FREDERICKSBURG DISTRICT District Engineer Marcie Parker, P.E. May 8, 2018 3 Interstate 95 Projects Fredericksburg Area Fredericksburg region will see greatest degree of I-95 construction since widening in 1980s 4 Interstate 95 Projects
FREDERICKSBURG DISTRICT
District Engineer Marcie Parker, P.E. May 8, 2018
3
Interstate 95 Projects
Fredericksburg Area Fredericksburg region will see greatest degree
- f I-95 construction
since widening in 1980s
4
Interstate 95 Projects
Fredericksburg Area 7 major I-95 projects finished by 2023:
- Exit 140 Diverging Diamond Interchange and Widening
- I-95 Express Lanes Fredericksburg Extension
- I-95 Rappahannock River Crossing – Southbound and Northbound (2)
- I-95 Safety Improvements at Route 3
- Exit 118 Reconstruction
- I-95 Bridges Rehabilitation
PLUS: New commuter parking, regional road projects and bridge replacements
$1 billion in highway corridor investment
5
6
Calendar Year
2018 2019 2020 2021 2022 2023 2024 Exit 140 – Diverging Diamond Interchange I-95 Express Lanes Fredericksburg Extension “Fred Ex” I-95 Southbound Rappahannock River Crossing I-95 Northbound Rappahannock River Crossing (estimated) Route 3 Safety at Exit 130 Exit 118 Interchange at Thornburg I-95 Bridge Rehabilitation
All new lanes
- pen
to traffic
7
Exit 140 Diverging Diamond Interchange, Stafford County
$185.3 million Widens Courthouse Road to 4 lanes New interchange design reduces conflict points, improves traffic flow Complete July 2020
8
I-95 Express Lanes Fredericksburg Extension (FredEx)
9
- Fully funded by Transurban
- Extends I-95 Express Lanes 10 miles south to Route
17 interchange
- Two reversible lanes – tolled facility
- Connects with I-95 Rappahannock River Crossing
projects
- Replaces American Legion and Truslow Road
- verpasses
- New Express Lanes access at I-95 interchanges at
Route 17, Courthouse Road, and Quantico (Russell Road)
- Construction Spring 2019 - Fall 2022
10
I-95 Southbound Rappahannock River Crossing
- Construction on $125 million project begins August 2018
- Converts 3 existing lanes to local lanes on I-95
southbound
- In the median, 3 thru traffic lanes will be built on I-95
southbound
- New lanes start north of Route 17 interchange in
Stafford and continue south past Route 3 interchange in Fredericksburg/Spotsylvania
- New bridge to be built over the Rappahannock River to
carry thru lanes in the median
- Replaces Route 17 overpasses in Stafford
11
I-95 Southbound Rappahannock River Crossing
12
I-95 Northbound Rappahannock River Crossing
Funding announced January 10, 2018 $132 million budget Adds lane capacity to I-95 northbound between Route 3 and Route 17 Interchange Modification Report (IMR) underway
13
I-95 Safety Improvements at Route 3
$21 million federally- funded safety project Reduces merging and weaving at Exit 130 and Route 3 interchange Triple right turn lanes to Route 3 westbound, controlled by signal New free-flow lane to Central Park tracking to open in June 2018
14
I-95 Safety Improvements at Route 3
Triple left turn lanes
- n Route 3 eastbound
to I-95 NB New signal at I-95 northbound ramp entrance Current cloverleaf ramp will close Project completion by January 2019
15
Exit 118 Overpass and Interchange Improvements
New 4-lane overpass improves sight distance on Mudd Tavern Road Replaces structurally deficient bridge Improves interchange ramp configuration Aligns with SMART SCALE widening, access management project to west Completion of $22.4 million project by September 2019
16
Maryland Transportation Authority (MDTA)
- wned, operated
Type: Design-Build Procurement Project Budget: $765 million Request for Qualifications: October 2018 Request for Proposals: March 2019 Virginia Commitment: $13 million
Governor Harry W. Nice Bridge Replacement
17
Route 301 and Route 207 Corridor
Arterial Management Plan
18
- 42-mile corridor
- Potomac River in King George County to
Route 1 in Caroline County
- Prepare for heavier traffic anticipated with opening
- f new, expanded Nice Bridge
- Alternative to Interstate 95
- Set expectations for future economic development
- Reduces need for retrofit projects
- Recommends access, intersection and crossover
improvements
- Final report in June 2018
Chatham Bridge Rehabilitation Project
City of Fredericksburg, Stafford County $22 million Improves bridge condition by replacing superstructure Adds 10 ft. wide shared use path separated from traffic by barrier Two travel lanes in each direction – 10 ft. wide Construction begins early 2021 Bridge will be closed during construction
19
Virginia Department of Transportation
Chatham Bridge Rehabilitation Project
20
Virginia Department of Transportation
Chatham Bridge Rehabilitation Project: Detour Map
21
- Route 1 and Telegraph Road/Woodstock Lane
- Route 1 and Courthouse Road
- Route 1 and Potomac Creek Drive
- Route 301 Northbound and Southbound Turn Lanes at Dahlgren
- Courthouse Road and Hood Drive Intersection
- Lafayette Boulevard and Harrison Road
- Ladysmith Road and Partlow Road Safety Improvements
Fredericksburg District Projects
Intersection, Turn Lanes
22
Stafford King George Spotsylvania Caroline
- Route 606 (Mudd Tavern Road) Widening
- Route 639 (Ladysmith Road) Widening
- Virginia Central Railway Bridge
- Twin Lake Drive – Kensington Pedestrian Connector
23
Fredericksburg District Projects
Spotsylvania Caroline
Widening Projects Pedestrian and Trail Projects
City of Fredericksburg
I-95 Southbound Ramp, Route 1
24
Exit 126 Area Improvements
- After construction, there will be 2 right turn lanes from I-95 southbound exit ramp to Route 1 southbound
- Also, 2 right turn lanes from Route 1 southbound to Southpoint Parkway
- Construction advertised June 2021
Route 17 Overpass Replacement, Widening
25
Exit 126 Area Improvements
- Builds new 4-lane overpass
- Widens Route 17 to east of Hospital Boulevard
- Sidewalks
- Project completed fall 2022
26
Route 1 and Commonwealth Drive Park & Ride
- $16.6 million
- Approximately 700 new spaces in
Massaponax area
- Construction advertised in
spring 2020
- Lot opens summer 2021