SLIDE 1 1.
Introduction
2.
Classification of High Voltage Tests
3.
Test Voltages
4.
High Voltage Testing of Electrical Apparatus
CHAPTER 10 HIGH VOLTAGE TESTING OF ELECTRICAL APPARATUS
SLIDE 2
Purpose of the testing: To ensure that the
electrical equipments are capable of withstanding the overvoltages that are met with in service.
Covers basic requirements procedures for testing
- n several electrical apparatus. Normally, high
voltage (HV) testing is to investigate the insulation performance.
International/national specifications for testing are
- utlined (details of test, specific equipment,
procedure and acceptable limits) to meet the users’ and manufacturers’ requirements.
SLIDE 3
2.1 CLASSIFICATION OF HIGH VOLTAGE TESTS
Destructive Test
Normally the equipment underwent
destructive test cannot be used in the service.
Test voltage is higher than its normal
working voltage.
Breakdown test.
SLIDE 4
Con’t
Non-Destructive Test
Mainly done to assess the electrical
properties, eg. Resistivity, dielectric constant and loss factor.
The apparatus is not destroyed during
the test and can be used again.
SLIDE 5 2.2 TYPES OF TESTS
Made by the manufacturer on every finished piece
To fulfills the specifications.
Performed on each type of equipment before their
supply on a general commercial scale – demonstrate performance characteristics.
No need to repeat the test unless changes are
made in the design of the product.
SLIDE 6 Con’t
Usually carried out after
maintenance/repair of the equipment.
Conducted according to schedule
provided.
Purpose of the test : To ensure the
equipment lifetime is achieved.
SLIDE 7 Types of tests
The range of high voltage tests depends
equipment being tested
SLIDE 8 3.0 TEST VOLTAGES
TEST VOLTAGES
impulse voltages. power- frequency alternating voltages (AC) Direct voltages (DC)
SLIDE 9
Con’t
Test with Direct Voltage (DC).
Mainly to test equipment used in
HVDC transmission systems.
Insulation testing, fundamental
investigations in discharge physics and dielectric behavior.
Rate of voltage rise above 75% of its
estimated final value should be about 2% per second.
SLIDE 10
Con’t
Test with Alternating Voltage (AC).
Frequency range : 40-60 Hz,
sinusoidal shape.
Dry withstand test : Most common
routine test for all types of electrical equipment especially insulators, bushing, rod gaps etc.
Applied voltage between two to three
times of the normal working voltage.
SLIDE 11 Con’t
Test with Alternating Voltage (AC) – cont.
Wet withstand test : To simulate the effect of
natural rain on external insulation.
Recommended for tests on apparatus which are designed
for outdoor used.
Use artificial rain. Applied for 30-60 seconds.
SLIDE 12 Con’t
Test with Impulse Voltage.
Is designed to investigate the
insulation performance due to the lightning stroke or Lightning impulse chopped on the front switching operation.
3 types of impulse voltages, ie;
1) Full wave 2) Chopped wave 3) Switching wave
BS 923: Part 2: 1980
SLIDE 13 Con’t
BS 923: Part 2: 1980
Lightning impulse chopped
Full switching impulse
SLIDE 14 Con’t
Rated impulse withstand test
For test on non-self-restoring insulation, 3 impulses
are applied.
For withstand tests on self-restoring insulation, 2
procedures are used:
1) 15 impulses (rated withstand voltage) with the specified
shape and polarity are applied
2) Test procedure for determining 50% disruptive discharge
voltage is applied The method used for determining the levels of
applied voltage is up-and-down methods.
SLIDE 15 Atmospheric Correction Factors
The electrical characteristics of the insulators and
- ther apparatus are normally referred to the reference
atmospheric conditions.
According to the British Standard Specifications, they
are: Temperature : 20oC Pressure : 1013 millibars (or 760 torr) Absolute humidity : 11 gm/m3
Since it is not always possible to do tests under these
reference conditions, correction factors have to be applied.
SLIDE 16
Atmospheric Correction Factors
V0 = voltage under actual test conditions, Vs = voltage under reference atmospheric conditions, h = humidity correction factor, and d = air density correction factor. The air density correction factor is given by, where, b = atmospheric pressure in millibars, and T= atmospheric temperature, oC.
SLIDE 17
Humidity correction factor h is obtained from the
temperatures of a wet and dry bulb thermometer, by obtaining the absolute humidity and then computing h from the absolute humidity.
SLIDE 18
Example 1
Sarzaminor conducted an AC flashover test at
power frequency on a cap and pin insulator for his FYP project. From the test, it was found that flashover occurred at 80 kV. If the dry and wet temperatures during the test were 25˚C and 22˚C respectively, and atmospheric pressure was at 1 atm, determine the flashover voltage under the reference atmospheric condition.
SLIDE 19 Example 1
Dry Temp. = 25˚C Wet Temp. = 22˚C
18
Absolute humidity = 18g/m3
SLIDE 20 Example 1
Dry Temp. = 25˚C Wet Temp. = 22˚C 1 atm = 1013.25 milibar
0.92
h=0.92
SLIDE 21
4.0 HIGH VOLTAGE TESTING OF ELECTRICAL APPARATUS
Transformer Circuit breaker Insulator Cable
SLIDE 22 Impulse testing on transformer
- A change in the waveshape of the voltage
and current both before and after the chopped waves have been applied.
- The existing of acoustic noise.
- Visual signs of flashover
- According to BS 171: Part 3. Carried
- ut at room temperature with the
transformer not energized.
- Used standard impulse waveshapes.
Full and chopped waves.
Impulse Test Temperature Rise Test Short Circuit test Failure detection (Insulation failure)
SLIDE 23 Testing of Circuit Breaker (BS 5227: Part 2, IEC 56)
withstand tests of power frequency, lightning and switching impulse voltages.
the open and closed positions
Dielectric tests or
- vervoltage tests,
- Type test
Temperature rise and mechanical tests
- The most important test
- n circuit breaker since
these tests assess the primary performance of these devices, i.e. their ability to safely interrupt the fault currents
Short Circuit Tests
SLIDE 24 Short Circuit Test
Methods of conducting short circuit tests are
(I) Direct Tests (a) using a short circuit generator as the source (b) using the power utility system or network as the source. (II) Synthetic Tests
Consists of two separate sources : one power source acting
as a current source supplying the required short-circuit current at a (relative) low-voltage level and a second source working as a voltage source supplying the required voltage.
Based on the fact that for certain (short circuit) tests the test
- bject is stressed by a high current and by a high voltage at
different time periods.
SLIDE 25 Tests on Insulator
Test on Insulator Power Frequency Test Dry and Wet flashover test increased at a uniform rate of about 2 % per second of 75% of the estimated test voltage Dry and Wet Withstand test Voltage applied under dry or wet conditions for a period of 1 minute with an insulator mounted as in service conditions. The test piece should withstand the specified voltage. Impulse Tests Impulse Withstand Voltage Test Both positive and negative polarities Insulator passed the test if five consecutive waves do not cause flashover or puncture
Impulse Flashover Test
Pollution Testing Due to outdoor electrical insulation and consequent problems of the maintenance
- f electrical power systems. Eg. Dust,
industrial pollution (smoke & petroleum vapor), desert pollution, snow Pollution causes corrosion, non- uniform gradients, deterioration of the material, partial discharges and radio interference.
SLIDE 26 Routine and Type test on cables
According to BS 923: Part 2, IEC 60-2, IEC 55-1, IEC 230 and BS6480.
Different tests on cables may be classified into I.
mechanical tests like bending test, dripping and drainage test, and fire
II.
resistance and corrosion tests,
III.
dielectric power factor tests,
- IV. power frequency withstand voltage tests, (a.c. voltage of 2.5
limes the rated value for 10 min.)
V.
Dc withstand voltage tests, (1.8 times the rated d.c. voltage
- f negative polarity for 30 min)
- VI. Impulse withstand voltage tests, (withstand five impulse of
prescribed magnitude without any damage
- VII. partial discharge tests,
SLIDE 27
SLIDE 28
SLIDE 29