Truckee River Flood Management Authority { FY2015 Budget Development For Discussion Forecast for the close of FY14 Operations Assumptions and Projections for FY15 Cash Flow through FY19 TRFMAs FY14 Year End Financial Position {


slide-1
SLIDE 1

{

Truckee River Flood Management Authority

FY2015 Budget Development

slide-2
SLIDE 2

 Forecast for the close of FY14 Operations  Assumptions and Projections for FY15  Cash Flow through FY19

For Discussion

slide-3
SLIDE 3

{

Bottom Line Forecast

TRFMA’s FY14 Year End Financial Position

slide-4
SLIDE 4

FY14 Ending Fund Balance

  • Budgeted $ 6,052,300
  • Projected $11,971,414
  • Difference due to:
  • Transfers Out to Capital Projects Fund
  • Fewer professional services used
  • Higher than expected revenues

General Fund

slide-5
SLIDE 5

FY14 Ending Fund Balance

  • Budgeted $ 73,900
  • Projected $156,877
  • Difference - much rolled to FY15
  • Transfers In from General Fund
  • NTD construction
  • Demolition project

Capital Projects Fund

slide-6
SLIDE 6

{

Budget Preview

TRFMA’s Financial Outlook for FY15

slide-7
SLIDE 7

Budget Calendar

 April 11 – Tentative Budget to Board  April 15 – File Tentative Budget with State  May 6 – Publish notice of public hearing  May 15 – Public Hearing  June 1 – File Final Budget with State

slide-8
SLIDE 8

The Bottom Line

General Fund 7-1-2014 $11,971,414 Revenue + 5,695,900 Expenses - 5,068,050 Transfer Out - 5,700,000 6-30-2015 $ 6,899,264 Capital Projects Fund 7-1-2014 $ 156,877 Revenue + 10,000 Expenses - 5,835,000 Transfer In + 5,700,000 6-30-2015 $ 31,877

slide-9
SLIDE 9

 Budget FY15 $7,964,300  Budget is up $379,200 from estimated FY14  Forecasting growth at 5%  Washoe County used 4.7% in January forecast

Sales Tax Distributions

slide-10
SLIDE 10

 Expecting to utilize a significant portion of

available cash in FY15

 Using same interest factor as in FY14  Consistent with Washoe County -

forecasting flat growth

Interest Earnings

slide-11
SLIDE 11

Payroll and Benefits

 8 employees  Promotion/reclass included  Within Washoe County estimates  No changes for COLAs or PERS  No change to health insurance premiums

slide-12
SLIDE 12

Professional Services

 Engineering

$1,730,747

  • KimleyHorn, RVA, HDR, Corps

 Flood Funding Study and Rate Hearing $454,199

  • FCS, Public Outreach, Recreation and

Restoration Analysis, Rate Hearing Prep

 Legal and Financial

$233,000

 Flood Warning and Environmental

$75,000

 Unallocated

$250,000

slide-13
SLIDE 13

 Virginia Street Bridge Construction

$3,000,000

 North Truckee Drain Construction

$2,375,000

 Demolitions

$ 450,000

Capital Projects

slide-14
SLIDE 14

 Not much change from FY14 budget  May be adjusted more in next month

Other Expenditures

slide-15
SLIDE 15

 Cash flow for all projects and activities is

positive.

 Presentation in April.

Cash Flow through FY19

slide-16
SLIDE 16

 FY14 ending fund balance > budget  FY15 sales tax distributions > FY14  FY15 capital projects – VSB, NTD, demos  FY15 rate development continues in earnest  FY15 total ending fund balances $6,931,100  5-Year Cash Flow projections are positive

In Summary

slide-17
SLIDE 17

{

?????????????????

Questions