Harvey Jones Channel (HJC) Improvements Public Meeting December 12, 2012 PLEASE SIGN IN 12/12/2012 1 HJC Improvements Project Welcome / Introductions: SSCAFCA Staff Dave Gatterman, P.E., Project Manager Chuck Thomas, P.E.,


slide-1
SLIDE 1

Harvey Jones Channel (HJC) Improvements

Public Meeting December 12, 2012 PLEASE SIGN IN

12/12/2012 1

slide-2
SLIDE 2

HJC Improvements Project

  • Welcome / Introductions:

– SSCAFCA Staff

  • Dave Gatterman, P.E., Project Manager
  • Chuck Thomas, P.E., Executive Engineer

– Bohannan Huston, Inc. (BHI) Staff

  • Howard Stone, P.E., Principal
  • Scott Armstrong, P.E., Project Manager
  • Denise Weston, Project Planner
  • Marron and Associates, Environmental Consultant

– VOC Mayor and Council members

12/12/2012 2

slide-3
SLIDE 3

HJC Improvements Project

  • Setting

– The HJC is the bottom of the Montoyas Arroyo Watershed Park

12/12/2012 3

slide-4
SLIDE 4

HJC Improvements Project

  • Montoyas Watershed Park statistics

– Two major arroyos, Montoyas and Lomitas Negras – Runs thru unincorporated Sandoval County, the City of Rio Rancho, and the Village of Corrales – Watershed area is ~ 60 square miles – Approximately 75% of this watershed park is undeveloped

12/12/2012 4

slide-5
SLIDE 5

HJC Improvements Project

  • Where exactly is the project?

Sandia Pueblo City of Rio Rancho Village of Corrales Harvey Jones Channel NM448 Project Location

12/12/2012 5

slide-6
SLIDE 6

HJC Improvements Project

  • Why are we proposing this project?

– 2006 – 2010

12/12/2012 6

slide-7
SLIDE 7

HJC Improvements Project

  • Project Objectives / Goals

– Hydraulic considerations

  • Increase capacity under NM448 (Corrales Rd.)
  • Move hydraulic jump downstream of bridge

– Sediment from upstream reduces hydraulic capacity during storm event

  • Minimize sediment deposition under bridge

– This project is part one of a three part fix

  • SSCAFCA is seeking funding for parts two and three

12/12/2012 7

slide-8
SLIDE 8

Companion projects

Future Sediment Pond Future Sediment Pond

12/12/2012 8

slide-9
SLIDE 9

HJC Improvements Project

  • Project Constraints

– Maintain current grade on Corrales Rd.

  • Avoid raising current road profile

– Improvements contained in public ROW

  • Avoid ROW takes

12/12/2012 9

slide-10
SLIDE 10

HJC Improvements Project

  • Funding

– NMDOT Funds (from FHWA) – State Legislative Appropriation – Funds are secured for project completion – Total funding available from non-SSCAFCA sources ~$950K

  • Any additional funding would need to be supplied using

SSCAFCA sources, with Board approval

12/12/2012 10

slide-11
SLIDE 11

HJC Improvements Project

  • Status

– BHI has completed the draft Design Analysis Report (DAR) for SSCAFCA review – BHI/Marron and Associates performing NEPA compliance activities.

(((TURN OVER TO BHI)))

12/12/2012 11

slide-12
SLIDE 12

HJC Improvements Project

  • Conceptual Design (Option 1)

– Trapezoidal Outlet Channel Option

  • Plan view of new trapezoidal outlet channel
  • Profile view of new trapezoidal outlet channel

12/12/2012 12

slide-13
SLIDE 13

HJC Improvements Project

Trapezoidal Channel Plan View

12/12/2012 13

slide-14
SLIDE 14

HJC Improvements Project

Trapezoidal Channel Profile View

12/12/2012 14

slide-15
SLIDE 15

HJC Improvements Project

  • Conceptual Design (Option 2)

– Concrete Box Culvert (CBC) Option

  • Plan and profile for new box culvert
  • Traffic Control/Detour

12/12/2012 15

slide-16
SLIDE 16

HJC Improvements Project

CBC Option Plan and Profile

12/12/2012 16

slide-17
SLIDE 17

HJC Improvements Project

Traffic Control/Detour

12/12/2012 17

slide-18
SLIDE 18

HJC Improvements Project

  • Common Project Components

– Sediment removal pond & 3’ sill removal – Sediment disposal site – Sediment disposal haul routes

  • Option #1: Truck haul route (MRGCD levee road)
  • Option #2: Truck / conveyor haul route (HJC)
  • Summary Evaluation of conceptual designs

12/12/2012 18

slide-19
SLIDE 19

HJC Improvements Project

Sediment removal pond/3’ sill removal

12/12/2012 19

slide-20
SLIDE 20

HJC Improvements Project

Sediment disposal site

12/12/2012 20

slide-21
SLIDE 21

HJC Improvements Project

Sediment Disposal Haul Route

12/12/2012 21

slide-22
SLIDE 22

HJC Improvements Project

Summary Evaluation of Conceptual Designs

  • Trapezoidal Outlet Channel

– Higher cost – Provides higher increased hydraulic capacity vs. CBC option – No traffic detouring required – Provides positive slope in channel downstream of Corrales Rd.

  • More efficiently prevents sediment buildup at Corrales Bridge
  • CBC Option:

– Least cost method – Increases capacity at bridge – Requires traffic detour during construction

12/12/2012 22

slide-23
SLIDE 23

HJC Improvements Project

  • Environmental Process

– National Environmental Policy Act (NEPA) – Federal funds / FHWA lead agency – Categorical Exclusion – Tribal Coordination – Public Involvement

12/12/2012 23

slide-24
SLIDE 24

National Environmental Policy Act

NEPA PROCESS

Visual Impacts

Noise

Cultural Resources

Wetland s Air Quality

Community Cohesion Public Involvement Endangered Species

Wetlands

Environmental Justice

Land Use

Economic Development Multimodal Access

12/12/2012 24

slide-25
SLIDE 25

HJC Improvements Project

  • Biological Survey

– No Threatened & Endangered Species – Habitat Protection

  • Restrict construction season
  • Prevent project-related sediment in waterway
  • Cultural Resource Survey

– No impact

  • Water Resources

– Jurisdictional Waterway

  • USACE Permit

12/12/2012 25

slide-26
SLIDE 26

HJC Improvements Project

  • Project Outreach

– Kick off Meeting

  • Village of Corrales – October 30, 2012

– Agency Meeting

  • Held at SSCAFCA – November 27, 2012

– Public Involvement Meeting

  • Village of Corrales – December 12, 2012

12/12/2012 26

slide-27
SLIDE 27

HJC Improvements Project

  • Proposed Project Schedule

– Public Involvement Meeting: December 12, 2012 – Final Design Analysis Report: January 2013 – Design: Jan – Mar, 2013 – Environmental Process: now – May, 2013 – NMDOT Certifications: Jan – May, 2013 – Final PSE deadline for NMDOT funds: August 15, 2013 – Construction:

  • Oct. 2013-Jan, 2014

12/12/2012 27

slide-28
SLIDE 28

HJC Improvements Project

Public Input

Comments Received Until December 27th

  • Speak tonight
  • Fill out comment sheet
  • Email/Call

– Denise Weston (BHI) 923-3321/dweston@bhinc.com