San Francisco Roadway Bridges Project Dogpatch Neighborhood Association Tuesday, May 13, 2014 Overview Scope & Need Construction Timeline & Sequence Construction Impacts Project Elements Next Steps 2


slide-1
SLIDE 1

San Francisco Roadway Bridges Project

Dogpatch Neighborhood Association Tuesday, May 13, 2014

slide-2
SLIDE 2

Overview

  • Scope & Need
  • Construction Timeline & Sequence
  • Construction Impacts
  • Project Elements
  • Next Steps

2

slide-3
SLIDE 3

Scope & Need

slide-4
SLIDE 4

Project Scope

  • Remove and replace three existing

vehicular/pedestrian bridges over the Caltrain tracks at the following locations:

  • 22nd Street
  • 23rd Street
  • Paul Avenue

4

slide-5
SLIDE 5

Project Area

5

Replace Three Vehicular/Pedestrian Bridges

slide-6
SLIDE 6

Background

Why do these bridges need to be replaced?

  • Rapidly aging vehicular/pedestrian bridges
  • Bridges deemed structurally deficient; do not meet

existing seismic safety standards

  • Must be replaced for the safety of community

members and Caltrain customers

6

slide-7
SLIDE 7

The E’s of Rail Safety

  • EDUCATION
  • ENGINEERING

7

Jerrold Street Bridge - 2011

slide-8
SLIDE 8

Background

  • Project cost: $20 million
  • Paid for by Federal Highway Administration

and local funding

  • Owned by the City of San Francisco
  • Maintained by Caltrain

8

slide-9
SLIDE 9

Construction Timeline & Sequence

slide-10
SLIDE 10

Construction Timeline

  • Schedule

– Construction set to begin in Fall 2014 and last until Fall 2016 – Work is expected to last 9 to 12 months per bridge – Work not concurrent

10

slide-11
SLIDE 11

Construction Sequence

23rd Street 22nd Street

11

Fall 2015-16 Fall 2014-15

slide-12
SLIDE 12

Construction Sequence

12

Paul Avenue

Fall 2014-15

slide-13
SLIDE 13

Construction Impacts

slide-14
SLIDE 14

Construction Impacts

  • Majority of work done during day
  • Some night and weekend work required during

certain construction activities

  • Localized noise impacts
  • Notification process

– Mailers sent 14 days before starting construction, loud operations and/or night work – Notices are mailed to residents and businesses located up to a ½ mile from the project site

14

slide-15
SLIDE 15

Construction Impacts

  • Vehicular and pedestrian restrictions will be

required and posted at each bridge

  • During closures at 22nd and 23rd streets,

detours and shuttle in place during peak AM/PM hours

  • During closure on Paul Avenue, detours
  • MUNI coordination

15

slide-16
SLIDE 16

Project Elements

slide-17
SLIDE 17

Project Elements

  • Retrofit existing abutments to support new

structures

  • Utility relocations
  • Temporary street closures
  • Demolition/construction
  • Paving and street improvements

17

slide-18
SLIDE 18

Next Steps

slide-19
SLIDE 19

Community Outreach

  • Community meetings – Feb. 25 & 27, 2014
  • Visitacion Valley Library and Potrero Hill Neighborhood House
  • Community Based Organizations
  • Neighborhood Groups
  • Local Developers
  • Notification Process
  • Notices/mailers (residents, businesses, community based
  • rganizations)
  • Special project Web page www.caltrain.com/SFRB, with

subscribe option

  • Social media (Facebook & Twitter)
  • Responses to individual public requests and questions
  • News releases

19

slide-20
SLIDE 20

Next Steps

  • Advertise and award of construction contract
  • June 2014 to September 2014
  • Continue communications and dialogue with

residents and businesses regarding project

  • Next community meeting to be held prior to

construction (Late Fall 2014)

20

slide-21
SLIDE 21

More Info

  • www.caltrain.com/SFRB
  • Subscribe to updates
  • Email: sfrb@samtrans.com
  • Construction Outreach Hotline: 650.508.7726

21