Ports-to-Plains Corridor Feasibility Study (HB 1079) Segment #1, Committee Meeting #5 Conference Call/Web-Ex June 11, 2020 June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) Ports-to-Plains Corridor Feasibility Study (HB


slide-1
SLIDE 1

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Ports-to-Plains Corridor Feasibility Study (HB 1079)

Segment #1, Committee Meeting #5 Conference Call/Web-Ex

slide-2
SLIDE 2

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Welcome

TxDOT Leadership Caroline Mays, Director, Freight, Trade and Connectivity, TxDOT Honorable Dan Pope, Mayor, City of Lubbock, Ports-to-Plains Advisory Committee Chair Jared Miller, Amarillo City Manager, Segment #1 Committee Chair

slide-3
SLIDE 3

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Chapter 4 7

Agenda Review

Welcome 1 Summary of Public Meeting and Public Comments 2 Cover Page, Table of Contents, and Chapter 1 3

3

Adjourn 11 Chapter 5 8 Chapter 2 4 Chapter 3 5 Break 6 Chapter 6 and Appendices 9 Executive Summary 10

slide-4
SLIDE 4

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1

Summary of Public Meeting and Public Comments

Caroline Mays, TxDOT

slide-5
SLIDE 5

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Overview of Public Meeting #3 Segment #1 - May 14, 2020

5

▪ The public attended a virtual online public meeting due to COVID-19 ▪ Number of Attendees – Website analytics - 23 new users, and 116 pageviews – 5 General Public Sign-ins on website – ~7 General Public attended LIVE meeting ▪ Topics Presented – preliminary recommendations provided by the study's segment committee ▪ Comments/Input – One comment in support of the Study

Virtual Meeting

slide-6
SLIDE 6

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1

Cover Page, Table of Contents, Chapter 1 - Introduction

Jared Miller, Segment #1 Chair Caroline Mays, TxDOT

slide-7
SLIDE 7

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

7

This chapter provides information about the importance of the Corridor and Segment #1. It reviews HB 1079, Segment Committees, and the process. ▪ Introduction ▪ House Bill 1079 ▪ Segment Committee Membership

– Study Purpose and Background – Goals of the Study

▪ Study Development Process ▪ Organization of the Report Chapter 1: Introduction

slide-8
SLIDE 8

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1

Chapter 2 – Existing Conditions and Needs Assessment

Jared Miller, Segment #1 Chair Caroline Mays, TxDOT

slide-9
SLIDE 9

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

9

The purpose of this chapter is to summarize the existing conditions and characteristics in the Corridor and in Segment #1. ▪ Environmental Characteristics ▪ Population Characteristics ▪ Economic Conditions

– Median Household Income – Employment – Energy – Agriculture

▪ Roadways and Bridges ▪ Traffic Conditions ▪ Truck Traffic and Freight Flow Conditions ▪ Safety Conditions

– Total Crashes – Total Truck Crashes

Chapter 2: Existing Conditions and Needs Assessment

slide-10
SLIDE 10

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1

Chapter 3 – Forecasted Conditions

Jared Miller, Segment #1 Chair Caroline Mays, TxDOT

slide-11
SLIDE 11

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Chapter 3: Forecasted Conditions

11

▪ Forecasted Population ▪ Forecasted Economics

– Household Median Income – Employment – Gross Domestic Product

▪ Forecasted Freight Tonnage ▪ Land Use Potential ▪ Planned and Programmed Projects ▪ Gap Analysis ▪ Future Traffic Conditions

– Baseline vs. Interstate Upgrade

▪ Forecasted Freight Flow The purpose of this Chapter is to provide a summary of Forecasted Conditions to the year 2050.

slide-12
SLIDE 12

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Meeting Break

slide-13
SLIDE 13

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1

Chapter 4 – Segment Interstate Corridor Feasibility and Analysis

Jared Miller, Segment #1 Chair Caroline Mays, TxDOT

slide-14
SLIDE 14

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Chapter 4: Interstate Feasibility Analysis and Findings

14

This Chapter provides an analysis of the feasibility of an Interstate Facility within the Corridor, including findings on the requirements of HB 1079. ▪ Baseline ▪ Interstate ▪ Corridor Interstate Feasibility Analysis Process and Results

– Examination of freight movement – Ability of Energy Industry to Transport Products to Market – Determination of Traffic Congestion Relief – Determination of Ability to Promote Safety and Mobility – Determination of Areas Preferable and Suitable for Interstate Designation – Evaluation of Economic Development Impacts and Return on Investment – Assessment of Federal, State Local and Private Funding Sources

slide-15
SLIDE 15

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1

Chapter 5 – Public Involvement and Stakeholder Engagement

Jared Miller, Segment #1 Chair Caroline Mays, TxDOT

slide-16
SLIDE 16

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

16

Chapter 5: Public Involvement and Stakeholder Engagement This chapter is a review of public involvement and stakeholder engagement that occurred during the study process. ▪ Segment Committee Meetings ▪ Public Involvement ▪ TxDOT District Consultation

slide-17
SLIDE 17

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1

Chapter 6 – Recommendations and Implementation Plan, Appendices

Jared Miller, Segment #1 Chair Caroline Mays, TxDOT

slide-18
SLIDE 18

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

18

This chapter summarizes recommendations and prioritizations provided by Segment #1 Committee members. It also discusses key issues considered for recommendations including energy impacts, freight movement, congestion relief, safety and mobility, and ports of entry. ▪ Committee Recommendations

– Interstate upgrade – Relief route projects – Safety and operational improvements

▪ Segment Implementation Plan ▪ Next Steps Chapter 6: Segment Committee Recommendations and Implementation

slide-19
SLIDE 19

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Draft Executive Summary

Jared Miller, Segment #1 Chair Caroline Mays, TxDOT Segment #1

slide-20
SLIDE 20

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

20

Executive Summary Outline ▪ Introduction ▪ Purpose of the Study ▪ Stakeholder and Public Engagement ▪ Existing and Future Corridor Conditions ▪ Feasibility Analysis of an Interstate and Findings ▪ Recommendations and Implementation Plan ▪ Next Steps Segment Committee Report Executive Summary

slide-21
SLIDE 21

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020 Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Open Discussion

Jared Miller, Segment #1 Chair

slide-22
SLIDE 22

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Segment #1 Committee Next Steps

22

Segment #1

▪ Final Repor

  • rt sent to Advisor
  • ry Com
  • mmi

mittee June 30, 2020 ▪ Next Advisory

  • ry Commi
  • mmittee Meeting

Wednesday, July 15, 2020

slide-23
SLIDE 23

Ports-to-Plains Corridor Feasibility Study (HB 1079) June 11, 2020

Questions

23