I-10 from SH 46 to FM 3351 (Ralph Fair Road) Public Hearing - PowerPoint PPT Presentation

I-10 from SH 46 to FM 3351 (Ralph Fair Road) Public Hearing October 2, 2019 I-10 Public Hearing October 2, 2019 INTRODUCTIONS Elected Officials TxDOT Project Team Members Oct. 2, 2019 Open House: 5:00 p.m. 6:00 p.m. Public


  1. I-10 from SH 46 to FM 3351 (Ralph Fair Road) Public Hearing October 2, 2019 I-10 Public Hearing October 2, 2019

  2. INTRODUCTIONS  Elected Officials  TxDOT  Project Team Members Oct. 2, 2019 Open House: 5:00 p.m. – 6:00 p.m. Public Hearing: 6:00 p.m. Boerne Middle School South 10 Cascade Cavern Boerne, TX 78015 October 2, 2019 I-10 Public Hearing 2

  3. PUBLIC HEARING PURPOSE AND FORMAT  Purpose of the Public Hearing – To share proposed improvements – To gather comments and feedback from the community Public Hearing Format:  Sign up to speak  Provide your name, address, and organization (if applicable)  Limit your comment to three minutes  Time cannot be shared with other commenters October 2, 2019 I-10 Public Hearing 3

  4. PUBLIC COMMENT OPPORTUNITIES 1. Provide a verbal comment during the hearing 2. Complete a written comment card tonight 3. Email comments to: info@I10from46-3351.com 4. Mail comments to: I-10 from SH 46 to FM 3351 c/o HDR Engineering, Inc. Attn: Communications Manager 613 NW Loop 410, Suite 700 San Antonio, TX 78216 Deadline for Comments:  Written comments must be received on or postmarked by October 17, 2019 to be part of the official hearing record October 2, 2019 I-10 Public Hearing 4

  5. VERBAL COMMENTS Verbal Comment Process:  If you would like to make a verbal comment, please take a moment to fill out a speaker card  Speaker registration cards are available at the sign-in table October 2, 2019 I-10 Public Hearing 5

  6. PROPOSED PROJECT LIMITS PROJECT LIMIT: SH 46 PROJECT LIMIT: FM 3351 (Ralph Fair Road) October 2, 2019 I-10 Public Hearing 6

  7. TRAFFIC PROJECTIONS  2013-2017 AADT traffic volumes from TxDOT Count Map (I-10 mainlanes and frontage road AADT, north of FM 3351)  2024-2054 traffic volumes based on linear projections October 2, 2019 I-10 Public Hearing 7

  8. TYPICAL SECTIONS EXISTING 2 Mainlanes 2 Frontage Road Lanes (each direction) PROPOSED 3 Mainlanes Plus 1 HOV 2 Frontage Road Lanes (each direction) October 2, 2019 I-10 Public Hearing 9

  9. HIGH OCCUPANCY VEHICLE (HOV) LANES  What is an HOV lane? – An HOV lane, or carpool lane, is a special lane reserved for: • Carpools • Vanpools • Buses HOV Lane Benefits: • Motorcycles  Reduction in Congestion • Emergency response vehicles  Increase in Ridership/ Vanpools/Mass Transit Service – These special lanes enable those  Moving More People who carpool or ride the bus to  Improvement to Safety bypass traffic in the adjacent,  Establishment of Corridor unrestricted general purpose lanes. Lanes are identified as "2+" or "3+" Reliability  Long-Term Mobility Choice which refers to the minimum number of occupants to qualify. October 2, 2019 I-10 Public Hearing 9

  10. ENVIRONMENTAL CONSIDERATIONS Evaluated Potential Impacts: • Community • Edwards Aquifer No displacements; Portion of project in minimal changes in travel Bexar County lies over patterns and access the Contributing and Recharge Zones and • Biological would require an No impacts to threatened Edwards Aquifer or endangered species Protection Plan; water • Waters treatment controls would Impacts to two waters of be in place to meet Texas the United States Army Commission on Corps of Engineers Environmental Quality (USACE) (TCEQ) standards; no impacts anticipated October 2, 2019 I-10 Public Hearing 10

  11. ENVIRONMENTAL CONSIDERATIONS Evaluated Potential Impacts: Historic – no impacts to historic resources anticipated • Archeological – previously disturbed; low potential for impacts • Noise – 14 receivers impacted; abatement measures • examined but not found to be feasible and reasonable; no abatement is proposed Additional Considerations  Acquisition of additional right-of-way is not anticipated Envir ironme mental al d docume mentat ation i is a availab able f for revie iew October 2, 2019 I-10 Public Hearing 11

  12. PROJECT DEVELOPMENT SCHEDULE & NEXT STEPS WE ARE HERE Develop Anticipated Alternative Schematic Schematic and Public Hearing Environmental Analysis Approval Environmental October 2019 Approval May 2018 Spring 2020 November 2018 Fall 2019  This timeline is preliminary and subject to change October 2, 2019 I-10 Public Hearing 12

  13. PROJECT FUNDING Projected Construction Schedule Approximate  Begin construction date has not Construction Cost: been established  Project is currently unfunded $200 million October 2, 2019 I-10 Public Hearing 13

  14. VERBAL COMMENTS Speaker Comment Guidelines:  Submit speaker registration card  Speaking time limited to 3 minutes  Use microphone and face court reporter  State your name and whom you represent 3 (if applicable)  Unused time may not be given to another speaker 1 2  Questions will not be answered at this time, but will be documented October 2, 2019 I-10 Public Hearing 14

  15. VERBAL COMMENTS 3 minutes per speaker October 2, 2019 I-10 Public Hearing 15

  16. PUBLIC COMMENT OPPORTUNITIES 1. Complete a written comment card tonight 2. Email comments to: info@I10from46-3351.com 3. Mail comments to: I-10 from SH 46 to FM 3351 c/o HDR Engineering, Inc. Attn: Communications Manager 613 NW Loop 410, Suite 700 San Antonio, TX 78216 Deadline for Comments:  Written comments must be received on or postmarked by October 17, 2019 to be part of the official hearing record October 2, 2019 I-10 Public Hearing 15

  17. CLOSING REMARKS Thank hank you for r your r par artici cipat ation! October 2, 2019 I-10 Public Hearing 16

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.