flexibility for markets and grids
play

FLEXIBILITY FOR MARKETS AND GRIDS Economic and Technical Evaluation - PowerPoint PPT Presentation

FLEXIBILITY FOR MARKETS AND GRIDS Economic and Technical Evaluation of the hybrid-VPP Concept T. Esterl, AIT Austrian Institute of Technology C. Gutschi, cyberGRID IAEE 2017, Vienna, 5. September 2016 HYBRID-VPP CONCEPT Distribution grid Market


  1. FLEXIBILITY FOR MARKETS AND GRIDS Economic and Technical Evaluation of the hybrid-VPP Concept T. Esterl, AIT Austrian Institute of Technology C. Gutschi, cyberGRID IAEE 2017, Vienna, 5. September 2016

  2. HYBRID-VPP CONCEPT Distribution grid Market Flexibility 05/09/2017 2

  3. AGENDA 1. Project overview 2. Use case description 3. Use case Market & Customer 4. Use Case Market & DSO support 5. Analysis of regulatory framework 6. Conclusions of hybrid-VPP concept 7. Outlook: InteGrid project 05/09/2017 3

  4. INTRODUCTION TO HYBRID-VPP4DSO Hybrid operation of a VPP • hybridVPP: Market participation and support of the distribution grid • Focus on provision of ancillary services to the TSO by resources located inside distribution grids with significant restrictions Simulation and Proof-of-concept of hybrid-VPP concept • in two distribution grid sections in Austria and Slovenia • grid sections with diverse characteristics (urban/rural, feed-in from windpower/PV/hydropower vs. flexible loads, different topologies, etc.) Consortium AIT (Lead, research), cyberGRID (IT, market analysis), Energienetze Steiermark (DSO), Energie Steiermark (Trader), Elektro Ljubljana (DSO), Elektro Energia (Trader), Grazer Energieagentur (Consulting), TU Wien (research), Energetic Solutions (Consulting) Duration: 04/2014 – 06/2017 05/09/2017 4

  5. HYBRID-VPP CONCEPT Noncritical: VPP operation P ↕ permitted Semi-critical: only P ↓ permitted Critical: P ↓ required by DSO Semi-critical: only P ↑ permitted Critical: P ↑ required by DSO Highly critical: VPP operation prohibited MV grid HV connection to neighboring HV grid Transformer to transmission grid HV grid 05/09/2017 5

  6. OVERVIEW OF USE CASES FOR FLEXIBILITY • (1a) Participation in flexibility markets • (1b) Participation in flexibility markets with restrictions from distribution grid Market • (1c) Cost minimization of supply from energy only markets (day ahead, intraday) • (2a) Minimization of grid connection costs for new generators Customer • (2b) Minimization of grid connection costs for new consumers • (3a) Optimization of grid investments of DSO Grid • (3b) DSO-Support during maintenance and special switching states in case of a (DSO) quality regulation scheme 05/09/2017 6

  7. USE CASE “MARKET & CUSTOMER” Participation of VPP on the Tertiary Balancing Market and Minimization of grid connection costs for new generators in parallel New customer (wind park) applies for connection to the grid at an under-dimensioned connection point. Classic approach: Customer needs to invest into a new line to the closest feasible connection point or bear costs of grid reinforcement. Hybrid-VPP approach: • Customer agrees to be curtailed during critical hours  Cost savings due to lower grid connection costs  Additional benefits of participation in the balancing market 05/09/2017 7

  8. ECONOMIC EVALUATION OF VPP OPERATION 600 000 Business Case of VPP: Total net revenues, 40% shared with customer VPP revenues & costs, cumm. 1a [EUR] Total net revenues, 50% shared with customer • CAPEX and OPEX for VPP basically 500 000 Total net revenues, 60% shared with customer depending on capacity of customers and on VPP costs (CAPEX+OPEX), 0,2 MW/customer availability of 24/7 control room 400 000 VPP costs (CAPEX+OPEX), 1 MW/customer • Revenues from market participation are VPP costs (CAPEX+OPEX), 5 MW/customer difficult to predict (high volatility) 300 000  Positive Business Cases feasible in tertiary 200 000 balancing market (AT, SI; 2015) 100 000 Business Case of hybrid-VPP: • Additional costs for interface with DSO 0 • Additional benefits from customer use case 0 2 4 6 8 10 12 14 16 18 20 Capacity of controlled customers [MW] • Difficult regulation for remuneration of grid- supporting flexibility • Mainly non-financial drivers (customer access) 05/09/2017 8

  9. ECONOMIC EVALUATION OF CUSTOMER USE CASE Economic evaluation from customers’ € 2 500 000 Avoided investment perspective: Reduced revenues from feed-in (NPV) VPP service fee (NPV) € 2 000 000 • Customers agree to curtail their feed-in or Net savings consumption on demand of the DSO during critical hours. Use case is strongly dependent € 1 500 000 on grid topology and value of curtailed feed-in (or consumption). € 1 000 000 • Simulations showed a duration of required curtailment of maximum 300 h/a . € 500 000 • Substantial savings are possible especially for new generators. € 0 • In our case study for an industrial customer the costs of shifted load should not exceed Wind park A Wind park B Wind park C 42 €/MWh to be economically feasible (also highly dependent on grid typology, etc.). 05/09/2017 9

  10. USE CASE “MARKET & DSO” (A) Optimization of DSO’s grid investments & Participation in Tertiary Balancing Market Over voltage issues in winter due to market participation of VPP Under voltage issue in summer due to delayed grid investments hybrid-VPP min voltage in the grid  Issues caused by ancillary service max voltage in the grid provision being avoided  All voltage issues could be solved by applying the traffic light system 05/09/2017 10

  11. USE CASE “MARKET & DSO” (B) Supporting of DSO during maintenance and special switching states + Participation in Tertiary Balancing Market hybrid-VPP supports the DSO by reducing voltage problems during special switching states and thus preventing tripping of customers. hybrid-VPP  During non-critical hours, all units of the hybrid-VPP can participate in the balancing market. 05/09/2017 11

  12. REGULATORY ANALYSIS OF USE CASES • No regulatory issues for pure market partcipation Market • Minimization of grid connection costs: General connection requirement Customer • Benefit for network users possible, but no legal claim • Optimization of grid investment costs: Highly reliable network infrastructure in Austria, Grid Short-term benefits of hybrid-VPP for deferral of grid investments (DSO) • Maintenance and special switching states: exceptional grid state Quality regulation scheme would create incentives for hybrid-VPP 05/09/2017 12

  13. POSSIBLE COORDINATION SCHEMES Does the DSO operate the grid on its own? No Yes The DSO outsourced Does the DSO have sufficient the network operation information about flexibilities? No Yes Does the DSO procure the Model Service The DSO has to tender needed flexibility on the market? the required flexibility . Provider (?) No Yes Model Single The DSO operates the Model Market (?) Aggregator control infrastructure. Can the flexibility operator choose its marketer? Yes No Model Model Flexibility DSO (?) 05/09/2017 13

  14. CONCLUSIONS • Support of DSOs in parallel to active participation on a national market for tertiary control feasible • Recommendation of diverse pool with units in different locations and include demand side management as well as different types of (renewable) generators (Applicability of hybrid-VPP depends on grid topology and connection points, capacity and type of available flexibilities) • Added value of a hybrid-VPP is related to multitude of different use cases using the same hybrid- VPP platform (as for example reduction of investment costs for new users who connect to the grid as well as prevention/deferral of grid investments of DSOs) • Regulatory barriers for the integration of the hybrid-VPP for the remuneration of grid-supporting flexibility operation and for the definition of the connection point • Two promising solutions for the configuration of hybrid-VPP operator: i) aggregator as hybrid-VPP- operator and ii) DSO as market facilitator This work was funded by the Austrian Research Funding Association (FFG) under the scope of the e!mission program. 05/09/2017 14

  15. OUTLOOK: H2020 PROJECT INTEGRID Overview of the InteGrid project • Traffic Light System as investigated in hybrid-VPP4DSO will be further developed in the InteGrid project. • InteGrid aims at demonstrating how DSOs can enable different stakeholders to actively participate in the energy market, by testing and validating solutions in an integrated environment . Among these tools, the Traffic Light System will be refined in order to comply with multiple markets designs and to reach a higher Technological Readiness Level. • State of the art forecasting and optimisation algorithms (like multi-period Optimal Power Flow) will be integrated to realize the Traffic Light System as a tool for DSOs. • This concept will be implemented using a Grid and Market Hub platform to simplify communication with DSOs and tested by the DSOs Elektro Ljubljana (SI) and EDP Distribuição (PT) in the scope of Pilots of technical and commercial VPPs. This means a further development of the hybrid-VPP coordination scheme “Flexibility”. • Scalability and Replicability Analysis will be performed for several countries Project Homepage: www.integrid-h2020.eu

  16. MANY THANKS FOR YOUR KIND ATTENTION! 16 05/09/2017

  17. FLEXIBILITY FOR MARKETS AND GRIDS Economic and Technical Evaluation of the hybrid-VPP Concept T. Esterl, AIT Austrian Institute of Technology C. Gutschi, cyberGRID IAEE 2017, Vienna, 5. September 2016

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend