Harvey Jones Channel (HJC) Improvements Public Meeting December - PowerPoint PPT Presentation

Harvey Jones Channel (HJC) Improvements Public Meeting December 12, 2012 PLEASE SIGN IN 12/12/2012 1 HJC Improvements Project Welcome / Introductions: SSCAFCA Staff Dave Gatterman, P.E., Project Manager Chuck Thomas, P.E.,


  1. Harvey Jones Channel (HJC) Improvements Public Meeting December 12, 2012 PLEASE SIGN IN 12/12/2012 1

  2. HJC Improvements Project • Welcome / Introductions: – SSCAFCA Staff • Dave Gatterman, P.E., Project Manager • Chuck Thomas, P.E., Executive Engineer – Bohannan Huston, Inc. (BHI) Staff • Howard Stone, P.E., Principal • Scott Armstrong, P.E., Project Manager • Denise Weston, Project Planner • Marron and Associates, Environmental Consultant – VOC Mayor and Council members 12/12/2012 2

  3. HJC Improvements Project • Setting – The HJC is the bottom of the Montoyas Arroyo Watershed Park 12/12/2012 3

  4. HJC Improvements Project • Montoyas Watershed Park statistics – Two major arroyos, Montoyas and Lomitas Negras – Runs thru unincorporated Sandoval County, the City of Rio Rancho, and the Village of Corrales – Watershed area is ~ 60 square miles – Approximately 75% of this watershed park is undeveloped 12/12/2012 4

  5. HJC Improvements Project • Where exactly is the project? City of Rio Rancho Project Location Sandia Pueblo Harvey Jones Channel NM448 Village of Corrales 12/12/2012 5

  6. HJC Improvements Project • Why are we proposing this project? – 2006 – 2010 12/12/2012 6

  7. HJC Improvements Project • Project Objectives / Goals – Hydraulic considerations • Increase capacity under NM448 (Corrales Rd.) • Move hydraulic jump downstream of bridge – Sediment from upstream reduces hydraulic capacity during storm event • Minimize sediment deposition under bridge – This project is part one of a three part fix • SSCAFCA is seeking funding for parts two and three 12/12/2012 7

  8. Companion projects Future Sediment Pond Future Sediment Pond 12/12/2012 8

  9. HJC Improvements Project • Project Constraints – Maintain current grade on Corrales Rd. • Avoid raising current road profile – Improvements contained in public ROW • Avoid ROW takes 12/12/2012 9

  10. HJC Improvements Project • Funding – NMDOT Funds (from FHWA) – State Legislative Appropriation – Funds are secured for project completion – Total funding available from non-SSCAFCA sources ~$950K • Any additional funding would need to be supplied using SSCAFCA sources, with Board approval 12/12/2012 10

  11. HJC Improvements Project • Status – BHI has completed the draft Design Analysis Report (DAR) for SSCAFCA review – BHI/Marron and Associates performing NEPA compliance activities. (((TURN OVER TO BHI))) 12/12/2012 11

  12. HJC Improvements Project • Conceptual Design (Option 1) – Trapezoidal Outlet Channel Option • Plan view of new trapezoidal outlet channel • Profile view of new trapezoidal outlet channel 12/12/2012 12

  13. HJC Improvements Project Trapezoidal Channel Plan View 12/12/2012 13

  14. HJC Improvements Project Trapezoidal Channel Profile View 12/12/2012 14

  15. HJC Improvements Project • Conceptual Design (Option 2) – Concrete Box Culvert (CBC) Option • Plan and profile for new box culvert • Traffic Control/Detour 12/12/2012 15

  16. HJC Improvements Project CBC Option Plan and Profile 12/12/2012 16

  17. HJC Improvements Project Traffic Control/Detour 12/12/2012 17

  18. HJC Improvements Project • Common Project Components – Sediment removal pond & 3’ sill removal – Sediment disposal site – Sediment disposal haul routes • Option #1: Truck haul route (MRGCD levee road) • Option #2: Truck / conveyor haul route (HJC) • Summary Evaluation of conceptual designs 12/12/2012 18

  19. HJC Improvements Project Sediment removal pond/3’ sill removal 12/12/2012 19

  20. HJC Improvements Project Sediment disposal site 12/12/2012 20

  21. HJC Improvements Project Sediment Disposal Haul Route 12/12/2012 21

  22. HJC Improvements Project Summary Evaluation of Conceptual Designs Trapezoidal Outlet Channel • – Higher cost – Provides higher increased hydraulic capacity vs. CBC option – No traffic detouring required – Provides positive slope in channel downstream of Corrales Rd. • More efficiently prevents sediment buildup at Corrales Bridge CBC Option: • – Least cost method – Increases capacity at bridge – Requires traffic detour during construction 12/12/2012 22

  23. HJC Improvements Project • Environmental Process – National Environmental Policy Act (NEPA) – Federal funds / FHWA lead agency – Categorical Exclusion – Tribal Coordination – Public Involvement 12/12/2012 23

  24. National Environmental Policy Act Public Environmental Community Involvement Justice Cohesion Endangered Land Use Species Visual Impacts Air Quality NEPA PROCESS Noise Wetland Wetlands s Economic Development Cultural Resources Access Multimodal 12/12/2012 24

  25. HJC Improvements Project • Biological Survey – No Threatened & Endangered Species – Habitat Protection • Restrict construction season • Prevent project-related sediment in waterway • Cultural Resource Survey – No impact • Water Resources – Jurisdictional Waterway • USACE Permit 12/12/2012 25

  26. HJC Improvements Project • Project Outreach – Kick off Meeting • Village of Corrales – October 30, 2012 – Agency Meeting • Held at SSCAFCA – November 27, 2012 – Public Involvement Meeting • Village of Corrales – December 12, 2012 12/12/2012 26

  27. HJC Improvements Project • Proposed Project Schedule – Public Involvement Meeting: December 12, 2012 – Final Design Analysis Report: January 2013 – Design: Jan – Mar, 2013 – Environmental Process: now – May, 2013 – NMDOT Certifications: Jan – May, 2013 – Final PSE deadline for NMDOT funds: August 15, 2013 – Construction: Oct. 2013-Jan, 2014 12/12/2012 27

  28. HJC Improvements Project Public Input Comments Received Until December 27th • Speak tonight • Fill out comment sheet • Email/Call – Denise Weston (BHI) 923-3321/dweston@bhinc.com 12/12/2012 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.