8/6/13 Ground Improvement by Compaction Grouting cigmat.cive.uh.edu/content/cigmina98/report05.html 1/4
Ground Improvement by Compaction Grouting
Samson W. Bandimere
Project Overview Project location: Century Freeway, Los Angeles, California. Construction period: August, 1996 - August, 1997 Owner: California Department of Transportation (CalTrans). Engineer: CalTrans. General contractor: Denver Grouting Services, Inc. Scope of work: Approximately 6500 cy compaction grouting Contract value: $7,700,000
Background In March of 1995, major sinkholes occurred along a new 4 mile section of the I-105 freeway between the San Gabriel and Los Angeles Rivers in Los Angeles, CA. The sinkholes were attributed to infiltration of soil into the storm-drain system through insufficiently sealed pipe joints. This worsening situation represented a major safety hazard to high-speed traffic and heavily loaded trucks. CalTrans issued a multi-phased contract to Denver Grouting Services, Inc. (DGS) to: (1) stabilize the sub-soils and fill voids along alignments of Corrugated Metal (CMP) and Reinforced Concrete (RCP) storm-drain pipes beneath the freeway pavement, (2) repair leaking pipe joints, (3) mitigate liquefaction-potential along the pipe alignment under one of the pump-station structures, and (5) install water and observation wells for subsequent ground water draw-down testing. This freeway was built 40 ft. below surrounding ground levels, which required a major water-pumping system to be installed at the time of construction (1993). The drain pipes were installed 15 to 20 ft. below the highway slab level, which meant the drain pipes were actually 60 ft. below the original ground level. The groundwater table was less than 5 ft. below the freeway pavement in some areas. Solution
Compaction Grouting was the method chosen to stabilize the soils surrounding 14,460 l.f. of RCP and CMP storm drains, and to densify liquefiable sands beneath one of the pump
- structures. Storm-drain sizes included 24, 30, 36, 42, 48, and 54-inch diameters.