HEYWOOD INTERCONNECTOR UPGRADE RIT-T Public Forum 24 November 2011 - - PowerPoint PPT Presentation

heywood interconnector upgrade rit t
SMART_READER_LITE
LIVE PREVIEW

HEYWOOD INTERCONNECTOR UPGRADE RIT-T Public Forum 24 November 2011 - - PowerPoint PPT Presentation

HEYWOOD INTERCONNECTOR UPGRADE RIT-T Public Forum 24 November 2011 Presentation Outline Introduction and context (Rainer Korte) Drivers for the RIT-T (Luke Falla) Network augmentation options (Vinod Dayal) Market modelling


slide-1
SLIDE 1

HEYWOOD INTERCONNECTOR UPGRADE RIT-T

Public Forum

24 November 2011

slide-2
SLIDE 2

ElectraNet 2

Presentation Outline

 Introduction and context (Rainer Korte)  Drivers for the RIT-T (Luke Falla)  Network augmentation options (Vinod Dayal)  Market modelling approach (Bradley Harrison)  Discussion/Feedback (Rainer Korte)  AEMO Management perspective (Joe Spurio)  Close (Rainer Korte)

slide-3
SLIDE 3

3

Introduction and context

Rainer Korte – ElectraNet Executive Manager Network Strategy and Regulatory Affairs

slide-4
SLIDE 4

ElectraNet

2010 SA Interconnector Study

 Investigated feasibility of transmission options that would…

– provide additional support for South Australian at times of peak demand – allow further development of South Australia’s renewable energy resources by increasing export capacity

 Incremental upgrades and major new interconnectors considered  Impact of proposed Green Grid development considered as a sensitivity  Report published February 2011

Slide 4

slide-5
SLIDE 5

ElectraNet

Feasibility Study Conclusions

 Study demonstrated the potential for increased interconnector capacity between SA and rest of NEM  Upgrade of Heywood Interconnector shown to be feasible as early as 2017-18 under conditions of high growth, high carbon price and significant wind investment in SA  Major new 500 kV interconnector options – lowest cost southern option was shown to be most feasible (in 2020 to 2030 timeframe)

Slide 5

slide-6
SLIDE 6

ElectraNet

Heywood Interconnector Upgrade

 Subsequently AEMO and ElectraNet examined more closely the feasibility of relatively low cost upgrades of the Heywood Interconnector  Results indicated that an approx. 40% increase in capacity (up to 650 MW) would provide positive net market benefits

  • ver a wide range of scenarios with optimal timing between

2013 and 2017  Results published in South Australian and Victorian Annual Planning Reports (June 2011)  ElectraNet and AEMO immediately committed to and commenced application of the RIT-T to the Heywood Interconnector Upgrade

Slide 6

slide-7
SLIDE 7

ElectraNet Slide 7

RIT-T Consultation

 Purpose of the RIT-T and public forum

– Deliver cost effective investments that maximise market benefits – Promote understanding of the investment need and obtain input on credible options to achieve the above objective

 Project Specification Consultation Report (PSCR) has been published at www.electranet.com.au and www.aemo.com.au  AEMO and ElectraNet invite comments on the PSCR  Submissions to appleby.simon@electranet.com.au or planning@aemo.com.au by 30 January 2012  Project Assessment Draft Report to be published mid-2012

Slide 7

slide-8
SLIDE 8

8

Drivers for the RIT-T: Existing Interconnector limits and market impacts

Luke Falla – AEMO Principal Engineer, Network Planning

slide-9
SLIDE 9

ElectraNet

Increase in constraints binding

 Continuing trend of increasing VIC-SA interconnector binding hours

– Data for 2011 only up to November – In January 2011 the SA to VIC combined limit with Murraylink was increased from 420 MW to 580 MW

9 500 1000 1500 2000 2500 3000 3500 2008 2009 2010 2011 Hrs binding

slide-10
SLIDE 10

ElectraNet

Interconnector energy transfers

 General decrease in net VIC to SA flow, and increased SA to VIC flow

10

  • 1,000
  • 500

500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 GWh Year rt rt

Source- AEMO SASDO 2011

slide-11
SLIDE 11

ElectraNet 11

Increased wind farm generation

200 400 600 800 1,000 1,200 50 100 150 200 250 300 350 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 Jun-05 Sep-05 Dec-05 Mar-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Mar-08 Jun-08 Sep-08 Dec-08 Mar-09 Jun-09 Sep-09 Dec-09 Mar-10 Jun-10 Sep-10 Dec-10 Mar-11 Installed capacity (MW) Total wind farm monthly output (GWh) Year and month

Installed capacity (MW) Wind farm output (GWh)

Source- AEMO SASDO 2011

Financial Year Maximum Half-Hourly Output (MW)

2004/2005 235 2005/2006 286 2006/2007 320 2007/2008 540 2008/2009 641 2009/2010 765 2010/2011 978

slide-12
SLIDE 12

ElectraNet

Range of interconnector limits

 Limits vary considerably depending on SA region demand and dispatch conditions.

12 200 400 600 800 1,000 1,200 1,400 1,600 1,800 Hours Transfer limits

Export Import

Source- AEMO VAPR 2011 Positive flow is for VIC to SA direction

slide-13
SLIDE 13

ElectraNet

Impacts of SA to VIC limitations

 Number of negative price events increasing  Wind farms being constrained off

13 200 400 600 800 1,000

  • 1200
  • 900
  • 600
  • 300

300 0:00 6:00 12:00 18:00 0:00 Wind generation (MW) Sa price ($/MWh) Time of day

SA1 Price 30m Wind generation

Year Total 2006 1 2007 10 2008 51 2009 93 2010 139

  • No. of negative price

events in the SA region

slide-14
SLIDE 14

ElectraNet

Impacts of VIC to SA limitations

 Can contribute to high SA region prices  Price separation events between SA and VIC regions

  • ccurring

14 200 400 600 2000 4000 6000 8000 10000 12000 11:02 12:12 13:21 14:31 15:40 16:50 18:00 VIC-SA limit(MW) SA Price ($/MWh) Time of day SA1 5 min Price VIC-SA limit

Year SA1 VIC1 2008 66 40 2009 60 36 2010 40 34 2011 42 32

Average annual region price ($/MWh)

slide-15
SLIDE 15

ElectraNet

Constraint types setting limits

 For ‘Nil outage’ constraints in 2010

– Voltage stability in SA – 542 hrs – Thermal limits in SA – 204 hrs – Transient stability in VIC – 430 hrs – Thermal limits in VIC – 493 hrs – Oscillatory stability – 42 hrs i.e. a number of complex issues are required to be considered and resolved

15

Source- AEMO Constraint Report 2010

slide-16
SLIDE 16

ElectraNet 16

Existing network-limiting factors

Existing Interconnector limits are due to: Heywood 500/275 kV transformer ratings (460 MW) Thermal ratings in SA 132 kV network Voltage stability limits in the South East area (trip of largest unit in SA) Oscillatory stability limit (limit for Murraylink and Heywood, 580 MW) 500/330 kV F2 transformer rating at South Morang (for high VIC - NSW flow) Victorian Export transient stability limits

slide-17
SLIDE 17

ElectraNet

Previous studies

 Joint Interconnector Feasibility Study

– Studied in conjunction with larger upgrade options – Showed incremental option to have net benefits under all scenarios

 2010 NTNDP

– Incremental upgrade option chosen in some scenarios

17

slide-18
SLIDE 18

ElectraNet

Summary

 The existing interconnector continues to be constrained more and more often in both flow directions.  High prices in SA during high demand periods, and negative prices during low demand periods highlighting the issues.  New wind generation causing more and more energy to be exported to VIC from SA, and now being constrained off at times.  Limits caused by equipment ratings as well as stability limits.  Previous ElectraNet/AEMO studies highlighting the potential

  • f net market benefits for an upgrade.

18

slide-19
SLIDE 19

19

Network Augmentation Options

Vinod Dayal - ElectraNet Principal Engineer (Network Strategy)

slide-20
SLIDE 20

ElectraNet

South Australian power system – features and benefits of Interconnection

 Very peaky demand profile with average to low demands for most of the year  Significant wind penetration - 1200 MW  High wind generation mostly occurs during average to light demand periods  Abundant renewable generation resources  Significant mineral resources available  Interconnection strengthens the South Australian power system  Generation capacity reserves shared with Victoria, to effectively manage the short time that peak capacity is required in SA  Export surplus wind generation at times of lower SA demand  Importing lower cost generation from rest of NEM

20

Source: NTNDP 2010

 Maximum Interconnector Capacity

– Heywood + 460 MW – Murraylink + 220 MW

Typical annual SA Load Duration Curve

slide-21
SLIDE 21

ElectraNet

Victoria Transmission Network associated with SA Interconnector paths

 Heywood Interconnector is connected via 275 kV lines from SA, stepped up and connected to high capacity 500 kV lines to Melbourne (South-West corridor)  Murraylink is connected via number

  • f 220 kV lines; there are network

limitations under certain operating conditions

21

Heywood

275 kV

To South East

500 kV

To Melbourne

slide-22
SLIDE 22

ElectraNet

SA Transmission Network associated with Interconnector Paths  Heywood interconnector is connected via 275 kV lines from South East to Adelaide with an underlying 132 kV network; thermal and stability constraints are applied under certain operating conditions, limiting both Imports and Exports  Murraylink is connected via two 132 kV lines; there are network limitations under certain operating conditions, limiting both Imports and Exports

22

slide-23
SLIDE 23

ElectraNet 23

Augmentations - Victoria

Heywood

275 kV

To SA

500 kV

To Melbourne

 3rd 500/275 kV transformer at Heywood  Dynamic line rating of South East to Heywood 275 kV lines

slide-24
SLIDE 24

ElectraNet

Augmentations in SA – Issues for consideration

24

Summer design MVA ratings shown

 Impact of the lower capacity underlying 132 kV transmission system  Age of the lower capacity 132 kV transmission lines (~50 years)  High maintenance costs identified for the upkeep of aged transmission assets  Transient/Voltage stability consideration (Reactive Power requirements)  Impact of network reconfiguration

slide-25
SLIDE 25

ElectraNet 25

SA augmentation options

Summer design MVA ratings shown

 Options

– Operational management of thermal limitations – Decommission/ disconnect the Snuggery-Keith and Keith-Tailem Bend #1 132 kV lines – Un-mesh the 132 kV system from the 275 kV network

 Common works

– Upgrade minor plant to release additional transmission capacity in the interconnector corridor

Identification of additional requirements to support transfer capability (such as reactive plant) is an outcome

  • f the technical assessment
slide-26
SLIDE 26

ElectraNet

Assessment of SA options

Options not technically feasible or cost effective:  Operational Management

– Insufficient thermal inertia of lines to allow short term rating – Security issues related to inter-trip schemes – Cost of maintaining the aged assets

 Un-meshing of 132 kV network

– Significant reduction in stability limitations (and associated costs to fix the limitations) – Security impacts due to limited circuits across the transfer path – Cost of maintaining the aged assets

26

slide-27
SLIDE 27

ElectraNet

Assessment of SA options

 Option for consideration in market modelling

– Decommission/ disconnect Snuggery-Keith and Keith-Tailem Bend #1 132 kV lines – 100 Mvar 275 kV Capacitor Bank OR 30% Series Compensation of Tailem Bend – South East 275 kV Lines – Additional 132 kV reactive support at Keith and Penola connection points

 Advantages

– Provides significant thermal transfer capability – Good sharing of power flows between the 275 kV lines and the remaining 132 kV lines – Less reactive support required to meet stability requirements when 132 kV system is still connected – No on-going costs to maintain aged assets – Aligns with strategic planning outcomes for the region

27

slide-28
SLIDE 28

ElectraNet

Greenfield option

 SA Interconnector Feasibility Study concluded that the Southern option was the greenfield option showing a net positive market benefit in most scenarios  Therefore, Southern option to be progressed as the Greenfield option for this RIT-T

28

Source: AEMO-ElectraNet JFS report only

Greenfield Options Support Projects

Source: AEMO-ElectraNet JFS report only

slide-29
SLIDE 29

ElectraNet 29

Options for Market Modelling

slide-30
SLIDE 30

30

Market Modelling Approach

Brad Harrison, ElectraNet Principal Energy Market Analyst

slide-31
SLIDE 31

ElectraNet

* Includes fuel costs, losses and potential price impacts on consumption

Long term

(Plexos)

SRMC Time sequential

(Prophet)

Dynamic bidding

(Plexos) Horizon: to 2045 Time: Monthly, 18 load blocks Losses: Load does not include losses, interconnector loss model consistent with market dispatch algorithm.

Generation built Generation built. Asses grid impacts

1 Identify credible options and scenarios to be used 2

Horizon: 1 year at a time for 20 years Time: Time sequential, hour by hour Bidding: Short Run Marginal Cost

3 4

Results per run

NPV of:

  • Generation CAPEX
  • Generation OPEX*
  • Unserved energy

Bidding: Dynamic bidding strategy consistent with requirements of RIT-T.

5 6

Market Modelling Approach

31

slide-32
SLIDE 32

ElectraNet

Step 1 – Scenarios

Theme Scenario: Low growth Scenario: Medium growth Scenario: High growth Economic growth Low Medium High Demand growth Low Medium High + Eyre Peninsula and Olympic Dam Expansion Carbon price High Treasury price Core Treasury price Core Treasury price Technology timings Timings + 2 years NTNDP refresh Timings - 2 years Gas prices Low Medium High Demand side tech and management Zero Low High LRET Achieved Achieved Achieved

32

slide-33
SLIDE 33

ElectraNet

Step 2 – Modelling details

 Time resolution ( to 2045 )

– Monthly resolution – Targeting 18 Load Duration Curve blocks

 Geography

– Regional model

 Least cost co-optimisation

– Requirement of the RIT-T

 Relaxed integer model  Network losses – mark-up  Network congestion –remote and low impact constraints removed

33

slide-34
SLIDE 34

ElectraNet

Step 3 – LT expansion

 Observe where and when the Step 2 modelling invests in new capacity  Determine commissioning year:

– Relaxed integer build allows for increments of power stations. Requires some judgement

 Review implications of investment decisions for

– network management – network augmentation

34

slide-35
SLIDE 35

ElectraNet

Step 4 – Time sequential runs

 20 year assessment  Generators dispatched based on short run marginal cost  Hour by hour simulation  Ensure optimal operation given annual constraints

– Hydro energy limits

 All NTNDP system normal network constraints

– Additional constraints specific to the network options being modelled

35

slide-36
SLIDE 36

ElectraNet

Step 5 – Economic assessment

 Assumptions

– Discount rates

  • WACC ( 10 % )

– End effects

  • Benefits calculated to perpetuity

 Approach

– Compare total discounted system costs for each option/timing with a base case without any upgrades

 Is there a clearly preferred option?

– If not, assess dynamic bidding

36

slide-37
SLIDE 37

ElectraNet

Step 6 – Dynamic bidding

 Is modelling of dynamic bidding necessary?

– What is the magnitude of market benefits from dynamic bidding (competition benefits) – Are these benefits required to differentiate between credible

  • ptions

 RIT-T and wealth transfers

– Net market benefits, not just a price change

37

slide-38
SLIDE 38

38

Discussion/ Feedback

slide-39
SLIDE 39

39

AEMO Management Perspective

Joe Spurio, AEMO Senior Manager, Network Analysis

slide-40
SLIDE 40

ElectraNet Slide 40

Next Steps

 Project Specification Consultation Report (PSCR) has been published at www.electranet.com.au and www.aemo.com.au  Public forum slide pack will also be available on websites  AEMO and ElectraNet invite comments on the PSCR  Submissions to appleby.simon@electranet.com.au or planning@aemo.com.au by 30 January 2012  Submissions will be published on the websites  Project Assessment Draft Report to be published mid-2012

Slide 40