High Voltage Testing at the 35t Long Baseline Neutrino Committee - - PowerPoint PPT Presentation
High Voltage Testing at the 35t Long Baseline Neutrino Committee - - PowerPoint PPT Presentation
High Voltage Testing at the 35t Long Baseline Neutrino Committee (LBNC): ProtoDUNE-SP CE & TPC Sarah Lockwitz, FNAL June 23, 2017 ANL (eng), W&M (prof., student, tech), LBNL(scientist, eng), KSU (prof, post doc, student), U.C. Davis
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Motivation
- Design is new
- Resistive cathode
- Aluminum profiles
- Cable-based HV bus
- …more
- And how do these pieces
work together?
Photos from B. Yu
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Motivation
- Predicting HV behavior in LAr is not easy /
designing stable & robust LArTPCs with Vcathode=180 kV is not well-trodden territory
- Breakdown can break components
- it can also set the operating limit of the
detector limiting the physics reach
- Instabilities in the system (glitches, “blips”) are
annoying, and may affect data quality
- Possible light production… HV issues can
cause light affecting our light detection system
Long Bo TPC
This ring is open This is why you should care!
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Introduction to the Test
- The goal of the HV test in the 35t was
to test the ProtoDUNE-SP design with regard to high voltage
- The test was carried out in the 35t in
PC4
- The 35t cannot fit the full size of the
ProtoDUNE-SP field cage.
- We used a partial field cage with
full-scale components (e.g. the profile curvature was the same, etc.)
https://inspirehep.net/record/1397920
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Introduction to the Test
- The goal of the HV test in the 35t was
to test the ProtoDUNE-SP design with regard to high voltage
- The test was carried out in the 35t in
PC4
- The 35t cannot fit the full size of the
ProtoDUNE-SP field cage.
- We used a partial field cage with
full-scale components (e.g. the profile curvature was the same, etc.)
Cathode Resistor to ground Relative Anode Potential (kV)
1.5 m 1.5 m 1.5 m
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
HV Issues We Were Preparing for
- We expected HV problems
to be something like a spark
- Fast discharge/high
current drawn momentarily
- Visible light
Feedthrough went here
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
HV Issues We Were Preparing for
- We expected HV problems
to be something like a spark
- Fast discharge/high
current drawn momentarily
- Visible light
Feedthrough went here
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Monitoring
✴ Power supply: voltage and current monitoring ✴ Current resolution ~10s nA ✴ Two toroids on the HV cable ✴ Sensitive to fast changes in current ✴ Two pick-off points near the end of the resistor
network
✴ Current going down the resistor chain ✴ Three PMTs. No wavelength shifter on them — Just
visible
✴ Cameras — RPi
HV PS
What We Saw Note:
- The supply was a current-limiting supply. When
the output current from the supply reached a set limit, the supply reduces the voltage to stay below the current threshold.
- The voltage listed in the following slides is the
voltage at the power supply unless otherwise
- noted. The voltage at the cathode was 5% less.
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Initial Turn On
- Purge, cool down, and fill went well
- On March 31st, just after we were filled with
not TPC-qualty (7 ppb) LAr we began to ramp.
- We tripped at 160 kV
- It appeared to be a real “fast discharge” trip.
- Let it sit over night at 150 kV, and ramped
without issue to 190 kV the next morning
- It held until we ramped down Monday
morning
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Running with Purification
- The pump started without any issue
- We then ramped back up to 190 kV and noted it
seemed to be getting noisier
- We then saw periods of elevated current; we called
this “streamer mode”
- Current was noisier coming out of the supply & less
current was going to the end of the resistor network
- → Alternate path to ground
- We lowered the voltage and saw this behavior also
at 150 kV
No Circulation Pumps On Current Read Back (and any jumps)
Pick-off points (near end of chain)
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Running with Purification
- The pump started without any issue
- We then ramped back up to 190 kV and noted it
seemed to be getting noisier
- We then saw periods of elevated current; we called
this “streamer mode”
- Current was higher coming out of the supply &
less current was going to the end of the resistor network
- Alternate path to ground
- We lowered the voltage and saw this behavior
also at 150 kV
Pick-off Points — voltage /current near the end of the resistor network Power Supply Read back (current = green)
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Continuing with the Run: Contamination
- We then wanted to better check the
effect of purity on the current features
- We bypassed the filters and returned
the condensed liquid to the cryostat
- Still had current features, but their
magnitude was smaller
- Running at 175 kV in ~350 μs LAr
Current
Pick-offs (end of chain)
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Purity Effects
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
What Happens at 100 kV?
- Let’s re-purify and answer this
- Ran at 100 kV in 3 ppb O2 LAr for
a baseline and restarted purification
- Ran at a steady ~4 ms lifetime
- Still observed streamer-like events
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Running in Stable ~4 ms LAr
- Lowered the current limit of the supply to 24% over
the expected current draw; considered this a “tight”-er limit
- Still “jumps/spikes”, 1-2/hour, no streamers
- Changed to 90, 70 120, 140, and 160 kV (with
corresponding current limit),— still spikes, similar rate
- (Note the order)
- After running at 70 kV, the current limit was raised from
21 μA to 40 μA, and a two minute streamer occurred
- Tighter current limits quench the long-streamer
behavior
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
How do the features behave in time? Are there charge-up effects?
- We turned the voltage to 0 for ~67 hours
and then ran at 150 kV
- We observed charge-effects. No activity for
4.5 hours (previously 1-2 features/hour).
- More followed. Appeared to get busier in time.
- Saw this for other voltages too
- There is a hysteresis — one can go to a higher
voltage and have a stable period, but going down did not lead to a stable period.
- This was not simply a current limit effect
- We record spikes even in the tight current limit running
- We relaxed the current limit and did not observe streamers after being off
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Where are the Sparks? A Quick Note on What We Were Seeing
- We were expecting HV issues to be like sparks we’d seen in other test setups
- Light produced & relatively fast discharge (resistive cathode may have slowed this)
producing a signal on the toroid
- While ramping up the first day, we experienced a trip of the PS. This appeared to be like
something we expected — there was a signal on the toroid
- We had something similar while ramping the day after the pumps were turned on (4/4)
- The PMTs were instrumented shortly after we purified
- We did not see light or toroid signals for any of the streamer or current activity in the
month after April 4th
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
A Note on Diagnostics on These HV Events — Dark Sparks
- We have 3 PMTs in the cryostat (no TPB on them)
- The PMTs were running after the first purification
- We do not see light associated with these events (H.Y. Liao’s work in our weekly
meeting) — they do see noise
- The PMTs were working — they see the purity monitors and Cherenkov light from
showers
- Toroids do not see activity for the streamer events (slow developing).
- See two types of signals on the toroids
— small signal (10s mV)
- Large (multiple Vs) signals we expect
from breakdowns — only a few of these (1st day, 200 kV event, one while ramping…)
- It seemed to be hard to get a fast-discharge-like
event in the pure[r] states
Evidence the PMTs are working
Cherenkov light from shower
Photo: G. Horton-Smith
~95 μA current jump at 180 kV on 4/4 25 V 200 μA current jump at 170 kV on 4/25 30 mV
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
What’s Going On? Going Out with a Bang
- Toward the end of the run, after not seeing traditional
sparking behavior, we went to 200 kV — the maximum
- f the supply
- Current limit was loose (200 μA limit; ~48 μA exp.)
- Ran for 8 hours — streamers/activity
- Then, we suffered a major E&M event (30 kV swings)
- Probed issues that could occur
- Instrumentation tripped off (Keithleys, scopes, PMT HV, cameras) — some didn’t recover
- Our LAr pump was turned off
- Lesson: Look at conditions for cryo-system — make it resistant to sparks
- The field cage, resistor chain, and HV feedthrough + filters were not damaged.
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
A Note on These Current Features
- Between the PS and the field cage, there are a series of
resistors totaling 200 MΩ
- A 1 μA change in power supply current is a 200 V change on
the cathode
Cathode HV Impurities Current Read Back Current Set Limit
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
A Note on Diagnostics on These HV Events
- Looking at the pick-off points and
current measurements, one can make a model for where the leakage current to ground is occurring (assuming one discharge point per event).
- Three independent models
pointed to something near the cathode, but not the cathode
- One attractive candidate are the
cathode Field Shaping Strips (design since changed in PD-SP)
V
Ist
Filters Good side of FC Current to Gnd Anode to Gnd 3 non-streamer walls of FC Photo: G. Horton-Smith
Possible culprit?
Pick-offs + PS Current = ?
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Stage II Test
- There was always a plan to have a second run
including the beam plug once it was finished.
- That is being installed now
- The cathode field shaping strips have been modified
(smaller, will fit inside the envelope of the field cage)
- The ground planes above, below, and behind the
field cage are being instrumented to be read out
- Better identify where the source of the extra
current to ground is.
- A PMT with TPB is being installed
- Scheduled to begin purging in July
Beam plug in CA Beam plug @ FNAL Monday
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Closing Thoughts
- The 35t cryostat attained a 5-6 ms lifetime after identifying and addressing a stratification issue
- We do not immediately spark at any voltage tested up to ~190 kV on the cathode
- We see high current draws that seem to come from a feature near the cathode
- Long (in time) current streamers appear to be controlled by “tight” current limits
- Visible light is not associated with these
- We don’t know the effect of these features on a real TPC (electronics, scale). I note a 1 μA drop at the supply is a 200 V drop at the
cathode.
- Time at voltage is a dependent variable. Charge-up effects?
- Purity effects: Greater magnitude current draws in purer argon (but current spikes/jumps in the entire range of argon studied),
“difficulty” getting spark like behavior in very pure argon (streamers)
- The field cage, resistor network, HV feedthrough, HV filters & cables all survived (likely the largest LAr HV event on site).
- One should carefully consider fault conditions/interlocks for the cryogenics system. Interlocks need to be robust against E&M events.
Back-up Slides Follow
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Streamers?
- Reminded me of something from a
few years ago
- While looking for breakdown with a
1.3 mm ball, sparks were seen for gaps (between the sphere and ground) < 20 mm.
- At 20 mm, we just noted an
increasing current draw with the voltage from the PS
- No light, no sound — just a
steady current draw.
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Purification Success! Attained a τ ~ 5-6 ms
PrMs
O2 Analyzer
O2 analyzer switched to vapor space
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Purification Success! The Before: A Stratification Issue
- The returned filtered liquid
was assumed to be warmer than the bulk in the cryostat (flowing faster)
- But before returning, the
liquid passes through a phase separator that puts the liquid in the same state as the liquid-gas interface
- f the bulk liquid — cooler
Credit E. Voirin
- A. Hahn: 10.1109/NSSMIC.2014.7431158
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Purification Success! The Before: A Stratification Issue
- The return and the intake were located at the bottom of
the cryostat
- Temperature stratification
Credit E. Voirin
Input Return
Credit: E. Voirin Credit: A. Hahn
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Purification Success! The Before: A Stratification Issue
- The return and the intake were located at
the bottom of the cryostat
- τ ~ 3 ms
Credit E. Voirin
Input Return
Credit: E. Voirin
Longer PrMs
Credit: A. Hahn
LBNC: HV Test in the 35t Sarah Lockwitz June 23, 2017
Purification Success! The After
- The liquid return was modified to be about 2/3
- f the height of the cryostat. Plots below
show measured and predicted lifetimes vs. height in LAr
Credit: E. Voirin