HAMISH WESTWATER PROJECTS GROUP MANAGER INTRODUCTION / AGENDA - - PowerPoint PPT Presentation
HAMISH WESTWATER PROJECTS GROUP MANAGER INTRODUCTION / AGENDA - - PowerPoint PPT Presentation
HAMISH WESTWATER PROJECTS GROUP MANAGER INTRODUCTION / AGENDA Introduction 1. Beryl Hub / Garten Opportunity 2. The Leadership Challenge 3. Critical Success Factors 4. Culture & Leadership Setting the Expectation Early
1.
Introduction
2.
Beryl Hub / Garten Opportunity
3.
The Leadership Challenge
4.
Critical Success Factors
Culture & Leadership – Setting the Expectation
Early Stakeholder Engagement – Challenging the Norm
Fit for Purpose Design / Collaboration
5.
Meeting The Challenge - Accelerated Schedule
6.
Delivering The Scope - Facilities
7.
Final Outcome – Key Lessons Learned
INTRODUCTION / AGENDA
2
Beryl area lies in the UK North Sea
around 200 miles NE of Aberdeen in blocks 9/13, 9/18 & 9/19
Beryl First Production in 1976 Acquired by Apache 2011 In excess of 230 Development Wells (47
subsea wells) in total
Garten (6km SE of Beryl A) Discovery Well - March 18 First Production – Nov 18
BERYL HUB / GARTEN FIELD
3
Beryl Bravo Beryl Alpha Nevis Ness Buckland Storr Callater Garten Skene
GARTEN PROJECT – THE CHALLENGE
4
Pre-Drill, Garten Schedule was to deliver First Production end Q1 2019 However, significantly better than expected wellbore logs brought around a
challenge to accelerate production into Q4 2018 and maximise value to Apache Culture & Leadership
Set clear expectations Facilitate approvals Empower the team
Challenge The Norm
Identify critical path Challenge history Ask what can be done to accelerate
Early Stakeholder Engagement
Identify Stakeholders that can influence schedule Explain Challenge and work together to deliver
Fit For Purpose Design / Collaboration
Utilise existing design Don’t optimise the unknown Trust the Supply Chain
GARTEN PROJECT – CRITICAL SUCCESS FACTORS
5
Culture & Leadership – Setting the Expectation
Clear Leadership and expectations communicated from the Management Team All in-house Functions co-located and empowered to act – Apache Core Values Operations and Projects working closely together to deliver change – Operational Excellence
Working Managers Decisive, Invested and Committed Fire in the Belly
Sees the Big Picture and Translates into Action
Best Answer Wins
Communicates Effectively
GARTEN PROJECT – CRITICAL SUCCESS FACTORS
6
Early Stakeholder Engagement – Challenge the Norm
Review of the Critical Path identified many Stakeholder activities out with
Apache’s direct control but within our sphere of influence:
Commercial CTIA Commercial TPOSA FDP/ES Submission & Approval PWA Approvals Safety Case Update
By engaging early and challenging the norm with the Regulatory Bodies and
- ur Partners, we successfully changed timelines and ways of working to
accelerate all critical path approvals:
Commercial CTIA Commercial TPOSA FDP/ES Submission & Approval PWA Approvals Safety Case Update
All negotiated and approved in < 8 months Setting a new benchmark (In many cases, Approval times vastly accelerated)
GARTEN PROJECT – CRITICAL SUCCESS FACTORS
7
Fit For Purpose Design - Collaboration
Tried, Tested and Trusted Supply Chain - Utilising in place Service Agreements Exploit trusted relationships and Asset knowledge (Existing proven design) Maximise responsiveness and reactiveness
Highly Optimised schedule prepared including multiple parallel
scopes and approvals
MEETING THE CHALLENGE - ACCELERATED SCHEDULE
8
ACTIVITY Garten Development
Appraise CP2 Topsides & Subsea FEED Complete CP3 Post Drill Basis of Design Issue Drilling and Completion Commercial CTIA Commerical TPOSA FDP/ES Submission FDP/ES Approval PWA Approvals Detailed Eng & Des Proc & Fab [inc. Long Leads] Topsides Construction CP4 Subsea Installation CP4 Commissioning & Start-Up CP5 First Oil Project Close Out
2017 2019
Q1 Q4 Q2
2018
Q1 Q3 Q4
Milestone
DELIVERING THE SCOPE - FACILITIES
9
FINAL OUTCOME / LESSONS LEARNED
10
Outcome:
Discovery to First Production in < 8 months
3 zone smart completion
Subsea well tied back through Buckland bundle (utilising existing infrastructure)
Production re-routed from A6 to E4 riser (utilising existing infrastructure)
Topsides designed to deliver minimum 15mbd with potential upside of 25mbd via twin flowlines to existing platform infrastructure
Project future proofed for future production wells and water injection once reservoir characteristics known and fully understood
Key Lessons:
Possible to Maximise Value by accelerating production Historical Norms (internal and external) can be challenged and improved Design to the P50 case and where possible use existing infrastructure and
standardise where possible
Put Trust in your team and Trust the Supply Chain