Franklin County Water District Preliminary Engineering Report (PER) - - PowerPoint PPT Presentation

franklin county water district preliminary engineering
SMART_READER_LITE
LIVE PREVIEW

Franklin County Water District Preliminary Engineering Report (PER) - - PowerPoint PPT Presentation

Franklin County Water District Preliminary Engineering Report (PER) Flood Relief Project Alternatives 3/6/2017 CarolloBlueTemplateWithLogo.pptx D AVID H ARKINS , P.E., P H D. P HIL B ULLOCK , P.E. Carollo delivers national expertise


slide-1
SLIDE 1

CarolloBlueTemplateWithLogo.pptx

Franklin County Water District Preliminary Engineering Report (PER)

Flood Relief Project Alternatives 3/6/2017

DAVID HARKINS, P.E., PHD. PHIL BULLOCK, P.E.

slide-2
SLIDE 2

CarolloBlueTemplateWithLogo.pptx

2

Carollo delivers national expertise specializing ONLY in water and wastewater

slide-3
SLIDE 3

CarolloBlueTemplateWithLogo.pptx

3

EMERGENCY SPILLWAY LCS DAM

LAKE BOB SANDLIN

MORNING GLORY-TYPE SERVICE SPILLWAY 18” LOW FLOW VALVE STRUCTURE

Lake Cypress Springs

slide-4
SLIDE 4

CarolloBlueTemplateWithLogo.pptx

4

Lake Cypress Springs Spillway

slide-5
SLIDE 5

CarolloBlueTemplateWithLogo.pptx

5

December 2015 Event (383.92’)

350-YR Event

Event Elevation 2-year 379.1 5-year 379.5 10-year 379.9 25-year 380.5 50-year 381.3 100-year 382.3 500-year 384.7

slide-6
SLIDE 6

CarolloBlueTemplateWithLogo.pptx

6

Data Gathering for Analysis – Elevations

slide-7
SLIDE 7

CarolloBlueTemplateWithLogo.pptx

7

Data Gathering for Analysis – Elevations

slide-8
SLIDE 8

CarolloBlueTemplateWithLogo.pptx

8

Data Gathering for Analysis – Elevations

10 20 30 40 50 60 70 80 90 380 382 384 386 388 390 392 394 396 398 400 402 404 406 408 410 412 414 416 419 421 425 432 442 Below the Spillway Above the Spillway Above the Dam

Lake Cypress Springs Home Elevation Survey Results

slide-9
SLIDE 9

CarolloBlueTemplateWithLogo.pptx

9

1 3 2 4 5 4 10 11 17 25 29 17 5 10 15 20 25 30 35 380 380.5 381 381.5 382 382.5 383 383.5 384 384.5 385 385.5 Homes Below 385.5'

Count of Homes below 385.5'

Data Gathering for Analysis – Elevations

slide-10
SLIDE 10

CarolloBlueTemplateWithLogo.pptx

10

37 988 200 400 600 800 1000 1200 BELOW ABOVE

Count of Homes for December 2015 Event (383.92')

Data Gathering for Analysis – Elevations

17 Homes with Damage were Reported in the Survey

slide-11
SLIDE 11

CarolloBlueTemplateWithLogo.pptx

11

Data Gathering for Analysis – Online Survey

Costs Total Structural Damage Cost $571,642.00 Average Total Structural Cost $38,169.14 Total Boathouse Damage Cost $303,144.50 Average Boathouse Damage Cost $7,496.16 Total Retaining Wall Damage Cost $64,561.00 Average Retaining Wall Damage Cost $3,397.95 Total Other Damage Cost $460,977.65 Average Other Damage Cost $14,634.57 TOTAL DAMAGE COST ~$1,500,000

slide-12
SLIDE 12

CarolloBlueTemplateWithLogo.pptx

12

Data Gathering for Analysis – Online Survey

36.99% 0.63% 0.62% 2.58% 13.55% 4.61% 8.09% 4.61% 1.60% 26.71%

Percentage of Total Damage Cost

House Guest House Garage Storage Building Boat-house Retaining Wall Deck or Dock Water Pump Vehicles Boats

slide-13
SLIDE 13

CarolloBlueTemplateWithLogo.pptx

13

Data Gathering for Analysis - Samples

slide-14
SLIDE 14

CarolloBlueTemplateWithLogo.pptx

14

Evaluated Alternatives

1. Addition of canal on emergency spillway 2. Addition of box culverts on north end of Lake Cypress Springs Dam (LCS) 3. Add tainter gates to LCS dam (comparable to Lake Bob Sandlin (LBS)) 4. Add pump station at north end of LCS Dam 5. Additional morning glory spillway 6. Operational Alternative

slide-15
SLIDE 15

CarolloBlueTemplateWithLogo.pptx

15

Additional Canal

CANAL SECTION CROSSING SECTION 1,000 FT

slide-16
SLIDE 16

CarolloBlueTemplateWithLogo.pptx

16

Canal Section

NATURAL CANALS CONCRETE LINED CANALS OVERBANK CANALS

slide-17
SLIDE 17

CarolloBlueTemplateWithLogo.pptx

17

Crossing Section

CAST-IN PLACE CULVERTS LOW PROFILE CULVERTS LOW WATER CROSSINGS BRIDGES

slide-18
SLIDE 18

CarolloBlueTemplateWithLogo.pptx

18

Box Culverts

slide-19
SLIDE 19

CarolloBlueTemplateWithLogo.pptx

19

Building a Tainter Gate System

Tainter gates open at Lake Bob Sandlin Tainter gates at Lake Bob Sandlin

slide-20
SLIDE 20

CarolloBlueTemplateWithLogo.pptx

20

Response from the Public

  • 15
  • 10
  • 5

5 10 15 20 25 30 1 2 3 4 5 6

Votes (multiple allowed per person) Structural Alternative (6 = Operational Alternative)

Alternatives Responses (For/Against) from the Public

FOR: AGAINST:

slide-21
SLIDE 21

CarolloBlueTemplateWithLogo.pptx

21

5 Task Hurdles / 3 Sub-Alternatives

Sub-Alternative Identification

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply Sub-Alternatives

Sub-Alternative A Sub-Alternative B Sub-Alternative C 100-Yr Flood Event 350-Yr Flood Event (December 2015 Event) 500-Yr Flood Event Max Water Surface Elevation 381.00 msl Max Water Surface Elevation 381.00 msl Max Water Surface Elevation 381.00 msl

slide-22
SLIDE 22

CarolloBlueTemplateWithLogo.pptx

22

Alternatives Matrix

Alternative Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1A

    

1B

    

1C

    

2A

    

2B

    

2C

    

3A

   * 

3B

   * 

3C

   * 

6A

  

6B

  

6C

  

6D

  

6E

   Legend

Carollo predicts FCWD's ability to hurdle the task is feasible for specific alternative.

*

Carollo predicts FCWD's ability to hurdle the task is feasible, however, cost feasibility and funding

  • ptions will be determined by the FCWD available

funds and policy decisions.

Carollo predicts FCWD would not be able to hurdle the requirements for a specific alternative. Feasibility of accomplishment is deemed low.

slide-23
SLIDE 23

CarolloBlueTemplateWithLogo.pptx

23

Local Agency Approval (All Alternatives)

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply Local Agency Approval (Downstream Stakeholders) is Feasible

Agency Owner Request Approximate Cost Titus County Fresh Water Supply District TCFWSD Lake Bob Sandlin H&H Analysis for Downstream Impacts

~250K

North East Texas Municipal Water District NETMWD Lake of the Pines Water Quality Assessment

~85K

slide-24
SLIDE 24

CarolloBlueTemplateWithLogo.pptx

24

Alternatives Matrix

Alternative Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1A

    

1B

    

1C

    

2A

    

2B

    

2C

    

3A

   * 

3B

   * 

3C

   * 

6A

  

6B

  

6C

  

6D

  

6E

  

slide-25
SLIDE 25

CarolloBlueTemplateWithLogo.pptx

25

Alternatives Matrix

Alternative Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1A

    

1B

    

1C

    

2A

    

2B

    

2C

    

3A

   * 

3B

   * 

3C

   * 

6A

  

6B

  

6C

  

6D

  

6E

  

slide-26
SLIDE 26

CarolloBlueTemplateWithLogo.pptx

26

Additional Canal

CANAL SECTION CROSSING SECTION 1,000 FT

slide-27
SLIDE 27

CarolloBlueTemplateWithLogo.pptx

27

Hydraulic Feasibility

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1 - STRUCTURAL ALTERNATIVES Rain Event Probability Revised Conditions Alternative 1A Alternative 1B Alternative 1C 100-YR 350-YR 500-YR

71 culverts* 203 culverts* 243 culverts*

2-year 0.50000 379.1 378.9 378.8 378.7 5-year 0.20000 379.5 379.2 379.0 379.0 10-year 0.10000 379.9 379.6 379.3 379.2 25-year 0.04000 380.5 379.9 379.6 379.5 50-year 0.02000 381.3 380.5 379.9 379.8 100-year 0.01000 382.3 381.0 380.3 380.1 350-Year 0.00285 384.7 382.1 381.0 380.9 500-Year 0.00200 384.9 382.4 381.3 381.0

* 1 Culvert = 10’ Wide X 4’ Tall Box Pipe

slide-28
SLIDE 28

CarolloBlueTemplateWithLogo.pptx

28

Federal Agency Approval

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

CS1 CS2 CS3 CS4 Alternative 1A Alternative 1B Alternative 1C 100,000 200,000 300,000 400,000 500,000

CFS Capacity (Cross Section) or Discharge (Alternatives) Cross Section Alternative

Capacity of Cross Sections Compared with Maximum Discharge of Alternatives 1A / 1B / 1C

Maximum Area (SF) Available for Discharge

LBS LCS

slide-29
SLIDE 29

CarolloBlueTemplateWithLogo.pptx

29

USACE Permit Process State and Federal Regulation

USACE Permit Agency Comments

USFWS/ TPWD EPA TCEQ Applicant & Adjacent Landowners BOR Special Interest Groups General Public THC Post Offices, News Media TxDOT Congressman State & Local Officials NMFS State & Federal Agencies

  • EPA – U.S. Environmental Protection

Agency

  • USFWS – U.S. Fish and Wildlife

Service

  • TPWD – Texas Parks and Wildlife

Department

  • NMFS – National Marine Fisheries

Services

  • TxDOT – Texas Department of

Transportation

  • HUD – U.S. Department of Housing

and Urban Development

  • BOR – Bureau of Reclamation
  • SHPO – State Historic Preservation

Office

  • TCEQ – Texas Commission on

Environmental Quality

  • TCH – Texas Historical Commission

Communication Started in PER

slide-30
SLIDE 30

CarolloBlueTemplateWithLogo.pptx

30

Cost Feasibility

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

ALTERNATIVE 1 ITEM CATEGORIES 1A 1B 1C Startup and SW3P Items $642,526 $1,788,644 $2,136,139 Canal Items $7,174,574 $20,501,685 $24,540,203 Road Crossing Items $11,295,307 $31,346,107 $37,422,107 Closeout and Other Items $2,570,000 $7,190,000 $8,590,000 Design Fees $3,734,861 $9,225,048 $11,021,624 Contingency 20% $5,083,454 20% $14,010,297 20% $16,742,015

OPCC TOTAL COST $30,501,000 $84,062,000 $100,452,000

slide-31
SLIDE 31

CarolloBlueTemplateWithLogo.pptx

31

Alternatives Matrix

Alternative Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1A

    

1B

    

1C

    

2A

    

2B

    

2C

    

3A

   * 

3B

   * 

3C

   * 

6A

  

6B

  

6C

  

6D

  

6E

  

slide-32
SLIDE 32

CarolloBlueTemplateWithLogo.pptx

32

Box Culverts

slide-33
SLIDE 33

CarolloBlueTemplateWithLogo.pptx

33

Hydraulic Feasibility

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

2 - STRUCTURAL ALTERNATIVES Rain Event Probability Revised Conditions Alternative 2A Alternative 2B Alternative 2C 100-YR 350-YR 500-YR

72 culverts* 204 culverts* 244 culverts*

2-year 0.50000 379.1 378.9 378.8 378.7 5-year 0.20000 379.5 379.2 379.0 379.0 10-year 0.10000 379.9 379.6 379.3 379.2 25-year 0.04000 380.5 379.9 379.6 379.5 50-year 0.02000 381.3 380.5 379.9 379.8 100-year 0.01000 382.3 381.0 380.3 380.1 350-Year 0.00285 384.7 382.1 381.0 380.9 500-Year 0.00200 384.9 382.4 381.3 381.0

* 1 Culvert = 10’ Wide X 10’ Tall Box Pipe

slide-34
SLIDE 34

CarolloBlueTemplateWithLogo.pptx

34

Federal/State Agency Approval

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

  • Threatened and

Endangered Species

  • Jurisdictional Waters

and Adjacent Wetlands

  • Roadway Concerns

(FM3007)

slide-35
SLIDE 35

CarolloBlueTemplateWithLogo.pptx

35

Cost Feasibility

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

ALTERNATIVE 2 ITEM CATEGORIES 2A 2B 2C Startup and SW3P Items $485,259 $1,173,943 $1,381,980 Emergency Spillway Items $349,885 $349,885 $349,885 Dam Crossing Items $12,142,763 $33,366,896 $39,798,452 Closeout and Other Items $3,305,000 $4,625,000 $5,025,000 Design Fees $2,924,936 $5,928,285 $6,984,224 Contingency 20% $3,841,569 20% $9,088,802 20% $10,707,908

OPCC TOTAL COST $23,049,000 $54,533,000 $64,247,000

slide-36
SLIDE 36

CarolloBlueTemplateWithLogo.pptx

36

Alternatives Matrix

Alternative Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1A

    

1B

    

1C

    

2A

    

2B

    

2C

    

3A

   * 

3B

   * 

3C

   * 

6A

  

6B

  

6C

  

6D

  

6E

  

slide-37
SLIDE 37

CarolloBlueTemplateWithLogo.pptx

37

Building a Tainter Gate System

Tainter gates open at Lake Bob Sandlin Tainter gates at Lake Bob Sandlin

slide-38
SLIDE 38

CarolloBlueTemplateWithLogo.pptx

38

Hydraulic Feasibility

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

3 - STRUCTURAL ALTERNATIVES Rain Event Probability Revised Conditions Alternative 3A Alternative 3B Alternative 3C 100-YR 350-YR 500-YR

1 gates 2 gates 3 gates

2-year 0.50000 379.1 378.0 378.0 378.0 5-year 0.20000 379.5 378.0 378.0 378.0 10-year 0.10000 379.9 378.3 378.0 378.0 25-year 0.04000 380.5 378.6 378.0 378.0 50-year 0.02000 381.3 379.1 378.0 378.0 100-year 0.01000 382.3 379.7 378.4 378.0 350-Year 0.00285 384.7 381.1 379.4 378.4 500-Year 0.00200 384.9 381.5 379.6 378.6

slide-39
SLIDE 39

CarolloBlueTemplateWithLogo.pptx

39

Hydraulic Feasibility

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

slide-40
SLIDE 40

CarolloBlueTemplateWithLogo.pptx

40

Cost Feasibility

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

ALTERNATIVE 3 ITEM CATEGORIES 3A 3B 3C Mobilization $120,400 $154,800 $197,800 Structure Costs $14,439,975 $18,973,300 $23,906,625 Closeout and Other Items $2,236,474 $2,938,076 $3,702,440 Design Fees $3,027,027 $3,817,426 $3,702,440 Contingency 20% $3,964,775 20% $5,176,721 20% $6,497,079

OPCC TOTAL COST $23,789,000 $31,060,000 $38,982,000

slide-41
SLIDE 41

CarolloBlueTemplateWithLogo.pptx

41

Alternatives Matrix

Alternative Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1A

    

1B

    

1C

    

2A

    

2B

    

2C

    

3A

   * 

3B

   * 

3C

   * 

6A

  

6B

  

6C

  

6D

  

6E

   Legend

*

Carollo predicts FCWD's ability to hurdle the task is feasible, however, cost feasibility and funding

  • ptions will be determined by the FCWD available

funds and policy decisions.

slide-42
SLIDE 42

CarolloBlueTemplateWithLogo.pptx

42

Operational Alternative

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

slide-43
SLIDE 43

CarolloBlueTemplateWithLogo.pptx

43

Impact to Drinking Water Supply

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

Alternative Conservation Pool Difference in WSE Firm Yield (ac-ft) Difference (ac-ft) Existing 378.0 ft msl

  • 13,943
  • Alternative 6A

377.5 ft msl

  • 0.5 ft

13,597 346 Alternative 6B 377.0 ft msl

  • 1.0 ft

13,251 692 Alternative 6C 376.0 ft msl

  • 2.0 ft

12,560 1,383 Alternative 6D 375.0 ft msl

  • 3.0 ft

11,873 2,070 Alternative 6E 374.0 ft msl

  • 4.0 ft

11,188 2,755

slide-44
SLIDE 44

CarolloBlueTemplateWithLogo.pptx

44

Impact to Drinking Water Supply

Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

slide-45
SLIDE 45

CarolloBlueTemplateWithLogo.pptx

45

FINALIZED Alternatives Matrix

Alternative Task Hurdle Hydraulic Feasibility Federal / State Agency Approval is Feasible Local Agency Approval (Downstream Stakeholders) is Feasible Cost Feasibility Minimal Impact to Water Supply

1A

    

1B

    

1C

    

2A

    

2B

    

2C

    

3A

   * 

3B

   * 

3C

   * 

6A

  

6B

  

6C

  

6D

  

6E

  

slide-46
SLIDE 46

CarolloBlueTemplateWithLogo.pptx

46

Key Board-Decision Elements

Project Cost Storm Frequency (Risk) Property Damages

Total Lake Cypress Springs Damage Curve

37 988 200 400 600 800 1000 1200 BELOW ABOVE

Count of Homes for December 2015 Event (383.92')

slide-47
SLIDE 47

CarolloBlueTemplateWithLogo.pptx

47

Total Lake Cypress Springs Impact Curve

$ M $5 M $10 M $15 M $20 M $25 M $30 M $35 M $40 M DOLLARS OF DAMAGE ($) RESERVOIR WSE (FT)

LCS Impact Curve

House Boathouses and Docks Retaining Walls Waterpumps Vehicles Watercraft

slide-48
SLIDE 48

CarolloBlueTemplateWithLogo.pptx

48

Alternative 3 – Benefit Cost (BC) Ratio

ALTERNATIVE 3 Rain Event Probability Revised Model Conditions 3A 3B 3C 1 gates 2 gates 3 gates

Impacts ($) Impacts ($) Impacts ($) Impacts ($)

CAPITAL COSTS →

  • $23.8 M

$31.1 M $39.0 M 100-year 0.01000 $347,890 $38,402 $19,706 $16,104 350-Year 0.00285 $2,910,117 $120,175 $32,749 $19,706 500-Year 0.00200 $3,495,949 $174,235 $36,353 $21,790 100-YR BC RATIO 1.30% 1.06% 0.85% 350-YR BC-RATIO 11.73%* 9.26% 7.41% 500-YR BC-RATIO 13.96%* 11.14% 8.91%

* It takes over 7+ 500-yr events (or 8.5+ December 2015 Events) to break even on the capital investment of the 1-gate project

slide-49
SLIDE 49

CarolloBlueTemplateWithLogo.pptx

49

Completed Technical Memorandums (TMs)

  • TM#1 –Retaining Walls, Dredge, and Fill
  • TM#2 –Boat Houses
  • TM#3 –Lake Closure
  • TM#4 –FEMA Coordination
  • TM#5 –Residential Structures
slide-50
SLIDE 50

CarolloBlueTemplateWithLogo.pptx

50

Boat Lift Changes to Rules and Regulations

slide-51
SLIDE 51

CarolloBlueTemplateWithLogo.pptx

51

TM#4 – FEMA Coordination

  • Currently the County Judge is designated as the floodplain

administrator (FPA) by court order, meaning that it is the County's responsibility to enforce FEMA policy in the county.

Example Flood Insurance Requirement

  • County is participating in the National

Flood Insurance Program (NFIP).

  • The County has never been mapped,

but did enter the NFIP on 07/28/2000. FEMA mapping is scheduled to be completed at some unknown date in the future.

  • With mapping will come additional

regulations and mandates for construction in the floodplain/floodway. It also mandates flood insurance requirements.

slide-52
SLIDE 52

CarolloBlueTemplateWithLogo.pptx

52

Next Steps

YES YES Choose to proceed with Structural Alternative 3 Choose a series of Ancillary Alternatives

Impacts Assessments & Permitting Ancillary Option Analysis

Next Steps for the District?

H&H Analysis Water Quality Assessment Environmental Permitting FEMA Coordination Modification FCWD R&R Lake Closures Funding Strategies Implementation Design Construction

Proceed with Both Structural Alternative 3 and Ancillary Alternatives

$250K

$85K $148K ~ Cost

Cost Already Incurred by FCWD

~ Cost

slide-53
SLIDE 53

CarolloBlueTemplateWithLogo.pptx

53

Emergency Spillway Elevation Comparison

slide-54
SLIDE 54

CarolloBlueTemplateWithLogo.pptx

54

LCS Emergency Spillway Cross Section

slide-55
SLIDE 55

CarolloBlueTemplateWithLogo.pptx

55

Emergency Spillway Restoration Possibility

Fill Spoils Deposit Area Restoration by Excavation

Additional H&H Analysis Required to Determine Feasibility

slide-56
SLIDE 56

CarolloBlueTemplateWithLogo.pptx

56

Emergency Spillway Evaluation

Alternative

Task Hurdle

Hydraulic Feasibility Federal / State Agency Approval is Feasible Cost Feasibility Do-Nothing

 -  - *  -  - *  -  - *

Return Emergency Spillway to Design

 -  - *  -  - *  -  - *

Evaluation of Alternative Restoration

 -  - *  -  - *  -  - *

slide-57
SLIDE 57

CarolloBlueTemplateWithLogo.pptx

57

Questions