How Much Risk Is Too Much Risk? Boston SPIN January 20 th 2004 Tim - - PowerPoint PPT Presentation

how much risk is too much risk
SMART_READER_LITE
LIVE PREVIEW

How Much Risk Is Too Much Risk? Boston SPIN January 20 th 2004 Tim - - PowerPoint PPT Presentation

How Much Risk Is Too Much Risk? Boston SPIN January 20 th 2004 Tim Lister lister@acm.org The Atlantic Systems Guild, Inc. WHATS IT ALL ABOUT, ALFIE? WHATS IT ALL ABOUT, ALFIE? WHATS IT ALL ABOUT, ALFIE? WHATS IT ALL ABOUT, ALFIE?


slide-1
SLIDE 1

How Much Risk Is Too Much Risk?

Boston SPIN January 20th 2004 Tim Lister lister@acm.org The Atlantic Systems Guild, Inc.

slide-2
SLIDE 2

“The purpose of risk management is to make decisions, not to sit around and admire the risks.”

– Rockwell Collins Risk Management Guide

WHAT’S IT ALL ABOUT, ALFIE? WHAT’S IT ALL ABOUT, ALFIE? WHAT’S IT ALL ABOUT, ALFIE? WHAT’S IT ALL ABOUT, ALFIE? WHAT’S IT ALL ABOUT, ALFIE?

slide-3
SLIDE 3

“BUT WE CAN’T POSSIBLY MAKE “BUT WE CAN’T POSSIBLY MAKE “BUT WE CAN’T POSSIBLY MAKE “BUT WE CAN’T POSSIBLY MAKE “BUT WE CAN’T POSSIBLY MAKE THESE DECISIONS . . .” THESE DECISIONS . . .” THESE DECISIONS . . .” THESE DECISIONS . . .” THESE DECISIONS . . .”

“The winning general is the one who can best act on imperfect information and half formed theories.” – Napoleon Bonaparte

slide-4
SLIDE 4
  • 4. RISK MANAGEMENT:
  • 4. RISK MANAGEMENT:
  • 4. RISK MANAGEMENT:
  • 4. RISK MANAGEMENT:
  • 4. RISK MANAGEMENT:

WORLD’S SHORTEST TUTORIAL WORLD’S SHORTEST TUTORIAL WORLD’S SHORTEST TUTORIAL WORLD’S SHORTEST TUTORIAL WORLD’S SHORTEST TUTORIAL

Avoiding the obvious Explicitly declared uncertainty Tools of risk management Risk and value A test: Did we really do risk management?

slide-5
SLIDE 5

You’re blind-sided by a risk that’s happened a thousand times before. You have no infrastructure in place to deal with a risk when it materializes. You don’t have a useful (early) transition indicator.

RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES

slide-6
SLIDE 6

DENVER INTERNATIONAL AIRPORT DENVER INTERNATIONAL AIRPORT DENVER INTERNATIONAL AIRPORT DENVER INTERNATIONAL AIRPORT DENVER INTERNATIONAL AIRPORT

The automated baggage handling system:

slide-7
SLIDE 7
slide-8
SLIDE 8
slide-9
SLIDE 9

D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH

Baggage Handling Software . . Integration testing . Acceptance & signoff Airport opening 1993 1994 1995

slide-10
SLIDE 10

D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH

Baggage Handling Software . . Integration testing . Acceptance & signoff Airport opening 1993 1994 1995

slide-11
SLIDE 11

D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH

Baggage Handling Software . . Integration testing . Acceptance & signoff Airport opening 1993 1994 1995

slide-12
SLIDE 12

D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH D.I.A. PROJECT: CRITICAL PATH

Baggage Handling Software . . Integration testing . Acceptance & signoff Airport opening 1993 1994 1995

slide-13
SLIDE 13
slide-14
SLIDE 14

You’re blind-sided by a risk that’s happened a thousand times before. You have no infrastructure in place to deal with a risk when it materializes. You don’t have a useful (early) transition indicator.

RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES RISK MANAGEMENT ATROCITIES

slide-15
SLIDE 15
slide-16
SLIDE 16

NOW AVAILABLE NOW AVAILABLE NOW AVAILABLE NOW AVAILABLE NOW AVAILABLE FROM HANSER: FROM HANSER: FROM HANSER: FROM HANSER: FROM HANSER:

www.hanser.de/computer/neu.htm

slide-17
SLIDE 17
slide-18
SLIDE 18
slide-19
SLIDE 19

1. You have zero chance of delivering before January of next year.

  • 2. My best guess is you’ll be

done around April 1st . . .

  • 3. but to be at least 50% sure,

you’d better advertise a date

  • f May 1 or later.
  • 4. To be 100% safe, you’d have to

allow for delivery as late as end of next year.

slide-20
SLIDE 20
slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23

RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM:

A risk diagram shows explicitly how uncertain we are about delivery date (or anything else).

slide-24
SLIDE 24

RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM:

A risk diagram shows explicitly how uncertain we are about delivery date (or anything else).

RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM:

slide-25
SLIDE 25

RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM:

A risk diagram shows explicitly how uncertain we are about delivery date (or anything else).

RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM:

slide-26
SLIDE 26

RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM:

A risk diagram shows explicitly how uncertain we are about delivery date (or anything else).

RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM: RISK DIAGRAM:

slide-27
SLIDE 27

RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE:

Risk Modeling Process Sources of Uncertainty Resultant Uncertainty

Delivery Date Size Inflation Productivity Variation etc. Flaw in size estimate

slide-28
SLIDE 28

RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE:

Risk Modeling Process Sources of Uncertainty Resultant Uncertainty

Delivery Date Size Inflation Productivity Variation etc. Flaw in size estimate

slide-29
SLIDE 29

RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE: RISK DIAGRAMS IN USE:

Risk Modeling Process Sources of Uncertainty Resultant Uncertainty

Delivery Date Size Inflation Productivity Variation etc. Flaw in size estimate

slide-30
SLIDE 30

SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT:

Effort Size in (for example) Function Points

slide-31
SLIDE 31

SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT:

Effort Size in (for example) Function Points

20,000 FP

slide-32
SLIDE 32

SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT:

Effort Size in (for example) Function Points

20,000 FP 52 person months

slide-33
SLIDE 33

SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT:

Effort Size in (for example) Function Points

20,000 FP 52 person months

“The project will require 52 person-months of effort.”

slide-34
SLIDE 34

SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT: SENSIBLE PROJECT MANAGEMENT:

Effort Size in (for example) Function Points

20,000 FP 52 person months

slide-35
SLIDE 35

SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT:

Effort Size in (for example) Function Points

20,000 FP 52 person months

slide-36
SLIDE 36

SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT:

Delivery Date 6/2000 11/2000 9/2000 Effort 40 52 70 (Person Months)

“The project will take this much effort.”

slide-37
SLIDE 37

40 52 70 Effort (Person Months)

SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT: SENSIBLE RISK MANAGEMENT:

Delivery Date 6/2000 11/2000 9/2000

“The project will take this much time.”

slide-38
SLIDE 38
slide-39
SLIDE 39

How much risk is too much risk?

slide-40
SLIDE 40

INSIGHTS: INSIGHTS: INSIGHTS: INSIGHTS: INSIGHTS:

surprise about where the major risks lie surprise about the value of low risk projects surprise about risk quantification surprise about precision surprise about aggressively scheduled projects

slide-41
SLIDE 41

WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK?

slide-42
SLIDE 42

WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK?

slide-43
SLIDE 43

WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK? WHERE IS THE BIGGEST RISK?

slide-44
SLIDE 44

THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE:

The biggest risk an organization faces is lost opportunity, the failure to choose the right projects.

slide-45
SLIDE 45

THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE:

The biggest risk an organization faces is lost opportunity, the failure to choose the right projects. So . . . Value is every bit as important as cost (the plusses matter as much as the minuses).

slide-46
SLIDE 46

THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE: THE FIRST SURPRISE:

The biggest risk an organization faces is lost opportunity, the failure to choose the right projects. So . . . Value is every bit as important as cost (the plusses matter as much as the minuses). Your process for deciding which projects to do is more important than your process for how to do them.

slide-47
SLIDE 47

THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION:

slide-48
SLIDE 48

. . . so we think we can have this for you in seven months . . .

THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION:

slide-49
SLIDE 49

. . . so we think we can have this for you in seven months . . .

THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION: THE KEY PROJECT NEGOTIATION:

If we really told him what we think (15-20 months), he’d never do the project.

slide-50
SLIDE 50

THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE:

The real reason we need to do risk management is not so much to survive our risks, but to enable risk-taking.

slide-51
SLIDE 51

THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE:

The real reason we need to do risk management is not so much to survive our risks, but to enable risk-taking. Conversely: A failure to manage risks ensures that no one will take any but the most minor risks.

slide-52
SLIDE 52

THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE: THE SECOND SURPRISE:

The real reason we need to do risk management is not so much to survive our risks, but to enable risk-taking. Conversely: A failure to manage risks ensures that no one will take any but the most minor risks. Without credible risk management, it is impossible to pursue meaningful value.

slide-53
SLIDE 53

THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE:

The only reason to quantify cost (schedule and budget) is to have something to compare to your quantification of benefit.

slide-54
SLIDE 54

THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE:

The only reason to quantify cost (schedule and budget) is to have something to compare to your quantification of benefit. A failure to quantify benefit assures that: there is perfect one-way accountability; the project team is accountable but the client is completely unaccountable.

slide-55
SLIDE 55

THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE: THE THIRD SURPRISE:

The only reason to quantify cost (schedule and budget) is to have something to compare to your quantification of benefit. A failure to quantify benefit assures that: there is perfect one-way accountability; the project team is accountable but the client is completely unaccountable. there is no way to assure that the high value projects get done (prioritization is a charade).

slide-56
SLIDE 56

THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE:

There is no sense making cost quantification more precise than value quantification.

slide-57
SLIDE 57

THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE:

There is no sense making cost quantification more precise than value quantification. So if all the user is willing to say about benefit is: “We gotta have it!”

slide-58
SLIDE 58

THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE: THE FOURTH SURPRISE:

There is no sense making cost quantification more precise than value quantification. So if all the user is willing to say about benefit is: “We gotta have it!” then it’s perfectly reasonable to quantify budget and schedule only to this extent: “It’s gonna cost a lot,” and “It will be done when it’s done.”

slide-59
SLIDE 59
slide-60
SLIDE 60

I’m sorry, Tom, but I simply cannot tolerate delivery any later than December 31, 2003.

slide-61
SLIDE 61

I’m sorry, Tom, but I simply cannot tolerate delivery any later than December 31, 2003. If I limit them to this year they can’t possibly spend more than I’m willing to pay.

slide-62
SLIDE 62

THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE:

An aggressive delivery date is often driven by a cost containment motive, not an urgent date motive.

slide-63
SLIDE 63

THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE:

An aggressive delivery date is often driven by a cost containment motive, not an urgent date motive. The more aggressive the schedule, the more likely it is that the product is of low value.

slide-64
SLIDE 64

THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE: THE FIFTH SURPRISE:

An aggressive delivery date is often driven by a cost containment motive, not an urgent date motive. The more aggressive the schedule, the more likely it is that the product is of low value. An inescapable corollary: Starting a project late is a worse sin than finishing it late.

slide-65
SLIDE 65

INSIGHTS: INSIGHTS: INSIGHTS: INSIGHTS: INSIGHTS:

surprise about where the major risks lie surprise about the value of low risk projects surprise about risk quantification surprise about precision surprise about aggressively scheduled projects

slide-66
SLIDE 66

I think we’re doing risk management. Um . . . we are, aren’t we?

slide-67
SLIDE 67

THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST

(in six parts):

slide-68
SLIDE 68

1. Is there a census of risks with at least 10-20 risks on it?

THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST

(in six parts):

slide-69
SLIDE 69

1. Is there a census of risks with at least 10-20 risks on it?

  • 2. Is each risk quantified as to probability and cost and

schedule impact?

THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST

(in six parts):

slide-70
SLIDE 70

1. Is there a census of risks with at least 10-20 risks on it?

  • 2. Is each risk quantified as to probability and cost and

schedule impact?

  • 3. Is there at least one early transition indicator associated

with each risk?

THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST MANAGEMENT” TEST

(in six parts):

slide-71
SLIDE 71

THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED)

  • 4. Does the census include the core risks indicated by

past industry experience?

slide-72
SLIDE 72

THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED)

  • 4. Does the census include the core risks indicated by

past industry experience?

  • 5. Are risk diagrams used widely to specify both the

causal risks as well as the net result (schedule and cost) risks?

slide-73
SLIDE 73

THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK THE “ARE WE REALLY DOING RISK MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED) MANAGEMENT” TEST (CONTINUED)

  • 4. Does the census include the core risks indicated by

past industry experience?

  • 5. Are risk diagrams used widely to specify both the

causal risks as well as the net result (schedule and cost) risks?

  • 6. Is the scheduled delivery date significantly different

from the best-case scenario?

slide-74
SLIDE 74