- Dr. Christina M. Kishimoto
Gilbert Classical Academy Permanent Location Options December 1, - - PowerPoint PPT Presentation
Gilbert Classical Academy Permanent Location Options December 1, - - PowerPoint PPT Presentation
Gilbert Classical Academy Permanent Location Options December 1, 2015 Dr. Christina M. Kishimoto Superintendent Committee Alex Nardone, Chief of Staff, Chair of Stan Peterson, Director of Facilities Committee Charles Santa-Cruz,
Committee
2
■ Alex Nardone, Chief of Staff, Chair of Committee ■ Ann Anderlohr, Parent at GCA ■ Jason Delfing, Teacher at GCA ■ Teddy Dumlao,Director of Finance ■ Dan Hood, Principal at GCA ■ Brian Jaeger, Executive Director of Secondary Schools ■ Stan Peterson, Director of Facilities ■ Charles Santa-Cruz, Governing Board ■ Steve Smith, Executive Director of Technology ■ Missy Udall, Director of Talent Management ■ Tom Wohlleber, Chief Financial Officer ■ Paul Holland, Architect
■ Overview: Dr. Kishimoto ■ Educational Design: Mr. Hood ■ Cost and Space Variables: Dr. Kishimoto ■ Financial Projections: Mr. Holland ■ Options: Dr. Nardone ■ Questions ■ Next Steps, Key Assumptions: Dr. Kishimoto
Agenda
3
2015-16 Governing Board Goals
4
1. Establish a district-level Academic Data Dashboard. 2. Utilize the 2014-15 Demographic Study to identify enrollment priorities. 3. Identify a permanent location for Gilbert Classical Academy and finalize a comprehensive plan to support full implementation of the the school design.
GCA Educational Design
5
GCA Priority Space Needs
6
GCA is approx. 45,000 sq.ft; needs 91,000 sq.ft.
■ Science Labs and Adequate Size Classrooms ■ Library ■ Cafeteria ■ Gymnasium and Athletic Fields ■ Parking ■ Adequate Restrooms for Students and Faculty
Option 1: Stay in Current Location
7
Meets Educational Design: NO Cost: None Timeline: None
Option 2: Renovate Current Location
8
Meets Educational Design: NO Cost: $3-5M Timeline: 3-6 months
Option 3a: Renovate and Expand Keep Data Center
9
Meets Educational Design: NO Cost: $15-18M Timeline: 12 months
Option 3b: Renovate and Expand Relocate Data Center
10
Meets Educational Design: YES Cost: $20-25M Timeline: 12 months
Option 3c: Replace All GCA Buildings with New 3-Story Construction
11
Meets Educational Design: YES Cost: $25-30M Timeline: 24 months
Option 4a: Repurpose and Supplement an Existing Elementary School
12
Meets Educational Design: YES Cost: $15-20M Timeline: 12 months
Option 4b: Repurpose Existing Junior High School
13
Meets Educational Design: YES Cost: $500K Timeline: 12 months
Option 5: Relocate GCA to an Existing Junior High or High School and Develop a “School within a School” Model
14
Meets Educational Design: YES Cost: $2-5M Timeline: 12 months
Option 6: Lease or Purchase an Existing Building and Renovate
15
Meets Educational Design: YES Cost: TBD by property identified Timeline: 6-12 months
Option 7a: Build New on Desert Ridge High School Campus
16
Meets Educational Design: YES Cost: $25-30M Timeline: 18 months
Option 7b: Build New Adjacent to Desert Ridge High School
17
Meets Educational Design: YES Cost: $30-32M Timeline: 24 months
Option 8: Build New at Morrison Ranch Site
18
Meets Educational Design: YES Cost: $25-30M Timeline: 24 months
Option 9: Convert GCA to a Program in All High Schools
19
Meets Educational Design: NO
20
Option 10: Partner with a Charter School
Meets Educational Design: Not Known
21
Option 11a: Split the GCA Population East/West
Meets Educational Design: NO
22
Option 11b: Split the GCA Population Junior High/Senior High
Meets Educational Design: NO
23