - June 2014 to September 2014 • Continue communications and dialogue with residents and businesses regarding project • Next community meeting to be held prior to construction (Late Fall 2014) 20

  21. More Info • www.caltrain.com/SFRB - Subscribe to updates • Email: sfrb@samtrans.com • Construction Outreach Hotline: 650.508.7726 21

  22. Questions ?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend