How Does MnDOT Select Projects?
Project Selection Policy Public Advisory Committee DATE TBD
How Does MnDOT Select Projects? Project Selection Policy Public - - PowerPoint PPT Presentation
How Does MnDOT Select Projects? Project Selection Policy Public Advisory Committee DATE TBD Many have tried 9/7/2017 2 Weve tried long explanations Weve tried elevator speeches How MnDOT Selects Projects in Less Than 100
Project Selection Policy Public Advisory Committee DATE TBD
9/7/2017 2
How MnDOT Selects Projects in Less Than 100 words Transportation investments should improve the quality of life and support economic development. To meet Minnesota’s goals, MnDOT evaluates physical factors like smoothness for pavement or state-of-good-repair for bridges combined with qualitative factors like Minnesota’s quality of life or economic development potential. There are never enough resources to meet every worthy goal completely. So with the aid of citizen and transportation partner input, MnDOT chooses a mix
expansion, enhancements, local needs, legal obligations, and public opinion. Learn more in the Minnesota State Highway Investment Plan.
9/7/2017 8
http://www.auditor.leg.state.mn.us/ped/pedrep/mndotprojects.pdf
9/7/2017 9
9/7/2017 10
11
9/7/2017 12
https://www.revisor.mn.gov/laws/?year=2017&type=1&doctype=Chapter&id=3
9/7/2017 13
https://www.revisor.mn.gov/laws/?year=2017&type=1&doctype=Chapter&id=3
9/7/2017 14
https://www.revisor.mn.gov/laws/?year=2017&type=1&doctype=Chapter&id=3
9/7/2017 15
9/7/2017 16
9/7/2017 17
9/7/2017 18
9/7/2017 19
20
9/7/2017 21
9/7/2017 Optional Tagline Goes Here | mndot.gov/ 22
9/7/2017 Optional Tagline Goes Here | mndot.gov/ 23
Project Name Location CIMS Request % Non- MnDOT Pts B/C Ratio Pts Local Econ System Multimodal Health Context Total Score Mainstreet TH 61 Downtown Improvements Red Wing 2,445,000 $ 34% 5.9 10.7 60.0 90.9 Multimodal for TH 23 w/o Bridge Duluth 3,035,000 $ 10% 0.0 15.0 60.0 90.0 TH 10/TH 75 Safety/Operational Improvements Moorhead 3,404,000 $ 31% 5.5 10.7 60.0 89.5 TH 25-CSAH 75 Intersection Improvements Monticello 506,000 $ 84% 9.7 25.0 60.0 85.9 US 52-CSAH 9 Interchange Goodhue County 250,000 $ 20% 4.0 19.8 60.0 83.3 TH 23 J-Turn & Ped Overpass Marshall 4,500,170 $ 21% 4.1 4.2 49.5 71.1 OPTION: Buffalo TH25 Phase 1 only Buffalo 2,100,000 $ 33% 5.7 2.0 36.0 69.8 TH 25 Corridor Improvements Buffalo 3,503,000 $ 35% 6.0 1.8 34.8 68.9 Hwy 71 Complete Streets Jackson 1,260,000 $ 54% 8.2 1.2 31.3 62.7 Gateway Corridor Improvements International Falls 776,180 $ 48% 7.7 1.7 34.2 60.6 TH 29 Reconstruction Parkers Prairie 1,800,000 $ 33% 5.7 1.0 30.0 58.7 Veterans Memorial Bridge Mankato 565,000 $ 23% 4.4 1.4 32.4 58.6 Broadway Streetscaping & Pedestrian Improvements Albert Lea 794,089 $ 33% 5.7 1.4 32.7 55.7 TH 220 Reconstruction East Grand Forks 2,318,070 $ 17% 3.5 1.5 32.8 51.5 TH10/59 Trail Detroit Lakes 200,000 $ 10% 0.0 1.1 30.3 46.6 18th Ave. S Waite Park 1,067,000 $ 83% 9.6 0.5 10.0 44.6 Old Hwy 61 Trail Dresbach 450,000 $ 40% 6.6 0.0 0.4 28.8 9/7/2017 24
9/7/2017 Optional Tagline Goes Here | mndot.gov/ 25
9/7/2017 26
9/7/2017 27
9/7/2017 28
9/7/2017 29
ATP Total # of Projects in STIP Total # of Major Projects in STIP Percent of Total Projects that are Major 1 119 25 21.0% 2 101 6 5.9% 3 100 15 15.0% 4 77 7 9.1% 6 118 19 16.1% 7 84 27 32.1% 8 96 8 8.3% Metro 225 17 7.6% Central 46 11 23.9% Total 966 135 14.0%
* Major projects are projects with a cost greater than $5.0 M in Greater Mn and $15.0 M in Metro.
9/7/2017 Optional Tagline Goes Here | mndot.gov/ 30
9/7/2017 31
Patrick Weidemann MnDOT Office of Transportation System Management 651-366-3758